Definitions Flashcards

1
Q

a Set of conditions that are met before deliverables are accepted by the customers

A

Acceptance Criteria

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

A distinct, scheduled portion of work performed during the project. Usually stored on the activity list

A

Activity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

The actual cost incurred for the work performed on an activity during a specific time period

A

Actual Cost (AC)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

A technique for estimating the duration or cost of activity or a project using using historical data from a similar activity or project. Also know as top-down estimating.

A

Analogous Estimating

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

A factor in the planning processes considered to be true or real without proof or demonstration

A

Assumption

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

A critical path method technique for computing the late start and late finish dates by working backwards through the schedule model from the project end date

A

Backward Pass

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

The accepted version of a work product that can be changed using formal change control processes and is used as the basis for comparison to actual results

A

Baseline

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

A method of estimating project duration or cost by aggregating the estimates of the lower-level components of the work breakdown structure (WBS)

A

Bottom-Up Estimate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

The amount of all budgets established for the work to be performed

A

Budget at Completion (BAC)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

A process whereby changes to documents , deliverables, or baselines related with the project are identified, documented, approved, or rejected

A

Change Control

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

A formally commissioned group responsible for reviewing, assessing, approving, deferring, or rejecting changes to the project, and for recording and communicating such decisions

A

Change Control Board

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

A set of procedures that defines how modifications to the project deliverables and documentation are managed and controlled

A

Change Control System

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

A formal proposal to change any document, deliverable, or baseline in the project management plan

A

Change Request

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

A component of the project management plan that describes how, when, and by whom information will be administered and distributed

A

Communications Management Plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

A collection of procedures used to track project artifacts and monitor and control changes to these artifacts

A

Configuration Management System

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

A restrictive feature that affects the execution of a project

A

Constraint

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Time or money assigned in the schedule or cost baseline for known risks with response strategies

A

Contingency Reserves

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

A planned activity that restores the performance of the project work with the project management plan

A

Corrective Action

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

The approved version of work package cost estimates and contingency reserve that can be changed using formal change control procedures

A

Cost Baseline

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

A Component of a project management plan that defines how costs will be planned and controlled

A

Cost Management Plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

A Measure of the cost efficiency of budgeted resources expressed as the ratio of earned value to actual cost

A

Cost Performance Index (CPI)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

The Amount of budget shortfall or surplus at a given point in time, expressed as the difference between earned value and the actual cost

A

Cost Variance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

A schedule compression technique used to shorten the schedule duration by adding resources. This will greatly increase project Cost

A

Crashing

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

A schedule method that allows the project team to place buffers on a project schedule path to account for limited resources

A

Critical Chain Method

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

The sequence of activities that represents the longest path through a project, which determines the shortest possible duration . Activities on this path of ZERO float

A

Critical Path

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

Any activity on the critical path in a project schedule

A

Critical PAth Activity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
27
Q

A method used to estimate the minimum project duration and determine the amount of scheduling flexibility on the logical network paths within the schedule

A

Critical Path Method

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
28
Q

A technique used for dividing and subdividing the project deliverables into smaller, more manageable parts. Also used to subdivide the project activities.

A

Decmoposition

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
29
Q

An intentional activity to modify a nonconforming product or product component

A

Defect Repair

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
30
Q

Part of the product that is presented to the customer or stakeholders for acceptance

A

Deliverable

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
31
Q

The total number of work periods required to complete an activity or work breakdown structure component, expressed in hours, days or weeks

A

Duration

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
32
Q

The earliest an activity can finish without delaying the project end date

A

Early Finish Date

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
33
Q

The earliest an activity can start without delaying the project end date

A

Early Start Date

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
34
Q

The amount of money worth of work actually accomplished on the project

A

Earned Value (EV)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
35
Q

A methodology that combines scope, schedule, and resource measurements to assess project performance

A

Earned Value Management

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
36
Q

Conditions, not under the immediate control of the team, that influence, constrain, or direct the project

A

Enterprise Environmental Factors

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
37
Q

The forecast of the total cost of the project at the end based on the current spending rate of the project

A

Estimate at Completion (EAC)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
38
Q

The amount of money that will be needed to complete the current project based on the current performance

A

Estimate to Complete (ETC)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
39
Q

A schedule compression technique in which activities or phases are done in parallel for at least a portion or the entire duration. This can increase the risk on the project

A

Fast Tracking

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
40
Q

A relationship in which a successor activity cannot finish until a predecessor activity has finished

A

Finish-to-Finish

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
41
Q

A relationship in which a successor activity cannot start until a predecessor activity has finished

A

Finish-to-Start

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
42
Q

A critical path method technique for calculating the early start and early finish dates by working forward through the schedule

A

Forward Pass

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
43
Q

An organizational structure in which staff is grouped by areas of specialization and the project manager has limited authority

A

Functional Organization

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
44
Q

A bar chart of schedule information where activities are listed. Generally part of the project schedule

A

Gantt Chart

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
45
Q

The amount of time whereby a successor activity will be delayed to a predecessor activity

A

Lag

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
46
Q

The latest an activity can finish without delaying the project end date

A

Late Finish Date

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
47
Q

The Latest an activity can start without delaying the project end date

A

Late Start Date

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
48
Q

The amount of time where a successor activity can be started before the predecessor activity finishes

A

Lead

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
49
Q

The data gained during a project which shows how project events were addressed or should be addressed in the future for the purpose of improving future performance

A

Lessons Learned

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
50
Q

A dependency between two activities

A

Logical Relationship

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
51
Q

Time or money that management puts aside in addition to schedule or cost baseline and issues for unforeseen work that is within the scope of the project. This is not under the control of the project manager and will need an approved change request to access it.

