Discharge through performance Flashcards

1
Q

what is the strict rule of discharge

A

performance must be complete and exact

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

in what case can the unjust nature of the strict rule be seen

A

Cutter v Powell

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

in what case was the contract discharged

A

Re Moore Co.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

4 exceptions to strict rule

A

1) divisibility
2) substantial performance
3) acceptance of part performance
4) prevention of performance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

explain exception of divisibility with a case

A

if a contract has separate parts then non-completion of one part is not a breach of the whole contract, as in Ritchie v Atkinson

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

explain the exception of substantial performance

A

if a party has completed ‘substantial’ amount of work under the contract then that party entitled to be payed for the work done

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

does substantial performance apply where contract can’t be broken down + case

A

no, as in Cutter v Powell

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

under substantial performance, party ‘at fault’ may be entitled to payment based on what

A

quantum merit (as much as it is worth)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

what is ‘substantial’ as question of

A

fact, to be decided in each case

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

in what case had the contract been performed substantially, if not precisely

A

Dakin & Co v Lee

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

what case contrasts with Hoeing v Isaccs (contract substantially complete)

A

Bolton v Mahedeva - contract not completed substantially

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

explain acceptance of part performance

A

if one party agreed other party need not complete entire contract, strict rule will not apply and contract must be paid for on a quantum merit basis

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

in what case was the argument of part performance being accepted rejected and what was the outcome

A

Sumpter v Hedges - builder not entitled to be paid for the work he had done

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

explain prevention of performance with a case

A

if one party prevents the other from carrying out his obligations, the part trying to perform may have an action for damages as in Planche v Colburn

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

generally, failure to complete contract on time is treated as what

A

a breach of warranty (so damages but contract continues)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

court will regard time as a condition in what circumstances (so contract repudiated and/or damages)

A
  • parties expressly stated in contract that time is of the essence
  • in the circumstances time for completion is critical
  • 1 party already failed to perform + other insisted on a new date for completion as ‘time of the essence’
17
Q

what act of CRA may apply under time of performance

A

s52 - trader must perform within a reasonable time