Development Appraisals Flashcards
What is an FVA and when is it required?
- An assessment of a development’s viability. It considers whether or not a development is viable
- Required when not able to provide AH compliant scheme whilst making a fair return
What is Benchmark land value
- BLV used as the basis of value in a FVA.
- Based on EUV (value of land in its existing use) plus a premium for the landowner.
Minimum return required for a reasonable landowner to make the site available for redevelopment
What purpose does BLV surve in FVAs?
Used as basis of value in FVAs
This is compared with the RLV. When BLV is higher then the RLV scheme cannot afford any more affordable.
What is the EUV?
Value of land in its existing use
What is the premium?
- Provides reaonable incentive for land owner to bring forward land
- Calculated by other BLV premiums / judgement depending on site
What is AUV
(alternate use value)
- Considers other options for a property to ascertain the highest value and best use for the land
- e.g refurbished building PDO rights if within parameters (but only if reasonable)
POC vs IRR?
POC = profit relative to cost,
- not considering time value of money
- Good for simple projects
IRR = focuses on rate of return over time,
- considers when cash flow occur and their present value.
- More complex projects
What is a target rate of return?
- Level of return expected from an investment.
- Accounts for variety of factors (i.e market conditions, constrained site etc).
- Blended TRR accounts for Private (17.5%), AH (5%) and commercial (15%) blended together.
What RICS guidance is there when undertaking FVAs?
- PS - Financial viability in planning: conduct and reporting (2019) - which is mandatory for all RICS members carrying out financial viability assessments.
- Supplemented by PS - Assessing viability in planning under the NPPF 2019 for England (2021)
What are the key points in 2019 Professional Standard “Financial Viability in Planning, Conduct & Reporting”
- When providing BLV, RICS members must provide:
1. EUV,
2. Premium,
3. Market evidence,
4. Supporting considerations, assumptions and justifications adopted and
5. AUV if appropriate. - Objectivity, impartiality and reasonableness statement must be included in report.
- Fee statement (no contingent fees/performance related)
- Sensitivity analysis must be provided in all FVA.
What are the key points in 2019 Professional Standard “Financial Viability in Planning, Conduct & Reporting”
- FVAs in plan-making
- Makes key definitions
How would you undertake an FVA?
Method 1:
1. Calculate RLV (GDV-GDC-Profit)
2. Calculate BLV (EUV+)
2. If BLV is higher than RLV, the scheme cannot afford any more affordable housing
(can then work back varying the AH in appraisals)
Method 2:
1. Calculate the BLV and incorporate to calculate into development appraisal.
COMPARE IRR TO TARGET IRR
How is BLV calculated?
EUV+ approach
- Based on Existing Use Value (EUV) – E.g offices with comparables get rents, then apply ARY depending on location, specification and likely tenants.
- Then, plus a premium for the landowner (land comparables).
What are key development costs on a project?
- Construction costs
- Land acquisition (dev appraisal)
- Planning related costs (CIL, s106)
- Development Management & Contingencies
- Finance costs
How do you calculate construction costs?
- Internal/External QS to udnertake cost order of cost estimate
- BCIS
What are the neagtives about BCIS?
BCIS (building cost infromation service)
- Slightly out of date (historical data)
- Data from tenders NOT achieved (competitive?)
- BCIS unable to capture specific designs
How do you calculate land acquisiton costs?
Use land comparables to establish £ per acrea, and apply that to the size of the site
How would you estimate CIL or s106 costs?
For FVA, the planning consultant would advise.
CIL = SQM of additional floorspace, multiplied by the borough’s charging schedule
s106 = look at similar s106s in the area on the relevant planning authority’s portal. Apply judgement / pSQM
When are developemnt CIL exempt?
E.g extensions under 100 square meters that don’t create a new dwelling
What is a typical development management fee?
3-5% total project costs (depending on complexity of project)
What is a DMA (development management agreement)
What would you expect to see in it?
Contract between a landowner or investor and development manager to oversee and manage the development process of a property
- Roles and responsibilities
—–> scope of service
—–> level of authority - Fees
- Limitation of liability
What is typcial development contingency?
5-10% of construction costs (depending on level of risk/build cost fluctuations)
What would typical finance cost be?
How would you caculate finance costs?
Depends on market - typically 5-12%.
-
Sonia rate over last 3 months (sterling overnight index average) – 4.5%
+ premium for the banks (developer/asset/risk) – 3%
= 7.5% - If 30%/70% Loan to Value, 70* construction costs = chargable amount
FINANCE COSTS = SONIA+premium * chargable amount - Also – arrangement fee and exit fee 1% of the 100million, as well as non-utilisation fee (0.5%?)
What is the importanc of sales rates / programme on IRR based appraisals?
sales rates impact cash receipts
programme impacts build cost timing