A

Management Reserve

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
52
Q

An organizational structure in which the project manager shares authority with the functional manager

A

Matrix Organization

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
53
Q

A significant point or event in a project

A

Milestone

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
54
Q

a type of schedule that presents milestones with planned dates

A

Milestone Schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
55
Q

An estimate of the most probable activity duration that takes into account all of the known variables

A

Most Likely Duration

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
56
Q

A sequence of activities linked by logical relationships in a project schedule network diagram

A

Network Path

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
57
Q

A risk that would have a positive effect on one or more project objectives

A

Opportunity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
58
Q

An estimate of the shortest activity duration that takes into account all of the known variables

A

Optimistic Duration

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
59
Q

Plans, processes, policies, procedures, and knowledge bases specific to and used by the performing organization

A

Organizational Process Assets

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
60
Q

An estimating technique in which an algorithm is used to calculate cost or duration based on historical data and project parameters

A

Parametric Estimating

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
61
Q

A relationship in which a schedule activity has more than one predecessor

A

Path convergence

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
62
Q

An estimate expressed as a percent of hte amount of work that has been completed on an activity

A

Percent Complete

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
63
Q

An enterprise whose personnel are the most directly involved in doing the work of the project or program

A

Performing Organization

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
64
Q

An estimate of the longest activity duration that takes into account all of the known variables that could affect performance

A

Pessimistic Duration

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
65
Q

The authorized budget assigned to the scheduled work

A

Planned Value (PV)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
66
Q

Projects and programs, that are grouped together to achieve a strategic business goal

A

Portfolio

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
67
Q

The person or group assigned by the performing organization to establish, balance, monitor, and control portfolio components in order to achieve strategic business goals.

A

Portfolio Manager

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
68
Q

A technique used for building a schedule in which activities are represented by nodes and are graphically linked by one or more logical relationships to display the sequence in which the activities are to be performed

A

Precedence Diagramming Method

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
69
Q

An activity that comes before the dependent activity in a schedule

A

Predecessor Activity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
70
Q

An intentional activity that ensures the future performance of the project work is aligned with the project management plan

A

Preventive Action

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
71
Q

A table for diagramming the probability of occurrence of each of the risk and its impact on project objectives if that risk occurs

A

Probability and Impact Matrix

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
72
Q

A component of the project Management plan that describes how a team will acquire goods and services from an outside of the performing organization

A

Procurement Management Plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
73
Q

The series of phases that represent the evolution of a product, from concept through delivery to retirement

A

Product Life Cycle

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
74
Q

A group of related projects that are managed in a coordinated way to obtain benefits not available from managing them individually

A

Program

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
75
Q

A technique used to estimate project duration through a weighted average of optimistic, pessimistic, and most likely activity duration

A

Program Evaluation and Review Technique (PERT)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
76
Q

The application of knowledge, skills, tools, and techniques to a program to meet the program requirements and to obtain benefits and control not available by managing projects individually

A

Program Management

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
77
Q

The Person authorized by the performing organization to lead the team or teams responsible for achieving program objectives

A

Program Manager

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
78
Q

The iterative process of increasing the level of detail in a project management plan as greater amounts of information and more accurate estimates become available

A

Progressive Elaboration

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
79
Q

A temporary effort undertaken to create a unique product, service, or result

A

Project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
80
Q

A calendar that identifies working days and shifts that are available for scheduled activities

A

Project calendar

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
81
Q

A document issued by the project sponsor that formally authorizes the project and provides the project manager with the authority to apply organizational resources to project activities

A

Project charter

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
82
Q

The series of phases that a project goes through from its initiation to its closure

A

Project Life Cycle

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
83
Q

The application of knowledge, skills, tools, and techniques to project activities to meet the project requirements

A

Project Management

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
84
Q

A management structure that regulates the project-related governance processes and facilitates the sharing of resources, methodologies, tools and techniques

A

Project Management Office

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
85
Q

The document that defines how the project will be executed, monitored and controlled and cloaed

A

Project Management Plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
86
Q

The person assigned by the performing organization to lead the team that is responsible for achieving the project goals

A

Project Manager

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
87
Q

A collection of logically related project activities that culminates in the completion of one or more deliverables

A

Project Phase

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
88
Q

A graphical representation of the logical relationships around the schedule activities

A

Project Schedule Network Diagram

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
89
Q

The work achieved to deliver a product, service, or result with the specified features and functions

A

Project Scope

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
90
Q

The explanation of the project scope, major deliverables, assumptions, and constraints

A

Project Scope Statement

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
91
Q

An organizational structure in which the project manager has a full authority to assign work and resources

A

Projectized Organization

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
92
Q

A component of the project management plan that describes how an organizations quality policies will be implemented

A

Quality Management Plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
93
Q

A component of the project management plan that describes how requirements will be analyzed, documented, and managed

A

Requirements Management Plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
94
Q

A table that links requirements from their origin to the deliverables that satisfy them

A

Requirements Traceability Matrix

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
95
Q

The risk that is leftover after risk responses have been implemented

A

Residual Risk

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
96
Q

A ranked representation of resources by category type.

A

Resource Breakdown Structure

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
97
Q

A calendar that identifies the working days and shifts upon which each specific resource is available

A

Resource Calendar

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
98
Q

A component of the project management plan that describes the roles and responsibilities of the project team and management of the physical resources on the project.

A

Resource Management Plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
99
Q

a reource optimization technique in which changes are made to the project schedule to optimize the allocation of resources and which may affect critical path

A

Resource Leveling

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
100
Q

A technique in which activity start and finish dates are adjusted to balance demand for resources

A

Resource Optimization Technique

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
101
Q

A resource optimization technique in which total float are used without affecting the critical path

A

Resource Smoothing

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
102
Q

A grid that shows the project resources assigned to each work package

A

Responsibility Assignment Matrix

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
103
Q

An uncertain event that, if it occurs, has a positive or negative effect on one or more project objectives

A

Risk

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
104
Q

A risk response strategy where the project team decides to acknowledge the risk and not take any action unless the risk occurs

A

Risk Acceptance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
105
Q

The degree of uncertainty an organization or individual is willing to accept in hope of reward

A

Risk Appetite

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
106
Q

A risk response strategy whereby the project team acts to eradicate the threat or protect the project from its impact

A

Risk Avoidance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
107
Q

A ranked representation of the risks that organized according to risk categories

A

Risk Breakdown Structure

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
108
Q

A group of potential causes risk

A

Risk Category

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
109
Q

A Risk response strategy where the project team acts to increase the probability of occurrence or impact of an opportunity

A

Risk Enhancement

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
110
Q

A risk response strategy whereby the project team acts to ensure that an opportunity occurs

A

Risk Exploitation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
111
Q

A measure of the potential impact of all risks at any given point in time in a project

A

Risk Exposure

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
112
Q

A component of the project management plan that describes how risk management activities will be planned and performed

