Design economics and cost planning Flashcards
1
Q
Can you name some sources of cost data?
A
BCIS
Internal and external benchmarking
tender returns
2
Q
What are the stages of cost planning?
A
Stage 1 - feasibility Stage 2 - Concept design Stage 3 - Developed design Stage 4 - Technical design Stage 5 - Construction.
3
Q
How cost planning assists in the financial control of projects
during the design development stage
A
- More robust and reliable cost forecasting, which gives confidence to funders and results in less conditional authorisation by funding boards
- Accurate detailing of final users’ needs, which engages them in the sign-off process, offers less avenue for change and avoids the scope creep that is caused by generic, outline cost plans.
- Change Control is more defined and better managed when tied to a detailed cost plan.
- The implementation team is better informed through a comprehensive, detailed briefing document.