Design economics and cost planning Flashcards

1
Q

Can you name some sources of cost data?

A

BCIS
Internal and external benchmarking
tender returns

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are the stages of cost planning?

A
Stage 1 - feasibility 
Stage 2 - Concept design
Stage 3 - Developed design
Stage 4 - Technical design
Stage 5 - Construction.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

How cost planning assists in the financial control of projects
during the design development stage

A
  • More robust and reliable cost forecasting, which gives confidence to funders and results in less conditional authorisation by funding boards
  • Accurate detailing of final users’ needs, which engages them in the sign-off process, offers less avenue for change and avoids the scope creep that is caused by generic, outline cost plans.
  • Change Control is more defined and better managed when tied to a detailed cost plan.
  • The implementation team is better informed through a comprehensive, detailed briefing document.