Discharge of a Contract Flashcards

1
Q

what must the performance be

A

Performance must be complete and exact

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Cutter v Powell

A

Can only claim your payment if your work was complete

(in this case price was set for the whole performance)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Prevention of full performance

A

If one person prevents the other from performing their part of the contract, then the innocent party can claim to be paid on a quantum meruit basis (for what it is worth)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Planche v Colburn

A

Example of prevention of full performance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Ritche v Atkinson (severable contracts)

A

If a contract has separate parts, then the non-completion of one part does not breach the whole contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Substantial performance

A

If a party has done substantially what was required under the contract, then the doctrine of the substantial performance may apply (you have done nearly all the work)

There must be payment of the amount appropriate to what has been done (quantum meruit)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Dakin & CO v Lee (substantial performance)

A

Performance was complete even though some of the work was defective therefore he should be paid minus the amount to put it right

What amounts to substantial performance?

Theres no percentage or indicator of how much of the work should be done

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Bolton v Mahadeva (substantial performance)

A

court decided there had not been substantial performance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Hoening v Isaacs (substantial performance)

A

court said there had been substantial performance

Down to the courts to decide

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Acceptance of part payment

A

If one party has agreed that the other party need not complete the entire contract, then the contract must be paid on a quantum meruit basis

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Sumpter v Hedges (acceptance of part payment)

A

The customer had not accepted part performance as they had no choice but to perform the rest of the performance

(builder had done half the work and the customer done the other half so the builder tried claiming that showed the customer had accepted part performance)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

The court regards time as a condition if:

A

The parties have expressly stated in the contract that time is of the essence of the contract

In the circumstances time for completion of the contract is critical

One party has failed to perform on time and the other has insisted on a new date for completion of the contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Charles Rickards Ltd v Oppenheim

A

Time could be a condition of the contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is the effect of delay to performance

A

The effect of delay to performance is treated as a breach of condition and many of these points are present. If not, it will be treated as an innominate term

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

British Electric v Electric Railways

A

Duty to mitigate loss

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Law for duty to mitigate

A

A claimant is not bound to go to extraordinary lengths to mitigate loss, only what is reasonable in the circumstances