Contract Document Flashcards
Which document informs the Contractor that the work on the project is being stopped?
Stop Work Order
Which document protects the Owner from third party financial claims against the Owner’s property while the project is being constructed?
Labor and Material Bond
Assume that the Contractor has not been paid according to the contract payment due date. According to the contract documents, which document must the contractor complete and submit to ensure that they do not lose their rights under the contract for late payment?
Stop Work Notice
According to the project documents, after the signing of the Agreement which documents must be submitted by the contractor within fourteen days of executing the Agreement?
Construction Schedule and Schedule of Values