Definitions Flashcards
a Set of conditions that are met before deliverables are accepted by the customers
Acceptance Criteria
A distinct, scheduled portion of work performed during the project. Usually stored on the activity list
Activity
The actual cost incurred for the work performed on an activity during a specific time period
Actual Cost (AC)
A technique for estimating the duration or cost of activity or a project using using historical data from a similar activity or project. Also know as top-down estimating.
Analogous Estimating
A factor in the planning processes considered to be true or real without proof or demonstration
Assumption
A critical path method technique for computing the late start and late finish dates by working backwards through the schedule model from the project end date
Backward Pass
The accepted version of a work product that can be changed using formal change control processes and is used as the basis for comparison to actual results
Baseline
A method of estimating project duration or cost by aggregating the estimates of the lower-level components of the work breakdown structure (WBS)
Bottom-Up Estimate
The amount of all budgets established for the work to be performed
Budget at Completion (BAC)
A process whereby changes to documents , deliverables, or baselines related with the project are identified, documented, approved, or rejected
Change Control
A formally commissioned group responsible for reviewing, assessing, approving, deferring, or rejecting changes to the project, and for recording and communicating such decisions
Change Control Board
A set of procedures that defines how modifications to the project deliverables and documentation are managed and controlled
Change Control System
A formal proposal to change any document, deliverable, or baseline in the project management plan
Change Request
A component of the project management plan that describes how, when, and by whom information will be administered and distributed
Communications Management Plan
A collection of procedures used to track project artifacts and monitor and control changes to these artifacts
Configuration Management System
A restrictive feature that affects the execution of a project
Constraint
Time or money assigned in the schedule or cost baseline for known risks with response strategies
Contingency Reserves
A planned activity that restores the performance of the project work with the project management plan
Corrective Action
The approved version of work package cost estimates and contingency reserve that can be changed using formal change control procedures
Cost Baseline
A Component of a project management plan that defines how costs will be planned and controlled
Cost Management Plan
A Measure of the cost efficiency of budgeted resources expressed as the ratio of earned value to actual cost
Cost Performance Index (CPI)
The Amount of budget shortfall or surplus at a given point in time, expressed as the difference between earned value and the actual cost
Cost Variance
A schedule compression technique used to shorten the schedule duration by adding resources. This will greatly increase project Cost
Crashing
A schedule method that allows the project team to place buffers on a project schedule path to account for limited resources
Critical Chain Method
The sequence of activities that represents the longest path through a project, which determines the shortest possible duration . Activities on this path of ZERO float
Critical Path
Any activity on the critical path in a project schedule
Critical PAth Activity
A method used to estimate the minimum project duration and determine the amount of scheduling flexibility on the logical network paths within the schedule
Critical Path Method
A technique used for dividing and subdividing the project deliverables into smaller, more manageable parts. Also used to subdivide the project activities.
Decmoposition
An intentional activity to modify a nonconforming product or product component
Defect Repair
Part of the product that is presented to the customer or stakeholders for acceptance
Deliverable
The total number of work periods required to complete an activity or work breakdown structure component, expressed in hours, days or weeks
Duration
The earliest an activity can finish without delaying the project end date
Early Finish Date
The earliest an activity can start without delaying the project end date
Early Start Date
The amount of money worth of work actually accomplished on the project
Earned Value (EV)
A methodology that combines scope, schedule, and resource measurements to assess project performance
Earned Value Management
Conditions, not under the immediate control of the team, that influence, constrain, or direct the project
Enterprise Environmental Factors
The forecast of the total cost of the project at the end based on the current spending rate of the project
Estimate at Completion (EAC)
The amount of money that will be needed to complete the current project based on the current performance
Estimate to Complete (ETC)
A schedule compression technique in which activities or phases are done in parallel for at least a portion or the entire duration. This can increase the risk on the project
Fast Tracking
A relationship in which a successor activity cannot finish until a predecessor activity has finished
Finish-to-Finish
A relationship in which a successor activity cannot start until a predecessor activity has finished
Finish-to-Start
A critical path method technique for calculating the early start and early finish dates by working forward through the schedule
Forward Pass
An organizational structure in which staff is grouped by areas of specialization and the project manager has limited authority
Functional Organization
A bar chart of schedule information where activities are listed. Generally part of the project schedule
Gantt Chart
The amount of time whereby a successor activity will be delayed to a predecessor activity
Lag
The latest an activity can finish without delaying the project end date
Late Finish Date
The Latest an activity can start without delaying the project end date
Late Start Date
The amount of time where a successor activity can be started before the predecessor activity finishes
Lead
The data gained during a project which shows how project events were addressed or should be addressed in the future for the purpose of improving future performance
Lessons Learned
A dependency between two activities
Logical Relationship
Time or money that management puts aside in addition to schedule or cost baseline and issues for unforeseen work that is within the scope of the project. This is not under the control of the project manager and will need an approved change request to access it.
