Definitions Flashcards
Define a continuity test
A continuity test checks that there are no breaks in the circuit, and that they have a low enough resistance to function safely and correctly
Define an insultation resistance test
An insultation resistance test ensures that the insulating properties of the circuit(s) wiring and its accessories is sufficient to prevent current ‘leaking’ from the conductors.
Define a polarity test
A polarity test is used to verify that all the conductors in a circuit are in their correct terminals, and that protective and swtiching devices are on the line conductor only
Define a voltage test
A voltage test is used to determine whether or not a circuit is energized (live) or de-energized (dead).
When performing a voltage test, what is being measured?
Which terminals should be used to get this measurement?
Which pair of terminals will not provide a reading?
A voltage test gives an indication of the potential difference of an energized circuit.
Between the Live & Neutral terminals and Live and Earth terminals will give a reading of this potential difference.
Neutral and Earth will not give a difference reading as they are at the same potential.
Which documents provide more information regarding inspection & testing?
Part 6 of BS7671& Guidance Note 3
Which document provides information regarding testing equipment?
Guidance Note GS38
What is R1?
R1 is the value of the resistance of the Line Conductor in any given circuit.
What is R2?
R2 is the value of the resistance of the CPC in any given circuit.
What is Rn?
Rn is the value of the resistance of the Neutral conductor in any given circuit.
When does initial verification take place?
Before an installation is put into service
According to the BS7671 what must any additional components of an installation do?
It must be confirmed that any new additions or alterations should not invalidate the rating of the installation, for example, that the maximum current draw cannot exceed 32A if that is the rating of the circuit that is being added to.
Before adding additional components to an installation, what should take place?
A pre-work survey
What kind of work requires initial verification?
For new work or additions/ alterations
What kind of installation requires Periodic Inspection?
An existing installation