Cost Estimation Flashcards
1
Q
Purpose of Cost Estimation
A
- project viability
- option comparison
- funding approvals
- cost control
- programming / cashflow
- financial planning
2
Q
Phasing of Cost Estimates
A
- Feasability Estimate (FE)
- Option Estimate (OE)
- Scheme Estimate (SE)
- Pre-design Estimate (PE)
- Design Estimate (DE)
- Construction Estimate (CE)
3
Q
I & R
A
Investigation and Reporting
4
Q
PFR
A
Project Feasability Report
5
Q
D & PD
A
Design and Project Documentation
6
Q
Accuracy of Estimate at Concept Stage
A
+/- 50%
7
Q
Accuracy of Estimate at Pre-Feasability
A
+/- 30%
8
Q
Accuracy of Estimate at Feasability
A
+/- 25%
9
Q
Accuracy of Estimate at Preliminary Design
A
+/- 20%
10
Q
Accuracy of Estimate at Detailed Design
A
+/- 15%
11
Q
Accuracy of Estimate at Tender Price
A
actual price + variation
12
Q
Capital Cost Estimate could include:
A
- land aquisition or access agreements
- concept and pre-feasability studies
- resource consent applications with associated supporting studies, hearings, environment court (if applicable)
- investigations to support design
- design - preliminary through to detailed
- Building Consents and regulator fees
- construction, including materials, equipment and labour
- field supervision of construction
- construction financing
- insurance and taxes during construction
- construction overheads
- inspections, testing, environmental compliance monitoring
13
Q
CAPEX
A
Capital Expenditure
14
Q
Design Fees
A
- concept
- pre-feasability
- feasability
- preliminary
- detailed design
rule of thumb: (5-10%) of capital for all stages - but very dependant on project complexity, site constraints, number of options assessed etc
15
Q
Preliminary-Technical Studies
A
- river hydrology and morphology
- canal and intake structure hydraulics
- seismic hazard assessment
- geotechnical investigations
- initial geometric design