Design Economics and Cost Planning Flashcards

1
Q

What are the 8 RIBA Stages?

A

0 - Strategic Definition
1 - Preparation and Briefing
2 - Concept Design
3 - Spatial Coordination
4 - Technical Design
5 - Construction
6 - Handover
7 - Use

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is NRM1?

A

Order of Cost Estimating and Cost Planning for Capital Building Works

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is NRM2?

A

Detailed Measurement for Building Works

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is NRM3?

A

Order of Cost Estimating and Cost Planning for Building Maintenance Works

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

How would you adjust for TPI?

A
  1. Identify base period and current period
  2. Relevant TPI value
  3. Percentage change of TPI

( (current TPI- base TPI) / base TPI) x 100

  1. Apply percentage change to original price
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is the current TPI?

A

BCIS - 2.3%
G&T - 2.75%

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is TPI?

A

Tender Price Index.

Measures the movement of prices in construction tenders, reflecting how market conditions and competitiveness change over time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly