Contract dependencies Flashcards

1
Q

everyone to let the architect know of discovered errors or omissions in the contract documents

A

Expeditiously/with reasonable promptness

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

architect to respond to rfis and submittals

A

Expeditiously/with reasonable promptness

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Architect site visits during construction

A

Intervals appropriate to the stage of construction

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

contractor becoming aware of expiration, impending or actual cancelation of any insurance requirement contractor shall provide notice to the owner

A

3 Days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

notice of termination

A

7 Days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Architect issues certificate of payment to owner after receiving application from contractor

A

7 Days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Contractor shall pay subcontractors after receiving payment from owner

A

7 Days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Contractor provides proof of payment to subcontractors after request from owner

A

7 Days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

If the architect doesn’t issue a certificate of payment, contractor can issue written notice and stop work

A

7 Days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

after owner requested evidence from contractor to supply proof of payment of subcontractor, owner may contact sub directl

A

7 Days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Contractor may disclose confidential information if required by the law,

A

7 Days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Prior to date established, contractor will submit application for payment

A

10 Days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Initial decision maker to review claims

A

10 Days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

owner has right to carry out the work if Contractor, after x days notice, fails to commence with or start to make corrections to conform with contract documents

A

10 Days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Contractor maximum time to make owner and architect aware of concealed conditions that differ from contract documents

A

14 Days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Architect to notify contractor if architect or owner has objections to the contractors proposed superintendent or subcontractor

A

14 Days

17
Q

Owner to provide evidence of financial means to contractor

A

14 Days

18
Q

Contractor to object to proposed settlement

A

14 Days

19
Q

Owner to provide information about liens to contractor or architect

A

15 Days

20
Q

Maximum time to report injury or damage caused by acts or omissions of the other party

A

21 Days

21
Q

Notice of a claim by ether the owner or the contractor

A

21 Days

22
Q

After X consecutive days of stopped work, through no fault of the contractor, he may terminate the agreement if: issuance of court order stopped the work, he has not been paid or not been told why he has not been paid

A

30 Days

23
Q

Parties have X days after receipt of initial decision to file for mediation, otherwise they wave right to mediation or binding dispute resolution

A

30 Days

24
Q

owner’s final payment to contractor not later then X days after architects issues final certificate of payment

A

30 Days

25
Q

After X consecutive days of suspended work, contractor can terminate the agreement

A

60 Days

26
Q

Construction phase services more then X days after substantial completion of the work shall be compensated as additional services

A

60 Days

27
Q

Architect can terminate agreement if owner suspends project for more then X cumulative days.

A

90 Days

28
Q

After X accumulated days of suspended work, contractor can terminate the agreement, or exceeds days scheduled to finish work, whichever is less

A

120 days

29
Q

period for correction of work by contractor

A

1 Year

30
Q

Both parties wave rights to any claim X after substantial completion

A

10 Years

31
Q

How long does a contractor have to request additional funds for work?

A

21 days

32
Q

AIA 701 3.3.2 states that all substitutions must be submitted x days before the receipt of bids.

A

10 days

33
Q

How many days prior to the receipt of bids is the Contractor permitted to ask questions?

A

7

According to the A701,

§ 3.2.2 Bidders and Sub-bidders requiring clarification or interpretation of the Bidding Documents shall make a written request which shall reach the Architect at least seven days prior to the date for receipt of Bids.