critical path analysis Flashcards
CPA
A method of calculating the minimum time required to complete a project, identifying delays which could be crucial to completion.
benefits
allows higher efficiency (machinery and labour)
decision making (where to allocate resources)
time based management
working capital control (prevents wastage of financial resources)
limitations
based on estimations (can cause delays and fines)
not accepting another project
changes can occur in life of project e.g breakages
can be complex with bigger projects e.g building site
total float
time a task can be delayed without affecting the whole project
how is total float calculated
latest finish- earliest start- duration
free float
time a task can be delayed without affecting the following task
how is free float calculated
earliest start (of next task)-earliest start (of this task)-duration