Design and specification Flashcards
(41 cards)
What goes into a specification?
- SoW.
- Prelims.
- Materials and Workmanship.
What guidance do you follow for producing a specification?
- BS 8000.
- Design and Specification Guidance Note.
What are the advantages of using NBS Chorus?
You can select the items you want and it pulls them through into a document with the detail saving you time.
What parts did you do of the specification?
SoW, prelims, Materials and Workmanship.
Would you specify fire stopping?
No this is done by a specialist.
What is the advantage of taking the design to RIBA Stage 4?
- More control over design.
- More cost certainty.
[- Easier for contractor to price.
- Better understanding of project.]
How did you ensure the durability of products?
- Specify BS.
- Guarantees [insurance backed].
17 Bowling Green Lane: What protections were in place for the products?
Collateral warranties and manufacturers guarantee.
What is a heritage statement?
Describes the historical significance of a building.
Note: Design and spec - Ferry Lane.
- TDD (vendors).
- 20 metres from nearest protected staircase (should be max 18 metres).
- Proposed erecting protected corridor to reduce travel distance.
Ferry Lane: a) How did erecting a wall reduce the protected stairwell route?
b) Any alternatives considered?
a) Reduced the travel distance as it created a protected corridor.
b) Secondary staircase - too expensive.
Ferry Lane - How did you assess the level of fire protection required from the newly erected wall?
Specified:
- AD B.
- BS 9999.
- Recommended 30 min fire rated plasterboard [12.5mm] and fire doors.
Ferry Lane - Take me through the full specification of the partition wall.
- Plasterboard 12.5mm (30 min fire rating) [extended above suspended ceiling and below raised floor].
- Mineral wool insulation.
- Fire doors 30 minute.
OVO Arena: You mentioned that you noted numerous items that could be upgraded to improve the building’s sustainability. Aside from LED lighting, what did you identify and recommend?
- Add insulation.
- Upgrade windows [single to double glazed].
- Solar panels.
- Low-flow taps.
- PIRs.
[- Green roof.]
[- Energy efficient heating and cooling.]
OVO Arena - a) How were the works presented to your client in the PPM?
b) How were the sustainability works presented?
a) - Schedule [condition and year for each item].
- Report [explaining schedule].
b) Included within recommendations section of the report which summarised the schedule.
OVO Arena - What was your client’s key driver for the PPM requirement?
- Understand costs for maintaining the property.
- What years to undertake maintenance.
OVO Arena - How might the presentation of a PPM differ somewhat to providing your client with a vendor’s TDD?
- PPMs outline the maintenance over reporting period (typically 10 years).
TDD: - Compliance.
- Property sale not maintenace.
For D&B what RIBA Stage would you take the design to?
RIBA Stage 3 - Spatial Coordination.
What’s the difference between Building Regulations and British Standards?
- Building Regs: minimum standards (mandatory).
- British Standards: best practice (voluntary).
How are provisional sums dealt with post-contract?
- Provisional sum and works omitted.
- Contract instruction issued with defined works and cost [variation not CI if the cost differs].
[PS amount is deducted from contract sum and actual cost of instruction/variation is added]
Can you name some headings within the prelims document?
- DoW [Description of Work].
- The site.
- The contract.
When is planning permission required?
Not required for:
- Internal works.
- Permitted development.
- New build.
- Change of use.
- Extension.
How long does planning permission take?
- Typically around 8 weeks for normal property.
- Around 12 weeks for Listed building [both LBC and normal planning considered together].
What information is required when submitting a planning application?
- Site plan.
- Existing and proposed drawings.
- Application form.
Conservation areas: - Design and Access (D&A) statement
- Heritage statement.