Discharge of a contract-Performance Flashcards
3 ways in which a contract can be discharged.
- Performance of the contract by both parties
- A frustrating event
- Breach (where V then decides to end the contract)
What is ‘discharge’ of a contract?
When the contract comes to an end
What is the ‘strict rule’ of performance?
Holds that a party is not due any payment if he has not performed his side of the contract in full
Case for ‘strict rule’.
Cutter v Powell (1795)
Facts of Cutter
Cutter agreed to work as a second mate on a voyage for a FIXED fee.
Unfortunately, he died at sea near the end of the voyage.
His widow sued for for a proportion of his fee.
She was entitled to nothing as he had agreed to the entire voyage and had not done so.
As the strict rule can seem harsh, what are the exceptions the courts have developed?
- Divisibility
- Substantial or part performance
- Prevention of full performance
- Acceptance of part performance
Exception of strict rule regarding divisibility.
If a contract can be seen as compromising separate parts, then non-completion on one part is not a breach of the whole contract.
Case for divisibility exception.
Ritchie v Atkinson (1808)
Facts of Ritchie
Ship owner agreed to carry cargo at an agreed rate PER TON.
Carried only apart of the cargo
Ship owner entitled to be paid for part of cargo he had carried at agreed price PER TON.
But, was liable for breach on contract for not carrying the whole cargo.
Exception of strict rule regarding substantial or part performance.
Where a ‘substantial’ proportion of the work has been done then the party will be entitled to a proportion of the payment based on quantum meruit (the amount earned).
Cases for substantial or part performance exception.
Hoenig v Isaacs (1952)
Bolton v Mahadeva (1972)
Facts of Hoenig.
Decorator contracted to decorate and furnish room for £750.
Some of furniture was defective but could be repaired for £55.
Court decided contract was substantially completed on a financial basis.
Decorator entitled to be paid for what he had done on a quantum meruit basis.
Facts of Bolton v Mahadeva.
Builder agreed to install a central heating system for £560.
However, installation was defective as system gave off fumes and did not work properly.
Repairs cost £170.
Court decided builder was entitled to nothing, as there had not been substantial performance of the contract.
Exception of strict rule regarding prevention of full performance.
If one party prevents the other from carrying out his contract, then the innocent party can claim to be paid on a quantum meruit basis.
Case for prevention of full performance exception.
Planche v Colburn (1831)