Calculations for the CPM Flashcards
The earliest time at which an event can occur, considering the duration of preceding activities
Early Event Time (ET)
It is the latest time at which an event can occur if the project is to be completed on schedule
Late Event Time (LT)
Determines the early-start times of activities
Forward Path
Proceeds from the most left node in the network and moves to the right
Forward path
Determines the late finish (LF) times of activities by preceding ____ from the end node to the starting note
BACKWARD
Placed in the right side boxes adjacent to the nodes
LF Values
Determine the flexibility of an activity to be delayed
Float Calculations
done when forward path and backward path calculations are complete
Float Calculations
It is the CPM scheduling method for AON
Precedence Diagram Method