Management Reserve
An organizational structure in which the project manager shares authority with the functional manager
Matrix Organization
A significant point or event in a project
Milestone
a type of schedule that presents milestones with planned dates
Milestone Schedule
An estimate of the most probable activity duration that takes into account all of the known variables
Most Likely Duration
A sequence of activities linked by logical relationships in a project schedule network diagram
Network Path
A risk that would have a positive effect on one or more project objectives
Opportunity
An estimate of the shortest activity duration that takes into account all of the known variables
Optimistic Duration
Plans, processes, policies, procedures, and knowledge bases specific to and used by the performing organization
Organizational Process Assets
An estimating technique in which an algorithm is used to calculate cost or duration based on historical data and project parameters
Parametric Estimating
A relationship in which a schedule activity has more than one predecessor
Path convergence
An estimate expressed as a percent of hte amount of work that has been completed on an activity
Percent Complete
An enterprise whose personnel are the most directly involved in doing the work of the project or program
Performing Organization
An estimate of the longest activity duration that takes into account all of the known variables that could affect performance
Pessimistic Duration
The authorized budget assigned to the scheduled work
Planned Value (PV)
Projects and programs, that are grouped together to achieve a strategic business goal
Portfolio
The person or group assigned by the performing organization to establish, balance, monitor, and control portfolio components in order to achieve strategic business goals.
Portfolio Manager
A technique used for building a schedule in which activities are represented by nodes and are graphically linked by one or more logical relationships to display the sequence in which the activities are to be performed
Precedence Diagramming Method
An activity that comes before the dependent activity in a schedule
Predecessor Activity
An intentional activity that ensures the future performance of the project work is aligned with the project management plan
Preventive Action
A table for diagramming the probability of occurrence of each of the risk and its impact on project objectives if that risk occurs
Probability and Impact Matrix
A component of the project Management plan that describes how a team will acquire goods and services from an outside of the performing organization
Procurement Management Plan
The series of phases that represent the evolution of a product, from concept through delivery to retirement
Product Life Cycle
A group of related projects that are managed in a coordinated way to obtain benefits not available from managing them individually
Program
A technique used to estimate project duration through a weighted average of optimistic, pessimistic, and most likely activity duration
Program Evaluation and Review Technique (PERT)
The application of knowledge, skills, tools, and techniques to a program to meet the program requirements and to obtain benefits and control not available by managing projects individually
Program Management
The Person authorized by the performing organization to lead the team or teams responsible for achieving program objectives
Program Manager
The iterative process of increasing the level of detail in a project management plan as greater amounts of information and more accurate estimates become available
Progressive Elaboration
A temporary effort undertaken to create a unique product, service, or result
Project
A calendar that identifies working days and shifts that are available for scheduled activities
Project calendar
A document issued by the project sponsor that formally authorizes the project and provides the project manager with the authority to apply organizational resources to project activities
Project charter
The series of phases that a project goes through from its initiation to its closure
Project Life Cycle
The application of knowledge, skills, tools, and techniques to project activities to meet the project requirements
Project Management
A management structure that regulates the project-related governance processes and facilitates the sharing of resources, methodologies, tools and techniques
Project Management Office
The document that defines how the project will be executed, monitored and controlled and cloaed
Project Management Plan
The person assigned by the performing organization to lead the team that is responsible for achieving the project goals
Project Manager
A collection of logically related project activities that culminates in the completion of one or more deliverables
Project Phase
