Contract Practise Flashcards

1
Q

What is a contract?

A

A legal agreement between two parties.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Why are Contracts required / relevant for the construction industry?

A

Provides protection for both the employer and the contractors. It also prevents disputes.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are the different ways in which a contract can be made?

A

Verbally and written

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are the key requirements for a contract to be made binding?

A
  • Offer
  • Acceptance
  • Consideration
  • Intention to create legal relation
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are common main contract documents in JCT Design and Build.

A

Form of contract, employers requirements, contractors proposals, CSA, programme and clarifications.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are common main contract documents in JCT Intermediate.

A

Contract Drawings, specifications, bill of quantities.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What standard forms of JCT contracts are you aware of?

A

Intermediate, Design and Build, Intermediate, Major, and Minor.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Under what procurement route would you consider using a JCT Minor Works Building Contract.

A

Traditional procurement route.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

When might a JCT Minor Works Building Contract be appropriate?

A

Small, low value, basic construction projects where the work involved is simple in character.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Under what procurement route would you consider using a JCT Intermediate Building Contract?

A

Traditional procurement route.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is retention?

A

An amount of money owed to the contractor held by the employer, to ensure the contractor is completing the works in accordance with the contract, until the end of the rectification period.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

How is retention released?

A

Typically 1/2 s released on practical completion and 1/2 released at the end of the rectification period. This may vary depending on what is agreed at contract negotiation.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is a Notice of Completion of Making Good?

A

A certificate confirming that the contractor has made good any defects during the rectification period.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What are the advantages for standard contracts?

A
  • Standardised contracts backed up by case law
  • Known across the industry
  • Reduced legal costs
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What are the advantages for bespoke contracts?

A
  • Contracts can be customised to address project specific needs
  • Greater control over the agreed dispute resolution and payment methods.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What are the disadvantages for standard contracts?

A
  • Can be overly complicated for smaller projects
  • Limited flexibility to address specific project needs
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

What are the disadvantages for bespoke contracts?

A
  • Increased legal costs to draft a bespoke contract
  • Time consuming
  • Lack of case law or precedent can make it difficult to resolve disputes
18
Q

What is a relevant event?

A

An occurrence, such as delays caused by the client or external factors, that entitles the contractor to an extension of time for project completion.

19
Q

What is a relevant matter?

A

An occurrence, such as changes in design or unforeseen site conditions, that affects the contractor’s ability to perform the work as originally agreed and may justify a claim for additional costs or time.

20
Q

What are some examples of relevant events?

A

In JCT D&B
- Extreme weather
- Force Majeure
- Delay of possession of site
- Civil Commosion

21
Q

What is a letter of intent?

A

A document that outlines the intentions of parties involved in a construction project before a formal contract is signed.

22
Q

What are the benefits of a letter of intent?

A
  • Alleviates time-constraints
  • Allows more time for negotiations on the contract details
  • Provides clarity of scope of works
23
Q

Is a letter of intent legally binding?

A

Not necessarily. However, some elements include legally binding provisions. So it’s important that the client consults a solicitor to understand their obligations as it can sometimes be seen as legally binding.

24
Q

What are the disadvantages of a letter of intent?

A
  • Not necessarily legally binding, but can unintentionally become legally binding.
  • Ambiguity on the project outcome
  • May create a delay to create an official document
25
Q

What is a performance bond?

A
  • insures client against the contractor failing to fulfil contractual obligations
  • typically 10% of the contract value
26
Q

What is an advance payment bond?

A
  • if it has been agreed that the contractor will receive an advanced payment.
  • the bond is an insurance in favour of the client to call on if the contractor fails to meet its obligations or becomes insolvent
  • typically they are on-demand bonds
27
Q

What is an off-site materials bond?

A
  • used to pay for materials that remain off site.
  • protects the client against failure of the contractor
  • typically the bond is the value of the off-site materials and reduces as deliveries to site are made
  • typically an on-demand bond
28
Q

What is a bid bond?

A
  • rare in the UK
  • typically on-demand
  • used to secure the tenderer’s commitment to commence the contract.
29
Q

What is a retention bond?

A
  • an insurance taken out for the full value of the retention in lieu of deducting retention from interim payments
  • the client can call upon the bond if the contractor fails to address issues during the rectification period as they would with retention.
  • to pay for direct loss or damage suffered by a third party as a result of a breach of contract.
  • typically a small percentage (0.4 - 2%) of the retention value
30
Q

What is a defects liability bond?

A
  • used to ensure the contractor continues to provide services that become apparent after PC
  • typically on-demand
  • used on jobs where there are no outstanding costs
31
Q

What bonds are you aware of?

A
  • Performance bond
  • Bid bond- Retention bond
  • Defects liability bond
  • Advance payment bond
32
Q

What is a primary obligation?

A

‘the main duty a party has to fulfil’

  • simple or on-demand bonds
33
Q

What is a secondary obligation?

A

‘A penalty that applies if the party breaches their primary obligation’

  • conditional bonds
  • parent company guarantees
34
Q

What is the difference between bonds and guarantees

A

A guarantee is linked to non-performance of the underlying contract. A bond is different in that it can be paid on demand, regardless of the underlying contract.

35
Q
A
36
Q

What are some examples of relevant matters?

A
  • Instructions related to variations
  • Epidemics (new in JCT 2024)
  • Unexploded ordnance
37
Q

On Silbury House, you helped with the production of a schedule of derogations. Can you tell me what particular derogation you advised your client on getting legal advice on?

A
38
Q

Can you give me a couple more derogations you found or would anticipate in the schedule

A
39
Q

On York road, you advised your client they weren’t liable for an additional weeks claim in relation to ground conditions. Can you set out how you went about advising this against the contract?

A
40
Q

On Devonshire square, you make sure to follow the JCT valuation rules. When does the valuation process begin under this contract?

A
41
Q

Can you give me some differences between JCT Intermediate contract and JCT Design and Build contract?

A