DOMAIN 5: PROCUREMENT Flashcards

1
Q

What is the difference between instructions to bidders and instructions to proposers?

A

Instructions to Bidders
- Inform bidders how to obtain procurement documents
- How to submit requests for clarifications, interpretations, and substitutions
- How addenda will be transmitted
- How to submit the bid

Instructions to Proposers
- Establish ground rules and proper methods of obtaining clarifications or interpretations and define documents such as addenda

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is the purpose of addenda and when are they issued?

A
  • Addenda modify the procurement documents
  • Addenda are issued after the bidding period starts and before bids are submitted to the owner
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is bid shopping?

A

The unethical practice of revealing the price of one subcontractor to obtain a lower price from another subcontractor during procurement.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are the four procurement options?

A
  • Low Bid – Owner selects contractor with lowest bid
  • Best Value: Total Cost – Owner selects contractor based on total cost
  • Best Value: Fees – Owner selects contractor in which fees, rather than total construction cost, are considered
  • Qualifications-Based – Owner selects contractor based on contractor’s qualifications
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are the six methods used as a basis of payment for construction?

A

CLOSED BOOK
* Stipulated Sum
* Unit Price

OPEN BOOK
* Guaranteed Maximum Price
* Cost-Plus with GMP
* Cost-Plus without GMP
* Target Price

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are some reasons to have a contingency in a construction bid?

A
  • Incomplete documents
  • Unverified costs
  • Errors in pricing
  • Costs related to dispute resolution, claims, and legal fees
  • Costs for penalties related to weather and other
    circumstances
  • Default by a subcontractor or supplier
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What information should be made available to bidders, proposers, and contractors?

A
  • Preliminary schedules
  • Project budget info
  • Existing condition info
  • Survey info
  • Environmental assessment info
  • Existing material infor
  • Existing hazardous material info
  • Geophysical data
  • Geotechnical data
  • Permit application
How well did you know this?
1
Not at all
2
3
4
5
Perfectly