A graphical representation of the logical relationships around the schedule activities
Project Schedule Network Diagram
The work achieved to deliver a product, service, or result with the specified features and functions
Project Scope
The explanation of the project scope, major deliverables, assumptions, and constraints
Project Scope Statement
An organizational structure in which the project manager has a full authority to assign work and resources
Projectized Organization
A component of the project management plan that describes how an organizations quality policies will be implemented
Quality Management Plan
A component of the project management plan that describes how requirements will be analyzed, documented, and managed
Requirements Management Plan
A table that links requirements from their origin to the deliverables that satisfy them
Requirements Traceability Matrix
The risk that is leftover after risk responses have been implemented
Residual Risk
A ranked representation of resources by category type.
Resource Breakdown Structure
A calendar that identifies the working days and shifts upon which each specific resource is available
Resource Calendar
A component of the project management plan that describes the roles and responsibilities of the project team and management of the physical resources on the project.
Resource Management Plan
a reource optimization technique in which changes are made to the project schedule to optimize the allocation of resources and which may affect critical path
Resource Leveling
A technique in which activity start and finish dates are adjusted to balance demand for resources
Resource Optimization Technique
A resource optimization technique in which total float are used without affecting the critical path
Resource Smoothing
A grid that shows the project resources assigned to each work package
Responsibility Assignment Matrix
An uncertain event that, if it occurs, has a positive or negative effect on one or more project objectives
Risk
A risk response strategy where the project team decides to acknowledge the risk and not take any action unless the risk occurs
Risk Acceptance
The degree of uncertainty an organization or individual is willing to accept in hope of reward
Risk Appetite
A risk response strategy whereby the project team acts to eradicate the threat or protect the project from its impact
Risk Avoidance
A ranked representation of the risks that organized according to risk categories
Risk Breakdown Structure
A group of potential causes risk
Risk Category
A Risk response strategy where the project team acts to increase the probability of occurrence or impact of an opportunity
Risk Enhancement
A risk response strategy whereby the project team acts to ensure that an opportunity occurs
Risk Exploitation
A measure of the potential impact of all risks at any given point in time in a project
Risk Exposure
A component of the project management plan that describes how risk management activities will be planned and performed
Risk Management Plan
A Risk response strategy whereby the project team acts to reduce the probability of occurrence or impact of a threat
Risk Mitigation
A register in which outputs of risk management processes are recorded
Risk Register
A risk responses strategy where the project team allocates ownership of an opportunity to at third party who is best able to capture the benefit for the project
Risk Sharing
The level of risk exposure above which risks are addressed and under which risks may be accepted
Risk Threshhold
The degree of uncertainty that an organization or individual is willing to endure
Risk Tollerance
An iterative planning technique in which the work to be accomplished in the near term is planned in detail, while the work in the future is planned at a higher level
Rolling Wave Planning
The approved version of a schedule that can be changed using formal change control procedures and is used as the basis for comparison to actual results. It is part of the Project Management Plan
Schedule Baseline
A method used to shorten the schedule duration without reducing project scope
Schedule Compression
A component of the project management plan that establishes the criteria and the activities for developing , monitoring, and controlling the schedule
Schedule Management Plan
A technique to identify early and late start dates, as well as early and late finish dates, for the unfinished portions of project activities
Schedule Network Analysis
A measure of schedule efficiency expressed as the difference between the earned value and the planned value
Schedule Performance Index (SPI)
The approved version of a scope statement, Work Breakdown Structure (WBS), and its associated WBS dictionary that can be changed using formal change control procedures and is used as the basis for comparison to actual results. It is part of the project Management Plan
