CSE - Category IV – Bidding/Construction (20%) Flashcards
AIA G701 - Change Order
- Prepared by Architect
- Change in time OR cost (or both) to the original contact
- Description of the change and cost or time adjustment
- Singed by the Architect, Owner and Contractor
AIA G710
Supplemental Instructions
- Additional instructions or interpretations prepared by Architect
- Minor changes in work
- Assist Architect in performing obligations as interpreter of contract documents
- NO change in contract time or sum
- Only requires the Architects Signature
AIA G714
Construction Change Directive
- Written order prepared by the Architect
- Signed by the Architect and Owner
- Directs as change in work prior to agreement on adjustment in the Contract Sum, or Contract Time
- Is used in the absence of the total agreement on the terms of a Change Order
- Can also be used in fast-track projects
Applications for Payment
Based on the Architect’s evaluation of the Contractor’s Applications for Payment, the Architect will review and certify the amounts due the Contractor and will issue Certificates for Payment in such amounts.
Certificate of Occupancy
- Issued by the local Building Official after conducting final inspection and walk through with the Contractor.
- Once the Certificate of Occupancy is issued, the Owner can legally occupy the building.
Certificate of Substantial Completion
- Part of project close-out
- Establishes the responsibilities of the Owner and Contractor for security, maintenance, heat, utilities, damage to the work and insurances
- Warranty period begins
- Release of Retainage
- Sets the clock for Statute of Limitations beginning
Certificates for Payment
The Architect, within 7 days after receipt of the Contractor’s Application for payment:
- Issue to the Owner a Certificate of Payment
OR
- Notify the Contractor and Owner in writing the reasons for withholding payment.
Change Order
- Any modification or change to works agreed in the contract is treated as a variation.
- These modifications can be divided into three main categories
- Addition to the work agreed in the contract.
- Omission of work agreed in the contract.
- Substitution or alteration of work agreed in the contract.
Close-out Procedures - Contractor Role
Close-out Procedures - Owner Role
Close-out Procedures - Architect Role
Construction Change Directive
Process for the owner of a construction project to instruct the contractor to perform work in addition to what has been agreed to in the contract.
Contract Sum
The total amount payable by the Owner to the Contractor for performace of the Work under the Contract Documents.
Cost of Work
- The cost of work is the total of all costs incurred by the owner (excluding GST) that relate directly and indirectly to building and construction work.
- The direct costs necessarily incurred by CM@Risk in the proper performance of the Work.
- Cost of the Work may include direct labor costs, subcontract costs, costs of materials and equipment incorporated in the completed Work, costs of other materials and equipment, temporary facilities, building permit fees, materials testing, and related items.
- Cost of the Work shall not include CM@Risk’s Construction Fee, general conditions fee, taxes, bonds, or insurance costs.*
Decisions to Withhold Certificaiton
- If work on the Application does not match work completed in field.
- If Architect and Contractor cannot agree, Architect will issue Application of Certificate of Payment to Owner for the amount Architect believes is accurate.