A

Risk Management Plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
113
Q

A Risk response strategy whereby the project team acts to reduce the probability of occurrence or impact of a threat

A

Risk Mitigation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
114
Q

A register in which outputs of risk management processes are recorded

A

Risk Register

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
115
Q

A risk responses strategy where the project team allocates ownership of an opportunity to at third party who is best able to capture the benefit for the project

A

Risk Sharing

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
116
Q

The level of risk exposure above which risks are addressed and under which risks may be accepted

A

Risk Threshhold

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
117
Q

The degree of uncertainty that an organization or individual is willing to endure

A

Risk Tollerance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
118
Q

An iterative planning technique in which the work to be accomplished in the near term is planned in detail, while the work in the future is planned at a higher level

A

Rolling Wave Planning

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
119
Q

The approved version of a schedule that can be changed using formal change control procedures and is used as the basis for comparison to actual results. It is part of the Project Management Plan

A

Schedule Baseline

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
120
Q

A method used to shorten the schedule duration without reducing project scope

A

Schedule Compression

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
121
Q

A component of the project management plan that establishes the criteria and the activities for developing , monitoring, and controlling the schedule

A

Schedule Management Plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
122
Q

A technique to identify early and late start dates, as well as early and late finish dates, for the unfinished portions of project activities

A

Schedule Network Analysis

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
123
Q

A measure of schedule efficiency expressed as the difference between the earned value and the planned value

A

Schedule Performance Index (SPI)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
124
Q

The approved version of a scope statement, Work Breakdown Structure (WBS), and its associated WBS dictionary that can be changed using formal change control procedures and is used as the basis for comparison to actual results. It is part of the project Management Plan

A

Scope Baseline

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
125
Q

a degree of schedule performance expressed as the difference between the earned value to planned value

A

Schedule Variance (SV)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
126
Q

The uncontrolled growth to project scope without adjustments to time, cost, and resources

A

Scope Creep

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
127
Q

A component of the project management plan that describes how the scope will be defined, developed, monitored, controlled, and validated

A

Scope Management Plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
128
Q

A technique used to indicate performance trends by using a graph that displays cumulative costs over a specific time period

A

S-Curve Analysis

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
129
Q

An individual or a group that provides resources and support for the project and is accountable for enabling success

A

Sponsor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
130
Q

An individual, group, or organization that may effect, be effected by, or perceive itself to be affected by a decision, activity, or outcome of a project

A

Stakeholder

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
131
Q

A component of the project management plan that defines how stakeholders will be engaged in a project decision making and execution

A

Stakeholder Management Plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
132
Q

A relationship in which a successor activity cannot finish until a predecessor activity has started

A

Start-to-Finish

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
133
Q

A relationship in which a successor activity cannot start until a predecessor activity has started

A

Start-to-Start

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
134
Q

A dependent activity that logically comes after another activity in a schedule

A

Successor Activity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
135
Q

A risk that would have a negative effect on one or more project objectives

A

Threat

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
136
Q

A technique used to estimate cost or duration by applying an average or weighted average of optimistic, pessimistic, and most likely estimates when there is uncertainty with the individual activity estimates

A

Three-Point Estimating

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
137
Q

A measure of the cost performance that is achieved with the remaining resources in order to meet a specified management goal, expressed as the ratio of the cost to finish outstanding work to the remaining budget

A

To-Complete Performance Index (TCPI)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
138
Q

The amount of time that a schedule activity can be late or extended from its early start date without delaying the project finish date or violating a schedule constraint

A

Total Float

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
139
Q

An event or situation that indicates that a risk is about to occur

A

Trigger Condition

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
140
Q

A technique for determining the cause and degree of difference between the baseline and actual performance

A

Variance Analysis

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
141
Q

A document that provides detailed deliverable, activity, and scheduling data about each component in the work breakdown schedule

A

WBS Dictionary

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
142
Q

The process of evaluating scenarios in order to predict their effect on project objectives

A

What-If Scenarios Analysis

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
143
Q

A hierarchical decomposition of the total scope of work to be carried out by the project team to accomplish the project objectives and create the deliverables

A

Work Breakdown Structure (WBS)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
144
Q

The work defined at the lowest level of the work breakdown structure for which cost and duration can be estimated and managed

A

Work Package

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
145
Q

An immediate and temporary response to an issue, for which a prior response had not been planned or was not effective

A

Workaround

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
146
Q

An effective tool for root cause analysis in which the question “Why?” is asked of a problem in succession until the root cause is found. Developed by Sakichi Toyoda, a Japanese inventor and industrialist, the 5 Whys method is an integral part of the Lean philosophy.

A

5 Whys Method

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
147
Q

A general guideline with many applications; in terms of controlling processes, it contends that a relatively large number of problems or defects, typically 80%, are commonly due to a relatively small number of causes, typically 20%

A

80/20 Rule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
148
Q

A marketing approach used to determine user preferences by showing different sets of users’ similar services—an ‘Alpha’ and a ‘Beta’ version—with one independent variable.

A

A/B Testing

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
149
Q

A communication technique that involves acknowledging the speaker’s message and the recipient clarifying the message to confirm that what was heard matches the message that the sender intended

A

Active Listening

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
150
Q

A distinct portion of work, scheduled with a beginning and an end, that must be performed to complete work on the project.

A

Activity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
151
Q

Multiple attributes associated with each activity that can be included within the activity list

A

Activity Attributes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
152
Q

Each task is assigned a budget, and the aggregate of these estimates results in the project budget. Activity cost estimates include labor, materials, equipment, and fixed cost items like contractors, services, facilities, financing costs, etc. This information can be presented in a detailed or summarized form.

A

Activity Cost Estimates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
153
Q

A logical relationship that exists between two project activities. The relationship indicates whether the start of an activity is contingent upon an event or input from outside the activity.

A

Activity Dependency

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
154
Q

The quantitative assessments of the likely number of time periods that are required to complete an activity.

A

Activity Duration Estimates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
155
Q

A documented tabulation of schedule activities that shows the activity description, activity identifier, and a sufficiently detailed scope-of-work description so project team members understand what work is to be performed.

A

Activity List

156
Q

A graphical diagram on which schedule activities are represented by nodes (rectangle boxes) and their dependencies are depicted by arrows.

