DDS Flashcards

1
Q

If the CAMS (control and monitoring panel) is OOC or performance is suspect what may be used in its place to monitor CO2?

A

GEOTECH Monitor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is a LOC?

A

Lock Out Chamber

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is the max allowable CO2 for the GEOTECH CO2 monitor and the CAMS?

A

1000 ppm (GEOTECH)

1000 ppm / 0.76 torr (CAMS)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What checks need to be accomplished prior to entry of the DDS?

A

Check for the presence of water and ventilated for 5 min

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What speed and depth must the host ship not exceed when divers are outside the DDS?

A

1-1/2 knots

130 FSW (host ships deck)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is considered acceptable for the ambient air concentration of hydrogen?

A

3 % or lower (acceptable)

  • 4% -8% (ignite if lit)
  • <8% (EXPLOSION)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

During a electrical guard fault/hangar power circuit fault what must be done prior to switching the S2 switch to the both position?

A

Switch S1 to the off position

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What are the SDV batteries made of and what gas do they produce?

A

Silver Zinc Cells which produce hydrogen gas

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What are the 3 components of the DDS?

A
  1. Chamber
  2. Hangar
  3. Trunk
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What CO2 level constitutes ventilation of each compartment?

A

20,000 ppm (2%)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

If loss electrical power/ short circuit or CO2 scrubber/heater during O2 treatment or during high O2 in the chamber, what should you not do to troubleshoot until decompression treatment is completed?

A

Turn the breakers on and off

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

What is the maximum authorized depth in the hangar?

A

130 fsw

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

What is the minimal manning of the DDS whenever the LOC upper hatch is shut?

A

2 DDS operators

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

How much does the fairing weigh?

A

400 lbs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

How much is the DDS hoist rated to?

A

2000lbs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

How much does the DDS watertight door weigh?

23
Q

Using the ships HP blow from below what keel depth will exceed the maximum ascent rate for divers?

24
Q

Where do you find information about installing secondary cradle restrain straps prior to surfacing?

A

Appendix G & Figure G-1

25
Q

In the event of an injured diver, who can recommend the depth of transfer trunk to 60 FSW?

26
Q

If the SHF-1 will not shut and the SDV is present the host ship shall not dive deeper than how many FSW?

27
Q

If the SHF-1 will not shut and the SDV is not present the host ship shall not dive deeper than how many FSW?

28
Q

If SHF-1 fails to shut with waves higher 4 feet, what must be done?

A

The hangar door stop link and pin shall be inspected for deformity

29
Q

Training for SHF-1 not shutting (SEP-23), if authorized if wave height is lower than what?

31
Q

When the GEOTECH/CAMS reaches 2000 ppm (1.5 torr) divers must go on emergency breathing source at what boat pressure?

32
What degree of the ship’s roll prevents the LOC upper hatch from being opened, unless in an emergency?
10 degrees
35
What is the minimum allowable head pressure during drain down?
10 FSW
36
Above what PPO2 percentage increases fire hazard?
22%
40
What is the maximum authorized depth in the transfer trunk?
165 FSW
43
How frequently must operators report to the dive sup during any pressurization or depressurization?
Every 10 FSW
44
At what PPM do the CO2 monitors alarm?
15,000 ppm
45
What are the useful periods of no ventilation?
Hangar : 12,000 ppm SEV Hangar Bubble : 5,000 ppm SEV Transfer Trunk : 8000 ppm SEV Chanber : 8,000 ppm SEV
46
How long does the GEOTECH monitor readings lag behind current conditions?
Approximately 70 sec
47
For ventilation shallower than what FSW shall the vent valve be fully opened?
7 FSW