Scope Baseline
a degree of schedule performance expressed as the difference between the earned value to planned value
Schedule Variance (SV)
The uncontrolled growth to project scope without adjustments to time, cost, and resources
Scope Creep
A component of the project management plan that describes how the scope will be defined, developed, monitored, controlled, and validated
Scope Management Plan
A technique used to indicate performance trends by using a graph that displays cumulative costs over a specific time period
S-Curve Analysis
An individual or a group that provides resources and support for the project and is accountable for enabling success
Sponsor
An individual, group, or organization that may effect, be effected by, or perceive itself to be affected by a decision, activity, or outcome of a project
Stakeholder
A component of the project management plan that defines how stakeholders will be engaged in a project decision making and execution
Stakeholder Management Plan
A relationship in which a successor activity cannot finish until a predecessor activity has started
Start-to-Finish
A relationship in which a successor activity cannot start until a predecessor activity has started
Start-to-Start
A dependent activity that logically comes after another activity in a schedule
Successor Activity
A risk that would have a negative effect on one or more project objectives
Threat
A technique used to estimate cost or duration by applying an average or weighted average of optimistic, pessimistic, and most likely estimates when there is uncertainty with the individual activity estimates
Three-Point Estimating
A measure of the cost performance that is achieved with the remaining resources in order to meet a specified management goal, expressed as the ratio of the cost to finish outstanding work to the remaining budget
To-Complete Performance Index (TCPI)
The amount of time that a schedule activity can be late or extended from its early start date without delaying the project finish date or violating a schedule constraint
Total Float
An event or situation that indicates that a risk is about to occur
Trigger Condition
A technique for determining the cause and degree of difference between the baseline and actual performance
Variance Analysis
A document that provides detailed deliverable, activity, and scheduling data about each component in the work breakdown schedule
WBS Dictionary
The process of evaluating scenarios in order to predict their effect on project objectives
What-If Scenarios Analysis
A hierarchical decomposition of the total scope of work to be carried out by the project team to accomplish the project objectives and create the deliverables
Work Breakdown Structure (WBS)
The work defined at the lowest level of the work breakdown structure for which cost and duration can be estimated and managed
Work Package
An immediate and temporary response to an issue, for which a prior response had not been planned or was not effective
Workaround
An effective tool for root cause analysis in which the question “Why?” is asked of a problem in succession until the root cause is found. Developed by Sakichi Toyoda, a Japanese inventor and industrialist, the 5 Whys method is an integral part of the Lean philosophy.
5 Whys Method
A general guideline with many applications; in terms of controlling processes, it contends that a relatively large number of problems or defects, typically 80%, are commonly due to a relatively small number of causes, typically 20%
80/20 Rule
A marketing approach used to determine user preferences by showing different sets of users’ similar services—an ‘Alpha’ and a ‘Beta’ version—with one independent variable.
A/B Testing
A communication technique that involves acknowledging the speaker’s message and the recipient clarifying the message to confirm that what was heard matches the message that the sender intended
Active Listening
A distinct portion of work, scheduled with a beginning and an end, that must be performed to complete work on the project.
Activity
Multiple attributes associated with each activity that can be included within the activity list
Activity Attributes
Each task is assigned a budget, and the aggregate of these estimates results in the project budget. Activity cost estimates include labor, materials, equipment, and fixed cost items like contractors, services, facilities, financing costs, etc. This information can be presented in a detailed or summarized form.
Activity Cost Estimates
A logical relationship that exists between two project activities. The relationship indicates whether the start of an activity is contingent upon an event or input from outside the activity.
Activity Dependency
The quantitative assessments of the likely number of time periods that are required to complete an activity.
Activity Duration Estimates