Contract dependencies Flashcards
everyone to let the architect know of discovered errors or omissions in the contract documents
Expeditiously/with reasonable promptness
architect to respond to rfis and submittals
Expeditiously/with reasonable promptness
Architect site visits during construction
Intervals appropriate to the stage of construction
contractor becoming aware of expiration, impending or actual cancelation of any insurance requirement contractor shall provide notice to the owner
3 Days
notice of termination
7 Days
Architect issues certificate of payment to owner after receiving application from contractor
7 Days
Contractor shall pay subcontractors after receiving payment from owner
7 Days
Contractor provides proof of payment to subcontractors after request from owner
7 Days
If the architect doesn’t issue a certificate of payment, contractor can issue written notice and stop work
7 Days
after owner requested evidence from contractor to supply proof of payment of subcontractor, owner may contact sub directl
7 Days
Contractor may disclose confidential information if required by the law,
7 Days
Prior to date established, contractor will submit application for payment
10 Days
Initial decision maker to review claims
10 Days
owner has right to carry out the work if Contractor, after x days notice, fails to commence with or start to make corrections to conform with contract documents
10 Days
Contractor maximum time to make owner and architect aware of concealed conditions that differ from contract documents
14 Days
Architect to notify contractor if architect or owner has objections to the contractors proposed superintendent or subcontractor
14 Days
Owner to provide evidence of financial means to contractor
14 Days
Contractor to object to proposed settlement
14 Days
Owner to provide information about liens to contractor or architect
15 Days
Maximum time to report injury or damage caused by acts or omissions of the other party
21 Days
Notice of a claim by ether the owner or the contractor
21 Days
After X consecutive days of stopped work, through no fault of the contractor, he may terminate the agreement if: issuance of court order stopped the work, he has not been paid or not been told why he has not been paid
30 Days
Parties have X days after receipt of initial decision to file for mediation, otherwise they wave right to mediation or binding dispute resolution
30 Days
owner’s final payment to contractor not later then X days after architects issues final certificate of payment
30 Days
After X consecutive days of suspended work, contractor can terminate the agreement
60 Days
Construction phase services more then X days after substantial completion of the work shall be compensated as additional services
60 Days
Architect can terminate agreement if owner suspends project for more then X cumulative days.
90 Days
After X accumulated days of suspended work, contractor can terminate the agreement, or exceeds days scheduled to finish work, whichever is less
120 days
period for correction of work by contractor
1 Year
Both parties wave rights to any claim X after substantial completion
10 Years
How long does a contractor have to request additional funds for work?
21 days
AIA 701 3.3.2 states that all substitutions must be submitted x days before the receipt of bids.
10 days
How many days prior to the receipt of bids is the Contractor permitted to ask questions?
7
According to the A701,
§ 3.2.2 Bidders and Sub-bidders requiring clarification or interpretation of the Bidding Documents shall make a written request which shall reach the Architect at least seven days prior to the date for receipt of Bids.