DOMAIN 2: PROJECT CONCEPTION & DELIVERY Flashcards

1
Q

What are the four considerations that should be identified during facility programming?

A
  • Function
  • Form
  • Economy
  • Time

2.2.10

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Which type of study provides information on
the subsurface conditions of a site?

A

Geotechnical investigation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What costs are included in the project budget?

A

All costs associated with the project, including:
- Programming
- Design
- Procurement
- Construction
- Occupancy

These would be divided into two categories:
- Hard costs (tangible)
- Soft costs (non-tangible)

2.2.7.3

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What does an All-Risk Builder’s Risk insurance policy cover and who is responsible for obtaining the policy?

A

Protection of buildings under construction for damages caused by all listed perils, that may include fire, windstorm, collapse, vandalism, and theft.

The owner is required to obtain
it, but it may be obtained by contractor for the owner if required by the construction contract.

Table 2.2

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is the difference between the two approaches to scheduling?

A

Methods Technique: Establishes the required date of occupancy and identifies milestone dates by working backward. It is used when the completion date is most important.

Critical Path Method:
Determines the longest path for
completion based on activities that are dependent on each other.

2.2.8

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is the purpose of zoning regulations and what restrictions may they include?

A

Zoning regulations define the permitted and conditional uses of land by regulating the type and size of a facility, its use, its function, and the density of improvements.

2.2.9.1

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What are the three types of commissioning?

A
  • Total Project Commissioning
  • Systems and Equipment Commissioning
  • Building Envelope Commissioning

2.2.13.1

How well did you know this?
1
Not at all
2
3
4
5
Perfectly