Contract Strategy and Building Contract Flashcards
means selecting organizational and contractual
policies required for the execution of a specific
project.
Contract Strategy
an agreement made between two or
more parties which is enforceable by law
to provide something in return for
something else from a second party”
Contract
Elements that must be present before an agreement becomes a contract
- Competent Parties: • - Proper Subject Matter: Consideration: Agreement: Proper Form: - Consent of the Parties:
defines the extent or the area that the
contract covers.
Project Scope (performance):
Project Objectives (PRIMARY)
- Project Scope
- Time
- Price
translates what project
parties are involved in the project and how they
interact with each other
project delivery method
• is the most common approach in civil
engineering projects in which the design has to
be completed before construction can start.
Traditional Approach
owner organization performs both the design
and construction using its in-house labor force.
Direct Labor
a single organization is responsible for
performing both design and construction and,
in some cases, providing certain “know-how” for
the project
Design-build
• similar to the design-build approach but with the
organization being responsible for performing
both design, construction, know-how (if any), and
project financing.
Turnkey
• a business entity is responsible for performing
the design, construction, long-term financing, and
temporary operation of the project
Build-Operate Transfer (BOT)
can take various arrangements and the owner
needs to make a decision regarding the proper
arrangement that suits the project and the
parties involved.
Contractual Relationships
Contract where a single tendered price is given for the
completion of specified work to the satisfaction
of the client by a certain date.
Lump Sum Contract
Contact where the contractor specifies rates against each item including risk contingency.
Admeasurement Contract
Tenderers enter rates against each item of the
estimated quantities of work.
Bill of Quantities Contract:
separate rates to be quoted for labor, plant, and
materials
The contract price is derived by measuring the
man-hours, plant-hours and the quantities of
materials actually consumed
Schedule of Rates Contract
The contractor is reimbursed for actual cost plus
a special fee for head office overheads and
profit, no special payment for risk
• The contractor must make all his records and
accounts available for inspection by the client or
by some agreed third party.
• Payment may be made monthly in advance.
Cost-reimbursable Contract
• Cost targets may be introduced into cost-reimbursable
contracts.
• the contractor will be paid a share for any
saving between target and actual cost, while the
fee will be reduced if actual cost exceeds the
target.
Target Cost Contract
resemble cost-type arrangements
in that they are open ended, because the full
value of the arrangement is not defined at the
time of the award.
Time and Material Contracts
used in an emergency to begin work
immediately when a scope of work has not yet
been completed
Time and Material Contracts
The most important document from the legal
point of view
Agreement
They are terms expressing matters basic to the
contract.
Conditions