Contract admin Flashcards
What’s the difference between Minor Works and Intermediate contracts?
MW up to £250k and simple buildings.
IC up to £1m and moderate complexity, Clerk of Works, Sectional Completion.
How do you select which contract to use?
Contract value, complexity, JCT guide.
What documents are included within contract documents?
Spec, drawings, payment terms, [prelims, preambles].
What is the purpose of prelims and preambles?
Prelims: describe the nature of the work and how it’s achieved.
Preambles: explanation of the contract e.g. project objectives, project information (address etc).
Who are the parties on the contract?
Employer, contractor, consultants.
What are some key contract events?
Payment, PC, Final Certificate.
What are collateral warranties?
An agreement where a third party is covered despite not being part of the original contract.
What’s the difference between Sectional Completion and Partial Possession?
Sectional Completion is pre-planned.
Partial Possesion is not pre-planned.
What information is provided within a CPP?
Project description, site rules, emergency procedures etc.
Can you tell me some different types of procurement?
Traditional (client team).
Design and Build.
Management contracting: manages design and works but doesn’t complete works directly (Quinn on Windsor Walk).
What is the role of a Principal Designer (CDM)?
Plans and manages H&S during the pre-construction phase of a project involving more than one contractor.
What are some of the responsibilities of a Principal Designer (CDM)?
Manage H&S in the pre-construction phase, work with client and principal contractor, review CPP.
What information goes into a PCIP?
Fire procedures, emergency procedures, building information.
Is the Contractor’s Design Portion optional?
Yes.
What’s the alternative to including contractor’s design in a contract?
It could be designed entirely by the client’s side.
What specification would be used for a project designed entirely by the client’s side?
Prescriptive specification.
What informaiton is included when appointing a consultant?
Works, costs, timeline.
What is a novation agreement (substituted contract)?
When one party replaces another and takes on the rights and obligations.
What are the timelines for Interim Valuations?
Application for payment > Interim Valuation Date > Due date (7 days after IVD) > Payment certificate (CA - within 5 days of due date)/Pay less notice (up to 5 days before final payment date) > Final payment date (14 days after due date).
What is the base date?
Date from which fluctuations will apply i.e. inflation rises will be borne by contractor from this point. Typically date of tender returns.
What is the process when a contractor submits an EOT claim?
1) Notice from the contractor for delay stating Relevant Event.
2) Assessment by CA within 12 weeks of notice.
3) Accepted claim - extension granted, Loss and expense claim based on prelims.
What is the difference between a Relevant Event and Relevant Matter?
Relevant Event: EOT – caused by client or neutral event.
Relevant Matter: money (no time extension) – caused by client.
What is the purpose of Loss and Expense?
To reimburse the contractor for loss suffered in continuing to work.
Client only required to pay for actual loss.
When can an employer claim for Liquidated Damages?
When the contractor fails to meet the completion date.
How are Liquidated Damages paid?
Recovered from the contractor as a debt or from monies due.
Contractor required to pay rate pre-determined in the contract. Calculated as loss e.g. loss of rent.
What is time at large?
No PC date. Contractor no longer bound to complete works by a specific date.
What is Practical Completion?
All works in the contract are complete.
What is the process for Practical Completion?
Inspection > works complete/snagging list > test certificates > O&M manuals > BCA sign off > issue PC certificate.