A

Activity on Arrow or Activity on Node

157
Q

Material and human resources that are needed to complete an activity; often expressed by a probability or range.

A

Activity Resource Estimates

158
Q

The resources (physical, human, and organizational) required to complete the activities in the activity list.

A

Activity Resource Requirements

159
Q

A type of project life cycle or methodology that values responding to change over following a set plan. Adaptive methodologies seek solutions that deliver maximum value to the customer

A

Adaptive

160
Q

Involves verifying and documenting project results to formalize project or phase completion.

A

Administrative Closure

161
Q

A technique that allows large numbers of ideas to be classified into groups for review and analysis.

A

Affinity Diagram

162
Q

Technique designed to rapidly estimate large stories (epics or features) in the backlog. For example: T-Shirt sizing, coffee cup sizes, or Fibonacci sequence.

A

Affinity Estimating

163
Q

A term used to describe a mindset of values and principles as set forth in the Agile Manifesto.

A

Agile

164
Q

A process role on a project team that helps organizations achieve true agility by coaching teams across the enterprise on how to apply agile practices and choose their best way of working. See also “scrum master.”

A

Agile Coach

165
Q

An approach that assists with planning a project appropriately from the beginning to ensure the team can focus on the quality of each deliverable.

A

Agile Estimating

166
Q

An approach that is both iterative and incremental to refine work items and deliver frequently.

A

Agile Life Cycle

167
Q

A representation of the workflow of a process or system that the team can review before it is implemented in code.

A

Agile Modeling

168
Q

A person embracing the agile mindset who collaborates with like-minded colleagues in cross- functional teams. Also referred to as an agilist.

A

Agile Practitioner

169
Q

A process in which a team determines the number of iterations or Sprints that are needed to complete each release, the features that each iteration will contain, and the target dates of each release

A

Agile Release Planning

170
Q

Team space that encourages colocation, collaboration, communication, transparency, and visibility

A

Agile Space

171
Q

Any documents or communication that defines the initial intentions of a project. Examples include contracts, memorandums of understanding (MOUs), service-level agreements (SLAs), letters of agreement, letters of intent, verbal agreements, email, or other written agreements.

A

Agreements

172
Q

Costs that are allowed under the terms of the contract. Typically, allowable costs become relevant under certain types of cost-reimbursable contracts in which the buyer reimburses the seller’s allowable costs

A

Allowable Costs

173
Q

Logical approach that looks at the relationship between outcomes and the factors that can influence them.

A

Analytical Techniques

174
Q

Change requests that have been reviewed and approved by the change control board (CCB) and are ready to be scheduled for implementation.

A

Approved Change Requests

175
Q

Any project management processes, inputs, tools, techniques, outputs, EEFs, and OPAs that the project management team uses on their specific project. They are subject to configuration management and are maintained and archived by the team.

A

Artifact

176
Q

A process that explores the validity of the project assumptions within the constraints and identifies risks from any incompleteness or inaccuracy of these project assumptions.

A

Assumption and Constraint Analysis

177
Q

A list of all uncertainties that are treated as true for the purpose of planning.

A

Assumption Log

178
Q

Data that is counted such as the number of product defects or customer complaints

A

Attribute Sampling Data

179
Q

An examination of a project’s goals and achievements, including adequacy, accuracy, efficiency, effectiveness, and the project’s compliance with applicable methodologies and regulations. It tends to be a formal, one-sided process that can be extremely demoralizing to team members.

A

Audit

180
Q

A group decision-making method in which one member of the group makes the decision. In most cases, this person will consider the larger group’s ideas and decisions and will then make a decision based on that input.

A

Autocratic

181
Q

A strategy for managing negative risks or threats that involves changing the project management plan to remove the risk entirely by extending the schedule, changing the strategy, increasing the funding, or reducing the scope.

A

Avoid

182
Q

The prioritized list of all the work, presented in story form, for a project team

A

Backlog

183
Q

The progressive elaboration of project requirements and/or the ongoing activity in which the team collaboratively reviews, updates, and writes requirements to satisfy the need of the customer request.

A

Backlog Refinement

184
Q

A graphic display of schedule-related information. In the typical bar chart, schedule activities or WBS components are listed down the left side of the chart, dates are shown across the top, and activity duration’s are shown as date-placed horizontal bars.

A

Bar Chart

185
Q

The comparison of actual or planned products, processes, and practices to those of comparable organizations to identify best practices, generate ideas for improvement, and provide a basis for measuring performance.

A

Benchmarking

186
Q

The ratio of the expected benefits and the anticipated costs.

A

Benefit Cost Ratio (BCR)

187
Q

The documented explanation defining the processes for creating, maximizing, and sustaining the benefits provided by a project or program. It also describes how and when the benefits of a project will be derived and measured.

A

Benefits Management Plan

188
Q

The meetings with prospective sellers prior to the preparation of a bid or proposal to ensure all prospective vendors have a clear and common understanding of the procurement

A

Bidder Conferences

189
Q

A simple technique used to generate a list of ideas. It should be led by a facilitator with a group consisting of stakeholders, team members, and subject matter experts.

A

Brainstorming

190
Q

The failure to meet some or all the obligations of a contract.

A

Breach of Contract

191
Q

A time-phased plan for when funds will be disbursed on a project. It helps the organization anticipate when money will be coming in and/or going out, for the duration of the project.

A

Budget

192
Q

A planning term related to contingency.

A

Buffer

193
Q

A tool that is used to track the progress of the project by plotting the number of days of sprint against the number of hours of work remaining. It is used to communicate progress during and at the end of an iteration/sprint/ increment, showing the number of stores that have been completed and the ones that remain

A

Burn Chart

194
Q

The rate at which the project consumes financial resources, representing negative cash
flow.

A

Burn Rate

195
Q

A graphical representation of the work remaining versus the time left in a timebox.

A

Burndown Chart

196
Q

A graphical representation of the work completed toward the release of a product.

A

Burnup Chart

197
Q

A documented economic feasibility study used to establish the validity of the benefits of a selected component lacking sufficient definition and that is used as a basis for the authorization of further project management activities.

A

Business Case

198
Q

An artifact developed prior to the project, used as part of the business case, and which is reviewed periodically by a project professional to verify benefit delivery.

