critical path analysis Flashcards

1
Q

CPA

A

A method of calculating the minimum time required to complete a project, identifying delays which could be crucial to completion.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

benefits

A

allows higher efficiency (machinery and labour)
decision making (where to allocate resources)
time based management
working capital control (prevents wastage of financial resources)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

limitations

A

based on estimations (can cause delays and fines)
not accepting another project
changes can occur in life of project e.g breakages
can be complex with bigger projects e.g building site

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

total float

A

time a task can be delayed without affecting the whole project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

how is total float calculated

A

latest finish- earliest start- duration

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

free float

A

time a task can be delayed without affecting the following task

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

how is free float calculated

A

earliest start (of next task)-earliest start (of this task)-duration

How well did you know this?
1
Not at all
2
3
4
5
Perfectly