Contract Practice Flashcards

1
Q

What is off-site vesting?

A

Where ownership of materials manufactured off-site is transferred to the Client upon payment

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is required to pay for off-site materials?

A
  1. Needs to be listed in the Contract
  2. In accoradance with ERs
  3. Vesting Certificate - signed by both parties
  4. Labelled with Client name and location fo the project
  5. Insured by the Contractor until delivered to site
  6. Bonds to be provided
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Why was the JCT 2016 Minor Works with CDP recommended for the West-End retrofit project?

A

Scope of works were relatively small and didn’t require all the provisions of an SBC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are some of the differences between SBC and MW?

A

Simpler provisions – MW doesn’t have a provision for named subcontractors

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What were the CDP items for the St James’ project?

A

Floor box and grommet positions
Thickness of partitions

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What was your role within the West-End retrofit project contract?

A

Undertook post contract procedures such as interim valuations, valuing change

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is an example of a change you valued on the West-End retrofit project?

A

Change in the colour of paint to the internal office plate floors

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

How did you value the change in paint colour on the West-End retrofit project?

A

Used JCT valuation rules, and used a star rate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What other JCT Contracts were considered for the West-End retrofit project?

A

The contract used was JCT Design & Build. An alternative contract would be SBC however my understanding is design was not yet fully coordinated and therefore the Contractor was used to progress the design from RIBA Stage 3

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is the difference between a Relevant Matter and Relevant Event?

A

Relevant Matter - Employers actions which entitle the Contractor to Loss and/or Expense

Relevant Event - An instance where the Contractor is entitled to an Extension of Time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Where in the contract is Relevant Matter defined?

A

Relevant Matter – Section 4

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Where in the contract is Relevant Event defined?

A

Relevant Event – Section 2

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is the contractual process for notifying and assessing loss and expense claims?

A

(Clause 4.20) Contractor notifies as soon as reasonably apparent, follow with contractors’ initial assessment of loss and expense

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What are some examples of relevant events?

A

Force Majeure
Variations
Adverse weather conditions
Strikes

In 2024 – epidemics, change of statute after the base date

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is the base date?

A

Reference of the date of the conditions when the tender was prepared and therefore reflects that price

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What are the heads of claims?

A

1.Prolongation costs
2. General disruption
3. Finance charges
4. Loss of profits
5. Wasted management time

17
Q

What are some changes in the JCT 2024 Suite of Contracts?

A

Gender neutral
Time to review EOT amended from 12 weeks to 8 weeks
Additional relevant events including epidemics
Reference to new building safety act

18
Q

What are some common amendments you see in your projects?

A
  1. Amending final date for payment to suit Client financial cycle
  2. Amend rectification period from 6 months to 12 months
  3. D&B – Employers requirements take precedence over Contractor Proposals
19
Q

Can you talk me through the valuation timelines in the JCT SBC 2016?

A

Interim valuation date – 7 days for QS to walk around site
Due Date, 7 days after IVD. QS to raise recommendation
5 days after due date – CA to raise interim certification
14 days after – final date for payment
5 days before final date for payment, Client can issue Pay less notice

20
Q

What are the JCT Valuation rules?

A
  1. Where works are similar to use a Contract Rate
  2. Where works are similar but the conditions of works are different, use an adjusted fair rate (star rate)
  3. Where works are not similar, works should be valued fairly (market-test)
  4. Use dayworks where works cannot be measured
21
Q

What are the contract particulars?

A

Sets out project specific variables in the agreement (retention, dates)

22
Q

What is retention?

A

Percentage of money held by Employer as a safeguard for any defective/non-conforming works

23
Q

What percentage retention do you have on your projects?

A

3% on SBC and D&B
5% on Minor Works and Intermediate

24
Q

When is retention released?

A

Half after PC or sectional completion
Remaining after rectification period

25
Q

What is required to form a contract?

A
  1. Offer and Acceptance
  2. Intent
  3. Consideration
  4. Capacity
26
Q

Why have you recommended JCT contracts for your fit out projects?

A

Common in the fit-out industry and therefore saves time reviewing other contracts

27
Q

Why was a Letter of Intent (LOI) required on this project?

A

To allow for items to be ordered ahead of start of site

28
Q

What types of LOI are there?

A
  1. Letter of comfort
  2. Instructions to Proceed with Consent to Spend
  3. Letters Recognizing the Existence of a Binding Contract
29
Q

What is included within the LOI?

A
  1. Scope of works
  2. Limit of expenditure
  3. Agreed CSA
  4. Payment terms
  5. ADR
  6. Liquidated damages
30
Q

Are letters of intent legally binding?

A

Based on Ambleforth Abbey Trust v Turner & Townsend case law – no

31
Q

Why would you recommend LOI over PCSA?

A

PCSAs are used when Employer wants Contractor to provide pre-contract services such as advise on design.

32
Q

How did your client maintain control of design under the CDP packages?

A

Ensure robust information within CDP documents
CMT approval process
Novate design team

33
Q

What was included in the loss and expense claim in your St James Project? And what was the total agreed cost?

A
  1. Prolongation costs
  2. General disruption

C. £130,000