A

Business Document

199
Q

Listing of all requirements for a specific project.

A

Business Requirement Documents (BRD)

200
Q

The inherent risk in any business endeavor that carries the potential for either profit or loss. Types of business risks are competitive, legislative, monetary, and operational.

A

Business Risk

201
Q

The net quantifiable benefit derived from a business endeavor. The benefit may be tangible, intangible, or both.

A

Business Value

202
Q

The CMMI provides a framework for the integration of process improvement for multiple process areas. Associated with quality management

A

Capability Maturity Model Information (CMMI)

203
Q

This diagram shows the relationship between causes and effects. Primarily used in root cause analysis (risk and quality) to uncover the causes of risks, problems, or issues

A

Cause and Effect Diagram

204
Q

A legal document sent to an individual or a business with the direct intention of stopping specific activities and preventing their occurrence or recurrence.

A

Cease and Desist Letter

205
Q

A document used to request a project change. They can also be recommendations for taking corrective or preventive actions

A

Change Control Form

206
Q

A living list of all project change requests (CR). This log is used to track and provide accurate status of each CR (requester, owner, details, impact analysis, decision, etc.)

A

Change Log

207
Q

A comprehensive, cyclic, and structured approach for transitioning individuals, groups, and organizations from a current state to a future state in which they realize desired benefits

A

Change Management

208
Q

A component of the project management plan that establishes the Change Control Board, documents the extent of its authority, and describes how the change control system will be implemented.

A

Change Management Plan

209
Q

A shortened name for the project charter. A formal document that starts the project. Typically used by the project sponsor and the project manager, this document provides the reason for the project (based on business case) and may include high-level requirements, assumptions, constraints, milestone(s), and preliminary budget.

A

Charter

210
Q

A set of procedural instructions used to ensure that a product or component quality is achieved.

A

Checklist

211
Q

A technique for systematically reviewing materials using a list for accuracy and completeness.

A

Checklist Analysis

212
Q

An issue with the contract brought by one party against another. Claims must be resolved before the contract can be properly closed out.

A

Claim

213
Q

The process of finalizing all activities for the project, phase, or contract.

A

Close Project or Phase Process

214
Q

Sessions held at the end of a project or phase during which teams discuss work and capture lessons learned

A

Close-Out Meetings

215
Q

One of the five Project Management Process Groups. It consists of those processes performed to formally complete or close the project, phase, or contract.

A

Closing Process Group

216
Q

An agile servant leader role that exists to help the team and identify and remove any impediments (obstacles).

A

Coach

217
Q

The act of giving guidance and direction to another person to facilitate personal and/or professional growth and development.

A

Coaching

218
Q

A numbering system used to uniquely identify each component of the WBS.

A

Code of Accounts

219
Q

The act of working together and sharing information to create deliverables, work products or results.

A

Collaboration

220
Q

The process in which requirements documentation is developed. Precedes the Define Scope process.

A

Collect Requirements Process

221
Q

An organizational placement strategy in which the project team members are physically located close to one another to improve communication, working relationships, and productivity

A

Colocation

222
Q

A reason contributing to a quality problem that is usually considered acceptable. Common causes are considered unpreventable or if they are preventable, the cost of prevention would not justify the benefit.

A

Common Cause

223
Q

Act of accurately encoding, sending, receiving, decoding, and verifying messages. Communication between sender and receiver may be oral or written, formal or informal.

A

Communication

224
Q

The number of possible communication paths on a project. The formula for calculating communication channels is: [n(n-1)]/2; n=number of people on the project.

A

Communication Channels

225
Q

A systematic procedure, technique, or process used to transfer information among project stakeholders

A

Communication Method

226
Q

A description, analogy, or schematic used to represent how the communication process will be performed for the project.

A

Communication Models

227
Q

An analytical technique to determine the information needs of the project stakeholders through interviews, workshops, or study of lessons learned from previous projects, etc.

A

Communication Requirements Analysis

228
Q

A technique to identify the preferred communication method, format, and content for stakeholders for planned communication activities.

A

Communication Styles Assessment

229
Q

Specific tools, automated systems, computer programs, etc., used to transfer information among project stakeholders.

A

Communication Technology

230
Q

A type of contract that is completed when the vendor delivers the product to the buyer and the buyer accepts the product.

A

Completion Contract

231
Q

A characteristic of a program, project, or its environment, which is difficult to manage due to human behavior, system behavior, or ambiguity.

A

Complexity

232
Q

The state of meeting—or being in accord with—organizational, legal, certification or other relevant regulations.

A

Compliance

233
Q

An option in conflict management in which both parties give up something to reach an agreement.

A

Compromise

234
Q

The process of obtaining seller responses, selecting a seller, and awarding a contract.

A

Conduct Procurement Process

235
Q

Agile term describing the difficulty of estimating early due to unknowns and how that should improve over time.

A

Cone of Uncertainty

236
Q

Any component or project element that needs to be managed to ensure the successful delivery of the project, services, or result.

A

Configuration Item

237
Q

A tool used to manage changes to a product or service being produced as well as changes to any of the project documents—for example, schedule updates

A

Configuration Management

238
Q

A collection of procedures used to track project artifacts and monitor and control changes to these artifacts

A

Configuration Management System

239
Q

Difference of opinion or agenda on a project amongst team members, stakeholders, or customers.

A

Conflict

240
Q

The application of one or more strategies for dealing with disagreements that may be detrimental to team performance.

A

Conflict Management

241
Q

The process of working to reach an agreement after a conflict situation arises.

A

Conflict Resolution

242
Q

Group decision technique in which the group agrees to support an outcome even if the individuals do not agree with the decision.

A

Consensus

243
Q

A visual depiction of the product scope showing a business system (process, equipment, computer system, etc.), and how people and other systems (actors) interact with it.

A

Context Diagram

244
Q

A risk response strategy developed in advance, before risks occur; it is meant to be used if and when identified risks become reality

A

Contingency Plan

245
Q

A theory credited to Fred. E. Fielder which states that the set of skills and attributes that helped a project manager in one environment may work against them in another environment.

A

Contingency Theory

246
Q

The ongoing effort to improve products, services, or processes.

A

Continuous Improvement (CI)

247
Q

The practice of regularly merging all software code into a shared environment, several times a day, to check code quality and functionality.

