Case Study Flashcards

1
Q

Key Issue 1 - Option 1
Why would administering the contract correctly be seen as negative?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

If the subcontractors have been overpaid why would adjusting their accounts correctly be an issue?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What did your directors think about not being aggressive in recouping the overspend?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What was the overspend?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What was the action to take with the upstream account - how were you being contractual?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Option 2 -
Why would waiting have such a negative effect if the sub contractors had more money than they were entitled to?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Describe how the sub contractor was being very contractual?

A

They were issuing 7 day notices and threatening adjunctions and smash and grab wen the notices hadn’t been sent.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What do mean by the statement there was no fixed completion date?

A

We had passed the original PC Date and due to the fact that there was still design work to be done and items manufactured we couldn’t give the client a fixed completion date. We did give them regular programme updates.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Why did you not know where the account sat or what the final figures might be?

A

Once i had started to look into the account it became clear that my predecessor had lied about the accounts and lots of other things, i therefore assumed that all the figures were wrong. i had to redo and check everything to ensure that we did have the correct figures to report.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Option 3 -
Why was this option different to Option1?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Explain how this was more collaborative?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

How did you get the more valuable variations agreed?

A

I spent time on them ensuring all the correct and relevant information was sent to the PQS. I sat down with him and went through them.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Key Issue 2 - Option1
Whose design was behind schedule yours or the employers?

A

Ultimately both designs were behind, ours due to companies going into administration. The Employers

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

How could you have dealt with the variations being refuted

A

I spent time on them ensuring all the correct and relevant information was sent to the PQS. I sat down with him and went through them.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Who are MS?

A

They were the clients design team

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Why wouldn’t you stop work on elements that weren’t designed and was an Employer design element?

A
17
Q

Option 2 -
Was this realistically an option?

A
18
Q

Why did the glazer feel they didn’t have to use contract rates?

A

They didn’t believe that is how the contact worked, even after showing them the clause in the T&C’s, they refused to move on their position.

19
Q

How did they propose they price variations?

A

Mainly on dayworks.

20
Q

Why were they going to issue an EOT under this option?

A

Their original PC date had passed and they hadn’t finished so they thought they had an entitlement to an EOT.

21
Q

Option 3 -
How was building what we could managed?
How was this determined?

A

We looked through all the works left to complete and then what was designed o a point where it could be built.

22
Q

Can you give an example of where you worked together to minimise cost and programme impact?

A
23
Q

What was the alternative idea?

A
24
Q

Could you have suspended for this?

A
25
Q

Wasn’t there still additional time and costs with this approach?

A