Why is a BoQ critical to project success?

A

It lays out all works that need to be completed, that make up the contract sum. It allows you to ensure that you have let all works.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are the risks around using a LOI?

A

The contract is not signed.
There is no allowance for LADs.
There is no formal contract entered into.
Liability is capped.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What does the term vesting mean?

A

Gaining full ownership of an asset, usually materials off site.