Discharge Of A Contract Flashcards

1
Q

What is discharge by performance

A

The contract has been performed completely and exactly. Cutter v Powell - contract was not complete as Cutter died before finishing voyage

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Performance - divisible contracts

A

Contact can be divided into separate parts, so non-completion of one part doesn’t breach the whole contract.
Ritchie v Atkinson - entitled to be paid for what he did ship but breached by not shipping all

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Performance - substantial performance

A

When a party has done substantially what was required. Payment should be appropriate to what is done.
Dakin v Lee - entitled to be paid the price subject to a deduction for the defective work
Hoenig v Isaacs - quantum meruit basis of payment
Bolton v Mahadeva - contractor did the one task required wrong, so wasn’t entitled to payment
Young v Thames - did not do exact task, was entitled to payment minus savings

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Performance - prevention of full performance

A

Planche v Colburn - writer entitled to a fee for wasted work on quantum meruit based when published abandoned series

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Performance - acceptance of part performance

A

If one party agrees the other party need not comple the the entire contract then they must be paid quantum meruit, but consent must specifically acknowledge this, without undue pressure
Sumpter v Hedges - innocent party had no choice but to accept part performance so didn’t consent to part performance. Insufficient work done to deserve pay, but sum was awarded for leftover materials used.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Performance when time is of the essence

A

Time is a condition if:
- the parties have expressly stated in the contract that time is of the essence, or,
- in the circumstance time for completion of the contract is critical, or,
- one party has failed to perform on time and the other has insisted on a new deadline

Charles Rickards v Oppenheim - time had been made of the essence and not complied with so had the right to reject

Union Eagle v Golden Achievement - 10 minutes past the decided deadline was still too late

S52 CRA 2015 - if there is no expressly stated deadline, “reasonable time” is implied. Can have the right to a price reduction or end the contract.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Discharge by breach - actual breach

A

Either or both parties could breach
Breach of any term gives the right to claim damages, but in breach of a condition gives the right to repudiate the contract and/or sue for damages,

3 ways to breach contract are
- renunciation of liabilities (not paying a bill on time)
- impossibility created by own act (closing salon when appointments are booked)
- total or partial failure or performance (delivering defective goods)

3 repudiatory (serious) breaches
- breach of condition
- refusal to perform contract
- sufficiently serious breach of an innominate term
Means non breaching party can continue or terminate and claim damages

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Discharge by breach - anticipatory breach

A

Occurs when notice is given that contract won’t be performed. Can sue immediately or wait.
Horchester v de la Tour - don’t have to wait for actual breach

Can treat contract as ended

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Remedies for discharge by breach

A
  • anticipatory breach: can claim damages immediately
  • can wait to see if actual breach happens
  • may repudiate for anticipatory breach
  • can claim damages and or repudiation for breach of condition
  • can claim damages for breach of warranty
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Discharge by frustration

A

Taylor v Caldwell - an unforeseeable intervening event that is the fault of neither party

Contracts may contain a force majeure clause which excludes liability for extraordinary events which may delay or result in non performance

Can be through
1. Impossibility of performance
2. Subsequent illegality
3. Frustration of the common venture (commercial purpose no longer possible)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Frustration - impossibility of performance

A

Jackson v Union Marine Insurance - boat running aground was simply “perils of the sea”
Robinson v Davidson - illness of piano player was a frustrating event
Condor v Baron Knights - drummer was ill and could only work 4 hours a week, stand in was necessary so contract frustrated

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Frustration - contact becoming illegal to perform

A

Denny, Mott and Dickinson v James B. Fraser - court said a contract to import specific goods would become frustrated if it became illegal
Re Shipton Anderson - government requisitioned grain so would have been illegal to deliver

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Frustration of the common venture

A

Radical change of circumstances so commercial purpose cannot be achieved
Krell v Henry - renting the hotel room no longer had a purpose when coronation was cancelled so contract was frustrated
Herne Bay Steamboat v Hutton - hiring a boat to see fleet was not affected by presence of king or lack thereof so no frustration

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Where frustration doesn’t apply - self induced

A

Self-induced
Maritime National Fish v Ocean Trawlers - d chose where to assign licenses so no frustration
Gamerco SA v Fair Warning and Missouri Storm - venue license was withdrawn due to an external factor so frustration
J Lauritzen v Super Servant Two - other ship could be used, had options

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Where frustration doesn’t apply - less profitable

A

Less profitable or more difficult is not a reason
Davis Contracots v Fareham Urban District Council - labour shortages made job less profitable but there was no frustration
Tsakiroglou v Noblee - contract didn’t specify via Suez Canal, transport still could have been completed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Where frustration doesn’t apply - foreseeable risk or mentioned in the contract

A

Amalgamated Investment and Property v John Walker - listing was a risk associated with all old buildings

Armchair Answercall v People in Mind - had to be a “supervening outside event which the parties could not reasonably thought to have foreseen as a real possibility”

17
Q

Remedies for frustration

A

Common law - contract is automatically terminated at the time of the event. Future obligations are terminated.

Law Reform (Frustrated Contracts) Act 1943
S1(2)
- money paid before the frustrating event is recoverable (paying in advance)
- no longer an obligation to pay price agreed in the future
- if the party expecting money incurred costs due to the event, the court may award him a sum

S1(3)
- if one party has obtained a valuable benefit from the contract before the frustrating event they may have to pay a sum in respect of it (BP Explorstion v Hunt)
- that sun is whatever the court considers just

S1(4) estimating the expenses must be reasonable in respect of
- overhead expenses
- work or services personally performed