Contract Law Flashcards

1
Q

a legally binding agreement has to meet these following agreements

A

agreement between parties

capacity to enter into a contract

genuine intention to form a binding legal relationship

supported by consideration

must have lawful intent and not be contrary to public policy

ceratin formalities may be required

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Agreement

A

there has to be at least 2 parties to contract, but there can be no contract without agreement between the parties, have to agree on the same thing

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

twin elements of an agreement

A

offer and acceptance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

letters of intent

A

prior to the contract the parties sometime exchange communications
express the intention to enter a contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

duress, undue influence & fraud

A

the parties have to to voluntarily enter into the contract if a person induced into contract under duress or undue influence the contract is not valid

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

breach by owner

A

if they do not make proper payments as required by the contract if the contract does not expressly state

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

breach by contractor

A

the contractor does not perform the work to accordance with all of the terms of the contract, the contractor fails to meet the specifications

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

termination of contract by perfromance

A

when all parties have satisfactorily completed all of their obligations under the contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

termination of contract by agreement

A

contracts under seal and written contracts can be ended effectively by an oral agreement between the parties

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

arbitration

A

is a system for settlement of disputes without resorting to the courts

arbitration has a long history as a means of resolving commercial disputes especially when the specialized knowledge of the arbitrator is important

people cannot be forced to use arbitration to settle their disputes

even if parties commit to using arbitration, it is impractical to try to force them to keep to their agreement when they are reluctant to use arbitration

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

change order

A

agreement between the owner and the contractor to make certain change in the work for an agreed price or method of payment such as unit price, cost plus, or time and materials, the. change order may also include an agreed adjustment in the project in the contract time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

provisions for the interim release of the holdback allow the owner to release from the major lien fund on a subcontractors work _____ days after substantial completion of the sub contractos work when no liens have been registred in connection with that work

A

45 days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

builder’s liens

A

they require the owner to maintain a lien fund by holding back a percentage of all payments to a contractors for a certain time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

statutory holdback is what percentage?

A

10% of the value of work done

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

open bidding

A

the open form of competitive bidding is the most commonly used for public projects

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

criteria

A

at both the pre-qualifiaction and bid closing stage the selection of the builders/contractor is usually based on price, reputation, past performance experiences safety and financial status of BONDING

14
Q

finacial status and bonding

A

a contractor that is financially unstable is a risk to the owner and could jeopardize successful completion of the project

15
Q

the bonds she told us to highlight with no definition

A

BID BONDS
PERFORMACE BONDS

16
Q

labour and material bonds

A

is a commitment by the surety to pay for labour and materials furnished to the contractor for use on the project

17
Q

payment bonds

A

the principle would be the owner and obligee would be the contractor. this type of bond used when a contractor has some concerns about the owners ability to pay for the work

( this arrangement is contrary to the situation in all the other bonds we have considered )