DOMAIN 7: CONSTRUCTION Flashcards

1
Q

What are the three types of schedules used for construction?

A

**Gantt Chart **
Simplest form of schedule that uses a bar chart with tasks listed vertically

Critical Path Method (CPM)
More sophisticated schedule that establishes the shortest path through all activities

Location-Based Scheduling (LBS)
Most sophisticated method that emphasizes
physical locations to plan, analyze, and control workflow

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Who is responsible for construction means and methods according to available standardized general conditions?

A

The contractor is responsible for construction means and methods for all delivery methods except for Design
-Build, in which the design-builder is responsible

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What meetings are typically conducted during construction and where are the requirements for meetings located?

A

Meetings are specified in Division 01 and the types of
meetings include progress meetings, contractor/
subcontractor meetings, preinstallation meetings,
closeout meetings, owner closeout meeting, and other
meetings as needed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is the purpose of submittals?

A

Submittals demonstrate how the contractor proposes to conform to the information given and the design concept expressed in the contract documents.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is the process for preparing, reviewing, and processing submittals?

A

Submittals are usually prepared and assembled by
manufacturers, suppliers, fabricators, and subcontractors, reviewed and approved by the
contractor and finally submitted to the architect/engineer for review.

Only those submittals requested by the contract
documents should be submitted and they should comply with the requirements of Division 01.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is the difference between observe and inspect?

A

Observe
Is a less focused view of what is being looked at and
implies that simply noticing or seeing is enough

Inspect
To critically evaluate what is in place and implies a more careful observation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What are the definitions of quality assurance and
quality control as they apply to construction activities?

A

Quality Assurance
Procedures or guarding against construction
defects and deviations from the ontract documents before and during the execution of the work

**Quality Control **
Procedures for valuating completed activities and elements of work for conformance with contract
requirements

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What are the two types of contract modifications?

A
  • Those that require to the contract sum/price and/or time (Requires a change order)
  • Those that do not require change to contract sum/price and time (called minor changes)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is the schedule of values?

A

An itemization of the costs of the work apportioned across various divisions of work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is the definition of a claim and what is an unresolved claim called?

A
  • A claim is an assertion of a right under the contract
  • An unresolved claim is called a dispute
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is the purpose of project closeout?

A

To provide an orderly transfer of the completed project from the contractor to the owner.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is the definition of substantial completion?

A

When the project, or a portion of the project, is sufficiently complete to permit the owner to use it for
its intended purpose

How well did you know this?
1
Not at all
2
3
4
5
Perfectly