A

Continuous Integration

248
Q

The systematic, ongoing effort to improve products, services, or processes in an organization.

A

Continuous Process Improvement

249
Q

A mutually binding agreement that obligates the seller to provide the specified project or service or result and obligates the buyer to pay for it

A

Contract

250
Q

The system used to collect, track, adjudicate, and communicate changes to a contract.

A

Contract Change Control System

251
Q

A management control point at which scope, budget, actual cost, and schedule are integrated and compared to earned value for performance measurement.

A

Control Account

252
Q

A graphic display of process data over time and against established control limits, which has a center-line that assists in detecting a trend of plotted values toward either control limit.

A

Control Charts

253
Q

Monitor and control project costs to ensure they align with the cost baseline/budget.

A

Control Costs Process

254
Q

The process of managing procurement relationships, monitoring contract performance, making changes and corrections as appropriate, and closing out contracts

A

Control Procurements Process

255
Q

Part of the Monitoring and Controlling Process Group, this process is performed by the buyer to ensure compliance by the seller and the other party; it compares the terms in the agreement/contract.

A

Control Procurement’s Process

256
Q

Part of the Monitoring and Controlling Process Group, this process focuses on the quality of deliverables

A

Control Quality Process

257
Q

Part of the Monitoring and Controlling Process Group, this process ensures that the flow and usage of physical resources line up with the plan.

A

Control Resources Process

258
Q

Part of the Monitoring and Controlling Process Group, this process compares the planned work to the actual work.

A

Control Schedule Process

259
Q

Part of the Monitoring and Controlling Process Group, this process ensures that changes to scope are properly controlled

A

Control Scope Process

260
Q

A type of PMO that provides support and requires compliance through various means

A

Controlling PMO

261
Q

Steps (action) to bring future results in line with the plan; this can change the plan or the way the plan is being executed

A

Corrective Action

262
Q

Summing the lower-level cost estimates associated with the various work packages for a given level within the project’s WBS or for a given cost control account.

A

Cost Aggregation

263
Q

The approved version of the time-phased project budget, excluding any management reserves, which can be changed only through formal change control procedures and is used as a basis for comparison to actual results.

A

Cost Baseline

264
Q

A financial analysis method used to determine the benefits provided by a project against its costs.

A

Cost-Benefit Analysis

265
Q

Cost estimates adjusted based on performance—i.e., Estimate at complete, budget at completion, estimate to complete, etc

A

Cost Forecast

266
Q

A component of a project or program management plan that describes how costs will be planned, structured, and controlled.

A

Cost Management Plan

267
Q

The money spent during a project to avoid failures. This includes prevention costs that build a quality product and appraisal costs that assess the quality

A

Cost of Conformance

268
Q

The money spent after a project is complete because of failures. This includes internal and external failure costs

A

Cost of Non-Conformance

269
Q

All costs incurred over the life of the product by investment in preventing non-conformance to requirements, appraisal of the product or service for conformance to requirements, and failure to meet requirements

A

Cost of Quality (CoQ)

270
Q

A measure of the cost efficiency of budgeted resources expressed as the ratio of earned value to actual cost.

A

Cost Performance Index (CPI)

271
Q

A category of contract that involves payments to the seller for all legitimate actual costs incurred for completed work, plus an award fee representing seller profit.

A

Cost Plus Award Fee (CPAF) contract

272
Q

A type of cost-reimbursable contract in which the buyer reimburses the seller for the seller’s allowable costs (allowable costs are defined by the contract) plus a fixed amount of profit (fee).

A

Cost Plus Fixed Fee (CPFF) contract

273
Q

A type of cost-reimbursable contract in which the buyer reimburses the seller for the seller’s allowable costs (allowable costs are defined by the contract), and the seller earns its profit if it meets defined performance criteria.

A

Cost Plus Incentive Fee (CPIF) contract

274
Q

The amount of budget deficit or surplus at a given point in time, expressed as the difference between the earned value and the actual cost

A

Cost Variance (CV)

275
Q

A cost-benefit analysis allows project managers to compare if the benefits of an action outweigh the costs or, conversely, if the costs outweigh the benefits.

A

Cost-Benefit Analysis

276
Q

A type of contract involving payment to the seller for the seller’s actual costs, plus a fee typically representing the seller’s profit.

A

Cost-Reimbursable Contract

277
Q

Applying additional resources to one or more tasks/activities to complete the work more quickly. Crashing usually increases costs more than risks.

A

Crashing

278
Q

The sequence of activities that represents the longest path through a project, which determines the shortest possible duration

A

Critical Path

279
Q

Teams that have all the capabilities to deliver the work they’ve been assigned. Team members can specialize in certain skills, but the team can deliver what they’ve been called on to build.

A

Cross-Functional Team

280
Q

Understanding the cultural differences of the individuals, groups, and organizations in the project stakeholder community to adapt communication strategies to avoid or reduce miscommunication and misunderstandings.

A

Cultural Awareness

281
Q

The individual or organization that will accept the deliverable(s) or product.

A

Customer

282
Q

Refers to the period from the time a team starts a task until the time it is completed.

A

Cycle Time

283
Q

A short, 15-minute meeting in which the complete team gets together for a quick status update while standing in a circle.

A

Daily Standup

284
Q

Refers to gathered empirical information, especially facts and numbers.

A

Data

285
Q

The act of scrutinizing facts and numbers for typical purposes of decision-making, verification, validation, or assessment.

A

Data Analysis

286
Q

Techniques used to solicit and document ideas—i.e., brainstorming, interviews, focus groups, questionnaires, surveys, and so on.

A

Data Gathering

287
Q

A way of depicting data visually to aid in its communication/comprehension to various audiences

A

Data Representation

288
Q

Regulations that are widely accepted and adopted through use.

A

De Facto Regulations

289
Q

Regulations that are mandated by law or have been approved by a recognized body of experts

A

De Jure Regulations

290
Q

An informal, collaborative means of discussing the positives and the negatives of a project, what worked, and what will be done differently next time.

A

Debriefing

291
Q

The process of selecting a course of action from among multiple options.

A

Decision Making

292
Q

A diagramming and calculation technique for evaluating the implications of a chain of multiple options in the presence of uncertainty.

A

Decision Tree Analysis

293
Q

A technique used for dividing and subdividing the project scope and project deliverables into smaller, more manageable parts.

