Definitions Flashcards

1
Q

Acceptance Criteria

A

A set of conditions that is required to be met before deliverables are accepted.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Accepted Deliverables

A

Products results or capabilities produced by a project and validated by the project customer or sponsors as meeting there specified acceptance criteria.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Accuracy

A

Within the quality management system, accuracy is an assessment of correctness.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Acquire Resources

A

The process of obtaining team members, facilities, equipment, materials, supplies, and other resources necessary to complete project work.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Acquisition

A

Obtaining human and material resources necessary to perform project activities. Acquisition implies a cost of resources, and is not necessarily financial.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Activity

A

A distinct, schedule portion of work performed during the course of a project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Activity Attributes

A

Multiple attributes associated with each schedule activity that can be included within the activity list. Activity attributes include activity codes, predecessor activities, successor activities, logical relationships, leads and legs, resource requirements, imposed dates, constraints, and assumptions.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Activity Duration

A

The time in calendar units between the start and finish of a scheduled activity.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Activity-on-Node

A

See PDM -precedents diagramming method

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Actual Cost (AC)

A

The realized cost incurred for work performed on an activity during a specific time period.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Actual Duration

A

The time in calendar units between the actual start date of the schedule activity and either the data date of the project schedule if the schedule activity is in progress or the actual finish date if the schedule activity is complete.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Adaptive Life Cycle

A

A project life cycle that is iterative or incremental.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Affinity Diagrams

A

A technique that allows large numbers of ideas to be classified into groups for review and analysis.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Agreements

A

Any document or communication that defines the initial intentions of a project. This can take the form of a contract, memorandum of understanding (MOU), letters of agreement, verbal agreements, email, etc.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Alternative Analysis

A

A technique used to evaluate identified options in order to select the options or approaches to use to execute and perform the work of the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Analogous Estimating

A

A technique for estimating the duration or cost of an activity or a project using historical data from a similar activity or project.

17
Q

Analytical Techniques

A

Various techniques used to evaluate, analyze,or forecast potential outcomes based on possible variations of a project or environmental variables in their relationships with other variables.

18
Q

Assumptions

A

A factor in the planning process that is considered to be true, real, or certain, without proof or demonstration.

19
Q

Assumption Log

A

A project document used to record all assumptions and constraints throughout the project lifecycle.

20
Q

Attribute Sampling

A

Method of measuring quality that consist of noting the presence or absence of some characteristics (attribute) in each of the units under consideration.

21
Q

Authority

A

The right to apply project resources, expend funds, make decisions, or give approvals.

22
Q

Backward Pass

A

A critical path method technique for calculating the late start and late finish dates by working backward through the schedule model from the project end date.

23
Q

Bar Chart

A

Graphic display of schedule – related information. In the typical bar chart, schedule activities or work breakdown structure components are listed down the left side of the chart, dates are shown across the top, and activities durations are shown as date-placed horizontal bars. See also Gannt charts

24
Q

Basis of Estimates

A

Supporting documentation outlining the details use in establishing project estimates such as assumptions, constraints, level detail, ranges, and confidence levels.

25
Q

Benchmarking

A

The comparison of actual or planned product, processes, and practices to those of comparable organizations to identify best practices, generate ideas for improvement, and provide a basis for measuring performance.

26
Q

Benefits Management Plan

A

The document explanation defining the process for creating, maximizing, and sustaining the benefits provided by a project or program

27
Q

Bid documents

A

All documents used to solicit information, quotations, or proposals from perspective sellers.

28
Q

Bidder Conference

A

The meetings with prospective seller prior to the preparation of a bid or proposal to ensure all perspective vendors have a clear and common understanding of the procurement. Also known as contractor conferences, vendor conferences, or pre-bid conference.

29
Q

Delphi Technique

A

The Delphi Technique is an essential project management technique that refers to an information gathering technique in which the opinions of those whose opinions are most valuable, traditionally industry experts, is solicited, with the ultimate hope and goal of attaining a consensus.

30
Q

Facilitation

A

Facilitation sessions can be used to help groups of stakeholders with different perspectives reach consensus on prioritizing requirements.