Corp Finance Flashcards
reading 35 and 36
As the director of capital budgeting for Denver Corporation, an analyst is evaluating two mutually exclusive projects with the following net cash flows:
Year Project X Project Z 0 -$100,000 -$100,000 1 $50,000 $10,000 2 $40,000 $30,000 3 $30,000 $40,000 4 $10,000 $60,000 If Denver's cost of capital is 15%, which project should be chosen?
A) Project X, since it has the higher IRR.
B) Project X, since it has the higher net present value (NPV).
C) Neither project.
C
NPV for Project X = -100,000 + 50,000 / (1.15)1 + 40,000 / (1.15)2 + 30,000 / (1.15)3 + 10,000 / (1.15)4
= -100,000 + 43,478 + 30,246 + 19,725 + 5,718 = -833
NPV for Project Z = -100,000 + 10,000 / (1.15)1 + 30,000 / (1.15)2 + 40,000 / (1.15)3 + 60,000 / (1.15)4
= -100,000 + 8,696 + 22,684 + 26,301 + 34,305 = -8,014
Reject both projects because neither has a positive NPV.
If a project has a negative cash flow during its life or at the end of its life, the project most likely has:
A) a negative internal rate of return.
B) multiple net present values.
C) more than one internal rate of return.
C
Projects with unconventional cash flows (where the sign of the cash flow changes from minus to plus to back to minus) will have multiple internal rates of return. However, one will still be able to calculate a single net present value for the cash flow pattern.
Which of the following types of capital budgeting projects are most likely to generate little to no revenue?
A) New product or market development.
B) Regulatory projects.
C) Replacement projects to maintain the business.
B
Mandatory regulatory or environmental projects may be required by a governmental agency or insurance company and typically involve safety-related or environmental concerns. The projects typically generate little to no revenue, but they accompany other new revenue producing projects and are accepted by the company in order to continue operating.
The greatest amount of detailed capital budgeting analysis is typically required when deciding whether to:
A) expand production capacity.
B) replace a functioning machine with a newer model to reduce costs.
C) introduce a new product or develop a new market.
C
Introducing a new product or entering a new market involves sales and expense projections that can be highly uncertain. Expanding capacity or replacing old machinery involves less uncertainty and analysis.
Lane Industries has a project with the following cash flows:
Year Cash Flow 0 −$200,000 1 60,000 2 80,000 3 70,000 4 60,000 5 50,000 The project's cost of capital is 12%. The discounted payback period is closest to:
A) 2.9 years.
B) 3.4 years.
C) 3.9 years.
C
The discounted payback period method discounts the estimated cash flows by the project’s cost of capital and then calculates the time needed to recover the investment.
Year CF Discounted CF Cumulative Discounted CF
0 −$200,000 −$200,000.00 −$200,000.00
1 60,000 53,571.43 −146,428.57
2 80,000 63,775.51 −82,653.06
3 70,000 49,824.62 −32,828.44
4 60,000 38,131.08 5,302.64
5 50,000 28,371.30 33,673.98
discounted payback period =number of years until the year before full recovery + uncovered cost at beginning of the year/discounted CF during the year
=3+32,828.44/38,131.08=3.86
Two projects being considered by a firm are mutually exclusive and have the following projected cash flows:
Year Project 1 Cash Flow Project 2 Cash Flow
0 −$4.0 ?
1 $3.0 $1.7
2 $5.0 $3.2
3 $2.0 $5.8
The crossover rate of the two projects’ NPV profiles is 9%. What is the initial cash flow for Project 2?
4.22
The crossover rate is the rate at which the NPV for two projects is the same. That is, it is the rate at which the two NPV profiles cross. At a discount rate of 9%, the NPV of Project 1 is: CF0 = -4; CF1 = 3; CF2 = 5; CF3 = 2; I = 9%; CPT → NPV = $4.51.
Now perform the same calculations except that we need to set the unknown CF0 = 0. The remaining entries are: CF1 = 1.7; CF2 = 3.2; CF3 = 5.8; I = 9%; CPT → NPV = $8.73.
Since by definition the crossover rate produces the same NPV for both projects, we know that both projects should have an NPV = $4.51. Since the NPV of Project 2 (with CF0 = 0) is $8.73, the unknown cash flow must be a large enough negative amount to reduce the NPV for Project 2 from $8.73 to $4.51. Thus the unknown initial cash flow for Project 2 is determined as $4.51 = $8.73 + CF0, or CF0 = −$4.22.
When using net present value (NPV) profiles:
A)
one should accept all independent projects with positive NPVs.
B)
the NPV profile’s intersection with the vertical y-axis identifies the project’s internal rate of return.
C)
one should accept all mutually exclusive projects with positive NPVs.
A
Where the NPV intersects the vertical y-axis you have the value of the cash inflows less the cash outflows, assuming an absence of money having a time value (i.e., the discount rate is zero). Where the NPV intersects the horizontal x-axis you have the project’s internal rate of return. At this cost of financing, the cash inflows and cash outflows offset each other. The NPV profile is a tool that graphically plots the project’s NPV as calculated using different discount rates. Assuming an appropriate discount rate, one should accept all projects with positive net present values, if the projects are independent. If projects are mutually exclusive select the one with the higher NPV at any given level of the cost of capital.
