Contract Law Flashcards
a legally binding agreement has to meet these following agreements
agreement between parties
capacity to enter into a contract
genuine intention to form a binding legal relationship
supported by consideration
must have lawful intent and not be contrary to public policy
ceratin formalities may be required
Agreement
there has to be at least 2 parties to contract, but there can be no contract without agreement between the parties, have to agree on the same thing
twin elements of an agreement
offer and acceptance
letters of intent
prior to the contract the parties sometime exchange communications
express the intention to enter a contract
duress, undue influence & fraud
the parties have to to voluntarily enter into the contract if a person induced into contract under duress or undue influence the contract is not valid
breach by owner
if they do not make proper payments as required by the contract if the contract does not expressly state
breach by contractor
the contractor does not perform the work to accordance with all of the terms of the contract, the contractor fails to meet the specifications
termination of contract by perfromance
when all parties have satisfactorily completed all of their obligations under the contract
termination of contract by agreement
contracts under seal and written contracts can be ended effectively by an oral agreement between the parties
arbitration
is a system for settlement of disputes without resorting to the courts
arbitration has a long history as a means of resolving commercial disputes especially when the specialized knowledge of the arbitrator is important
people cannot be forced to use arbitration to settle their disputes
even if parties commit to using arbitration, it is impractical to try to force them to keep to their agreement when they are reluctant to use arbitration
change order
agreement between the owner and the contractor to make certain change in the work for an agreed price or method of payment such as unit price, cost plus, or time and materials, the. change order may also include an agreed adjustment in the project in the contract time
provisions for the interim release of the holdback allow the owner to release from the major lien fund on a subcontractors work _____ days after substantial completion of the sub contractos work when no liens have been registred in connection with that work
45 days
builder’s liens
they require the owner to maintain a lien fund by holding back a percentage of all payments to a contractors for a certain time
statutory holdback is what percentage?
10% of the value of work done
open bidding
the open form of competitive bidding is the most commonly used for public projects