A

Decomposition

294
Q

Part of the Planning Process Group, this process defines the activities (tasks) necessary to complete work packages/stories.

A

Define Activities Process

295
Q

Part of the Planning Process Group, this process produces the scope statement that depicts a detailed and complete understanding of the project’s vision.

A

Define Scope Process

296
Q

A team’s checklist of all the criteria required to be met so that a deliverable can be considered ready for customer use.

A

Definition of Done (DoD)

297
Q

A team’s checklist for a user-centric requirement that has all the information the team needs to be able to begin working on it.

A

Definition of Ready (DoR)

298
Q

Any unique and verifiable product, result, or capability used to perform a service and that is required to be produced to complete a process, phase, or projects.

A

Deliverable

299
Q

A form of gathering expert opinions in which members of a group are asked or polled anonymously.

A

Delphi Technique

300
Q

A review at the end of each iteration with the product owner and other customer stakeholders to review the progress of the product, get early feedback, and review an acceptance from the product owner of the stories delivered in the iteration

A

Demo

301
Q

A relationship between one or more tasks/activities. A dependency may be mandatory or discretionary, internal or external.

A

Dependency

302
Q

A set of technical guidelines that may be applied during the design of a product for the optimization of a specific aspect of the design.

A

Design for X (DfX)

303
Q

A data analysis technique to determine the optimal condition; typically used with multiple variables.

A

Design of Experiments (DoE)

304
Q

Part of the Planning Process Group, this process produces the cost baseline/project budget.

A

Determine Budget Process

305
Q

A collection of practices for creating a smooth flow of delivery by improving collaboration between development and operations staff.

A

DevOps

306
Q

Part of the Initiating Process Group, this process produces the project charter, which officially starts the project.

A

Develop Project Charter

307
Q

A planning process which is a guide on how the project will be managed. It is composed of 19 components

A

Develop Project Management Plan Process

308
Q

Part of the Planning Process Group, this process arranges activities to create the schedule baseline.

A

Develop Schedule Process

309
Q

Part of the Executing Process Group, this process enhances and empowers the team to improve teamwork and individual skills.

A

Develop Team Process

310
Q

Various means of depicting a system or virtual concept such as a business or process flow that indicate entities, relationships, and interactions

A

Diagramming Techniques

311
Q

A group decision technique in which one person makes the decision for the entire group.

A

Dictatorship

312
Q

Costs that are reported against the project, which may include salaries for resources, materials, and other expenses. It does not include shared expenses or overhead expenses.

A

Direct Cost

313
Q

A classification model that groups stakeholders based on how they influence the project and/or the project team: upwards (senior management); downwards (team or specialists); outwards (external); sidewards (project manager’s peers)

A

Directions of Influence

314
Q

A type of PMO that takes control of projects by directly managing the projects.

A

Directive PMO

315
Q

Breaking down epics or large stories into smaller stories. This is similar to decomposition on predictive projects.

A

Disaggregation

316
Q

A relationship that is established based on knowledge of best practices within a particular application area or an aspect of the project in which a specific sequence is desired.

A

Discretionary Dependency

317
Q

A technique used to gain project requirements from current document valuation.

A

Document Analysis

318
Q

Amount of time needed to complete an activity/task or work package.

A

Duration

319
Q

Used in a networking diagram, this represents the earliest date that the activity can finish

A

Early Finish

320
Q

Used in a networking diagram, this represents the earliest date that the activity can start.

A

Early Start

321
Q

A measure of work performed expressed in terms of the budget authorized for that work.

A

Earned Value (EV)

322
Q

A methodology that combines scope, schedule, and resource measurements to assess project performance and progress

A

Earned Value Management (EVM)

323
Q

Any or all environmental factors either internal or external to the project that can influence the project’s success to include culture, weather conditions, government regulations, political situation, market conditions, and so on.

A

EEF

324
Q

A way of analyzing the major risks inherent to a project that could have an impact on its success. These major risks include time, cost, quality, and scope.

A

Effect-Based Risk Classification

325
Q

The number of labor units required to complete a scheduled activity or WBS component, often expressed in hours, days, or weeks.

A

Effort

326
Q

The actual calendar time required for an activity from start to finish.

A

Elapsed Time

327
Q

The ability to identify, assess, and manage the personal emotions of oneself and other people, as well as the collective emotions of groups of people.

A

Emotional Intelligence (EI)

328
Q

Part of emotional intelligence (EQ or EI). The ability to understand others’ viewpoints and be a team player

A

Empathy

329
Q

An essential attribute of agile teams to enable localized decision-making capabilities. The quality of granting or being granted, nurturing, or motivating a team member or team to exercise one’s own knowledge, skill, and ability—or that of a team.

A

Empowerment

330
Q

Another name for “stakeholder engagement roadmap” - a guideline based on the stakeholder analysis that sets forth processes for engaging with stakeholders at current and all future states of the project.

A

Engagement Roadmap

331
Q

A strategy for managing positive risks or opportunities that involves increasing the probability that the opportunity will happen, or the impact it will have by identifying and maximizing enablers of these opportunities.

A

Enhance

332
Q

A block of work with one common objective, such as a feature, customer request or business requirement. A helpful way to organize work and create a hierarchy, epic helps teams break their work down, while continuing to work towards a bigger goal.

A

Epic

333
Q

The act of seeking helpful intervention in response to a threat that is outside the scope of the project or beyond the project manager’s authority.

A

Escalate

334
Q

A number, figure, or representation that denotes cost or time.

A

Estimate

335
Q

The expected total cost of completing all work expressed as the sum of the actual cost to date and the estimate to complete

A

Estimate at Completion (EAC)

336
Q

Part of the Planning Process Group, this process determines the financial estimate for each work package and/or activity.

A

Estimate Costs Process

337
Q

The expected cost of finishing all the remaining project work.

A

Estimate to Complete (ETC)

338
Q

Motivational theory which proposes that the team makes choices based on the expected outcome

A

Expectancy Theory

339
Q

Judgment provided based upon expertise in an application area, knowledge area, discipline, industry, etc., as appropriate for the activity being performed.

A

Expert Judgment

340
Q

Knowledge that can be codified using symbols such as words, numbers, and pictures. This type of knowledge can be easily documented and shared with others.

