Domain 6 - PreConstruction Flashcards
The Time period between the procurement phase and the beginning of actual construction work
Preconstruction
Preconstruction activities before contractor can start the work.
1.) A successful bidder is selected by the owner to be the contractor.
2.) A letter of Intent to award the contract is issued by the owner.
3.) Bonds are furnished to the owner by the new contractor.
4.) Insurance certificates are furnished to the owner by the new contractor.
5.) The Agreement is signed by both the Owner and the Contractor
6.) Building Permits are issued by the AHJ
7.) Owner issues a Notice to Proceed.
8.) Contractor starts buying out the project and awards subcontracts, and purchase orders.
9.) Site Conditions are verified
10. Preconstruction meeting is held
11.) The contractor mobilizes onto the site
What is the purpose of the Agreement
*Agreements signify that there is a “meeting of the minds”
*the two parties have freely mutually agreed to the stipulated terms; that the parties are bound until the terms of the
agreement are fulfilled;
*to legally protect the parties.
Describe the advantages of using standardized agreements
- Language consistency and enforcement predictability.
- Legal preparation time and expense are less compared to custom-drafted documents.
- Reflect both industry practices and customs, or may be based on a consensus of those that use the forms.
- Risks and responsibilities are assigned to the party that is best able to control them or protect from unexpected costs.
- Developed with the understanding that they would be tailored by attorneys to fit the unique requirements of a specific project.
Identify the elements of an Agreement
*Offer and Acceptance - creates a duty to perform the scope of the work as described in the Agreement.
*Mutual consent - “meeting of the minds”
*Capacity - competent to sign an agreement, fulfill obligations
* Scope of Work - description of the Work required for the exchange of consideration (money).
*Consideration - exchange of value (money) for doing the Work
*Legality - cannot violate a public policy in place
*Remedy for Breach of the Agreement - claim or lawsuit
*Written - put in in writing, oral agreement may not be enforceable
*Signature - by responsible parties with authority to bind an agreement.
Identify the provisions of a typical construction agreement
- Preamble
- Identification of parties
- Identification of other participants
- Contract documents
- Scope of Work
- Date of Commencement of the work
- Date of Substantial Completion of the Work
- Liquidation damages
- Incentives, Bonuses, and penalties
- Contact Sum
- Adjustment of contract sum
- Unit Prices
- Payment Procedures
*Due dates for payments
*Work completed
*Materials and Equipment stored off-site
*Progress payment and retainage
*Cutoff date
*Payment at Substantial Completion
*Due Date for Final Payment
*Miscellaneous provisions
*Termination or suspension
*Signatures
Establishes a fixed monetary amount per day, as a
result of failure by the contractor to complete the work
by the date of substantial completion, a stipulated time,
or by a stated calendar date
Liquidation damages
Establishes the percentage of the contract sum that
will be due upon substantial completion
Payment at Substantial Completion
Enumerates the graphic and written documents
(drawings and specifications) that constitute the work
required by the agreement
Contract documents
Establishes a number of days for the duration of
the work, or a specific date when the work is to be
completed and the owner can occupy the project or
a designated portion thereof for its intended use
Date of Substantial Completion of the Work
Records the date of the agreement and the legal
identification of the project
Preamble
Establishes the monetary amount that is to be paid
for the performance of the agreement
Contact Sum
Establishes the date on which the work is evaluated for payment (10 days or less)
Cutoff date
30 to 60 days after Substantial Completion at which the owner will make final payment to the contractor, subject to fully completed work, and free of liens.
Due Date for Final Payment
Establish monthly date for progress payments, owner may keep 5% to 10% to ensure full performance of the agreement. Retained funds may be place in interest earning accounts until project completion. Contractor is paid the retainage with interest accured.
Progress payment and retainage