Where the NPV intersects the vertical y-axis you have ____
Where the NPV intersects the horizontal x-axis you have
- the value of the cash inflows less the cash outflows, assuming an absence of money having a time value (i.e., the discount rate is zero).
- the project’s internal rate of return.
Where the NPV intersects the ____ axis you have the value of the cash inflows less the cash outflows, assuming an absence of money having a time value (i.e., the discount rate is zero). Where the NPV intersects the ___axis you have the project’s internal rate of return.
- y (vertical)
- x (horizontal)
Which of the following statements regarding the net present value (NPV) and internal rate of return (IRR) is least accurate?
A)
For mutually exclusive projects, you must accept the project with the highest NPV regardless of the sign of the NPV calculation.
B)
For independent projects, the internal rate of return IRR and the NPV methods always yield the same accept/reject decisions.
C)
The NPV tells how much the value of the firm will increase if you accept the project.
A
(first time picked B. Only when cash flow pattern is unconventional, IRR and NPV might be different. Also, for mutually exclusive projects the IRR and NPV techniques can yield different accept/reject decisions.)
If the NPV for two mutually exclusive projects is negative, both should be rejected.
A single independent project with a negative net present value has an initial cost of $2.5 million and would generate cash inflows of $1 million in each of the next three years. The discount rate the company used when evaluating this project is closest to:
A) 9%.
B) 10%.
C) 8%.
Given that the NPV is negative, the discount rate used by the company evaluating the project must be greater than the IRR (the discount rate for which the NPV equals zero). On a financial calculator: CF0 = -2.5; CFj = 1; Nj = 3; CPT IRR = 9.7%. Since the discount rate used for this project is greater than 9.7%, it must be closer to 10% than to either of the other answer choices.
when IRR > required rate of return ____ the project
accept
when IRR < ______, reject the project
required rate of return
when (NPV)_____, accept the project
independent vs mutually exclusive
NPV > 0 and the project is independent
or when project has the bigger NPV (if mutually exclusive)
when NPV _____, reject the project
<0
Profitability index = ?
= PV of future cash flow / CF0
= 1 + NPV/CF0
when profitability index (PI) ____, accept the project
> 1
Which of the following steps is least likely to be an administrative step in the capital budgeting process?
A)
Forecasting cash flows and analyzing project profitability.
B)
Conducting a post-audit to identify errors in the forecasting process.
C)
Arranging financing for capital projects.
- what are the steps?
(note, the capitol budgeting process has 4 “admin” steps. they are called admin, not because they aren’t important)
- Idea generation
- Analyzing project proposals (based on expected future cashflow)
- Creating the firm-wide capital budget
- Monitoring decisions and conducting a post-audit
The effect of a company announcement that they have begun a project with a current cost of $10 million that will generate future cash flows with a present value of $20 million is most likely to:
A)
only affect value of the firm’s common shares if the project was unexpected.
B)
increase the value of the firm’s common shares by $20 million.
C)
increase value of the firm’s common shares by $10 million.
A
The NPV method is a measure of the expected change in company value from undertaking a project. A firm’s stock price may be affected to the extent that engaging in a project with that NPV was previously unanticipated by investors.
(and this is only in theory, as in reality stock price could increase more than CF - for example if public expect further expansion, or less than CF - for example if analyst expects a less increase than mgmt’s forecast)
Edelman Enginenering is considering including an overhead pulley system in this year’s capital budget. The cash outlay for the pully system is $22,430. The firm’s cost of capital is 14%. After-tax cash flows, including depreciation are $7,500 for each of the next 5 years.
Calculate the internal rate of return (IRR) and the net present value (NPV) for the project, and indicate the correct accept/reject decision.
NPV IRR Accept/Reject A) $3,318 20% Accept B) $15,070 14% Reject C) $15,070 14% Accept
A
Using the cash flow keys:
CF0 = -22,430; CFj = 7,500; Nj = 5; Calculate IRR = 20%
I/Y = 14%; Calculate NPV = 3,318
Because the NPV is positive, the firm should accept the project.
The underlying cause of ranking conflicts between the net present value (NPV) and internal rate of return (IRR) methods is the underlying assumption related to the:
A) cash flow timing.
B) reinvestment rate.
C) initial cost.
B
The IRR method assumes all future cash flows can be reinvested at the IRR. This may not be feasible because the IRR is not based on market rates. The NPV method uses the weighted average cost of capital (WACC) as the appropriate discount rate.
projects with ____ cash flow patterns can produce multiple IRRs or no IRR.
unconventional
For projects with conventional cash flow patterns, the NPV and IRR methods produce ____ accept/reject decision
the same
Which of the following statements about the discounted payback period is least accurate? The discounted payback:
A) method can give conflicting results with the NPV.
B) frequently ignores terminal values.
C) period is generally shorter than the regular payback.
C
The discounted payback period calculates the present value of the future cash flows. Because these present values will be less than the actual cash flows it will take a longer time period to recover the original investment amount.
- For A, NPV could conflict with IRR, but prob not pay back period