A

Explicit Knowledge

341
Q

A strategy for managing positive risks or opportunities that involves attempting to make sure that the opportunity happens.

A

Exploit

342
Q

Types of activity dependencies that exist between project activities and non-project activities and can be out of the project’s control

A

External Dependency

343
Q

Agile methodology in which iterations last for one week and programmers work in pairs.

A

Extreme Programming (XP)

344
Q

Organized working sessions held by project managers to determine a project’s requirements and to get all stakeholders together to agree on the project’s outcomes.

A

Facilitated Workshops

345
Q

A skill used to lead or guide an assembled group toward a successful conclusion such as making a decision or finding a solution.

A

Facilitation

346
Q

A schedule compression technique in which activities or phases normally done in sequence are performed in parallel for at least a portion of their duration.

A

Fast Tracking

347
Q

A group of stories that delivers value to the customer

A

Feature

348
Q

A logical relationship in which a successor activity cannot finish until a predecessor activity has finished.

A

Finish-to-Finish (FF)

349
Q

A logical relationship in which a successor activity cannot start until a predecessor activity has finished.

A

Finish-to-Start (FS)

350
Q

A type of fixed price contract in which the buyer pays the seller a set amount (as defined by the contract), regardless of the seller’s costs.

A

Firm Fixed Price Contract (FFP)

351
Q

An agreement that sets the fee that will be paid for a defined scope of work regardless of the cost or effort to deliver it.

A

Fixed Price Contract

352
Q

A type of contract in which the buyer pays the seller a set amount (as defined by the contract), and the seller can earn an additional amount if the seller meets defined performance criteria

A

Fixed Price Incentive Fee (FPIF) contract

353
Q

A fixed-price contract, but with a special provision allowing for pre-defined final adjustments to the contract price due to changed conditions, such as inflation changes, or cost increases (or decreases) for specific commodities

A

Fixed Price with Economic Price Adjustment (FPEPA) contract

354
Q

An elicitation technique that brings together pre-qualified stakeholders and subject matter experts to learn about their expectations and attitudes about a proposed product, service, or result.

A

Focus Groups

355
Q

Technique for calculating the early start and early finish dates of the schedule activities. This is part of the critical path method and is paired with backward pass to determine activity and schedule float along with the critical path.

A

Forward Pass

356
Q

Supervisory organizational role in a specialized area or department.

A

Functional Manager

357
Q

An organizational structure in which staff is grouped by areas of specialization and the project manager has limited authority to assign work and apply resources.

A

Functional Organization

358
Q

In an agile context, an action that the system performs that adds value to the customer/user

A

Functionality

359
Q

Adding more scope than the customer requested and/or that the team planned for.

A

Gold Plating

360
Q

Expectations regarding acceptable behavior by project team members.

A

Ground Rules

361
Q

A bar or column chart that graphically represents numerical data—for example, the number of defects per deliverable, a ranking of the cause of defects, the number of times each process is noncompliant, or other representations of project or product defects

A

Histogram

362
Q

Archived information from previous projects that can be used for a multitude of reasons, including estimating cost, schedule, resources, and lessons learned.

A

Historical Information

363
Q

An estimation technique that refers to the time it would take to complete a given task assuming neither interruptions nor unplanned problems arise

A

Ideal Time

364
Q

An obstacle that prevents the team from achieving its objectives

A

Impediment

365
Q

A functional, tested, and accepted deliverable that is a subset of the overall project utcome.

A

Increment

366
Q

Agile concept that the functionality should be delivered in small pieces or stages rather than as a complete solution

A

Incremental Delivery

367
Q

An adaptive project life cycle in which the deliverable is produced through a series of iterations that successively add functionality within a predetermined time frame.

A

Incremental Life Cycle

368
Q

A cost usually tracked as part of a contract, that is not expended directly for the project’s benefit.

A

Indirect Costs

369
Q

Used in quality management decisions. A graphical representation of situations showing causal influences, time ordering of events, and other relationships among variables and outcomes.

A

Influence Diagram

370
Q

Used in stakeholder management. A classification model that groups stakeholders on the basis of their involvement in and impact on the project.

A

Influence/Impact Grid

371
Q

The act of presenting a good case to explain why an idea, decision, or problem should be handled a certain way, without resistance from other individuals

A

Influencing

372
Q

Data that has been analyzed, organized, and processed to make it more meaningful.

A

Information

373
Q

A system to allow the team to collaborate, share, and capture project work.

A

Information Management

374
Q

A way to collect, manage, and distribute project information

A

Information Management System

375
Q

A risk that has only the potential for loss and no potential for profit or gain

A

Insurable Risk

376
Q

In an agile context, this generally refers to face-to-face conversations between members, customers and stakeholders

A

Interactions

377
Q

An exchange of information between two or more individuals that ensures common understanding for everyone participating in that exchange

A

Interactive Communication

378
Q

A type of activity dependency that exists between project activities and is usually under the project’s control

A

Internal Dependency

379
Q

The interest rate that makes the net present value of all cash flow equal to zero. This rate is a function of the cost of capital for project implementation

A

Internal Rate of Return (IRR)

380
Q

Skills used to establish and maintain relationships with other people or stakeholders.

A

Interpersonal Skills

381
Q

A type of procurement document most commonly used when deliverables are commodities for which there are clear specifications and when quantities are very large. The invitation is usually advertised, and any seller may submit a bid.

A

Invitation for Bid (IFB)

382
Q

A current condition or situation that may have an impact on the project objectives.

A

Issue

383
Q

An issue is a current condition or situation that may have an impact on the project objectives. An issue log is used to record and monitor information on active issues. Issues are assigned to a responsible party for follow up and resolution.

A

Issue Log

384
Q

A timeboxed cycle of development on a product or deliverable in which all the work needed to deliver value is performed.

A

Iteration

385
Q

The work that is committed to be performed during a given iteration and is expected to burn down the duration. The work does not carry over to the next iteration.

A

Iteration Backlog

386
Q

A project life cycle in which the project scope is generally determined early in the project life cycle, but time and cost estimates are routinely modified as the project team’s understanding of the product/service increases. . Iterations progressively develop the product/service through a series of repeated cycles, while increments successively add
to the functionality of the product/service

A

Iterative Life Cycle