Contract Administration Flashcards

1
Q

What is a LAD

A

LAD- Liquidated Ascertained Damages

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What if the client tells you the LADs are to be £100,000 per week?

A
  • I would check that the LAD figure is based on a genuine pre-estimate of financial loss and explain that
    in the event LAD’s are to be applied, they would need to substantiate this figure.
  • I would also explain that if the figure inserted into the contract is shown to be punitive and not based
    on genuine financial loss it is not likely to be enforceable.
  • In this scenario the employer will have to pursue the Main Contractor for any actual direct loss that can
    be substantiated through a formal dispute resolution procedure.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are extensions of time?

A
  • Extensions of time adjust the completion date and relieves the contractor’s liability to pay liquidated
    damages for the period of the extension.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are liquidated damages?

A
  • A genuine pre-estimate of the likely loss incurred by the employer should the completion date not be
    met.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What if the employer actually suffered no loss or damage? (LD’s)

A
  • It doesn’t matter.
  • The damages can still be deducted at the value stated in the contract.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are the benefits of being able to grant an extension of time?

A
  • It relieves the contractor’s liability for liquidated damages for a delay that they did not cause.
  • It enables another completion date to be set, which maintains the employer’s ability to deduct
    liquidated damages if another delay occurs.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What must be in place before LDs can be deducted?

A
  • A non-completion certificate.
  • A withholding notice.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What happens when ‘time is at large’?

A
  • There is no set completion date.
  • The contractor only has the obligation to complete the works in a ‘reasonable time’.
  • Liquidated damages cannot be claimed as there is no date to take them from.
  • The employer would have to try and prove that the contractor had not completed in a reasonable time.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What are Relevant Events in a JCT form of Contract?

A
  • They are events that entitle the contractor to an extension of time.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What are the relevant events?

A

o Variations.
o Instructions.
o Execution of an approx. quantity that is not a reasonably accurate forecast.
o Deferment of possession of the site.
o Suspension by the contractor for non-payment.
o The carrying out of work by statutory authorities.
o Impediment, prevention or default by the employer.
o Loss or damages occasioned by the Specified Perils.
o Exceptionally adverse weather conditions.
o Strike or lock out.
o Civil commotion or terrorism.
o The exercise of any statutory power after the base date by the UK gov.
o Force majeure.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What are the main elements you would include within an interim
valuation?

A
  • Preliminaries.
  • Measured work.
  • Variations.
  • Materials on site.
  • Materials off site.
  • Loss and expense.
  • Retention.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What needs to be in place for you to include payments for materials on
site?

A
  • The materials should be for the works.
  • They should be adequately protected.
  • Delivered to programme.
  • In a reasonable quantity.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What needs to be in place for you to include payments for materials
off site?

A
  • Proof that ownership will transfer to the employer upon payment (vesting certificate).
  • Insurance until materials arrive at site.
  • Materials are clearly labelled as for the site and set apart from other materials.
  • A materials off site bond has been provided if required.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is a retention of title clause?

A
  • Where the sub-contractor or supplier retains ownership of materials until they are paid for them by the
    contractor.
  • This highlights the importance of vesting certificates as the employer may subsequently pay for
    materials that are not owned by the contractor.
  • This legal principle can lead to disputes in the event of insolvency.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

How do you evaluate interim valuations?

A
  • Go to site and inspect the works to form a view on the percentage of works undertaken.
  • Check for materials on site and materials off site.
  • Value time related and fixed preliminaries items undertaken.
  • Value any agreed variations and claims.
  • The valuation amount is presented as the gross valuation, less previous payment made and retention.
  • Finally I would send my recommendation to the Architect or Contract Administrator for them to
    prepare the payment certificate.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

How do stage payments work?

A
  • The stages and their values are set out in the contract particulars.
  • The stages are usually related to the completion of significant design items for example completion of
    the substructure or achieving a water tight structure.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

What is the interim certificate conclusive of?

A
  • Interim certificates are not conclusive.
  • They carry no contractual significance to state that the quality of materials or workmanship is
    satisfactory.
  • It is only the final certificate that is conclusive.
18
Q

What is retention?

A
  • It is a percentage of each interim certificate deducted and retained by the employer from each interim
    payment to the contractor.
19
Q

What is the purpose of retention?

A
  • It provides an incentive for the contractor to rectify any defects within the contract defects liability
    period.
  • It provides some financial security to the employer in the event of a contractor default.
20
Q

When is the retention released to the contractor?

A
  • Half of the retention is released in the interim certificate after Practical Completion.
  • The remaining retention is released in the final certificate after the certificate of making good defects is
    issued.
21
Q

What is a typical retention percentage under JCT contracts?

A
  • Usually retention is between 3% or 5% depending on the form in use.
22
Q

What is a retention bond?

A
  • This is a bond provided by the contractor in lieu of taking retention from interim payments.
  • It should be equal to the same value as the retention deducted.
  • The requirement for the bond should be stated in the contract particulars.
  • A standard form is provided in the JCT contract schedules.
23
Q

What happens if the contractor does not maintain the retention bond?

A
  • The employer can deduct retention from interim payments.
  • If the bond is subsequently taken out, the retention deducted must be repaid to the contractor.
24
Q

Why might a retention bond be used?

A
  • It may be used in difficult market conditions to aid the contractor’s cashflow.
25
Q

What are the disadvantages of a retention bond?

A
  • The employer would have to pay the premium for taking out the bond.
  • It may reduce the contractor’s incentive to complete making good defects promptly.
  • It reduces the employer’s cashflow.
  • The employer would not get the interest accruing on the amount of the retention bond.
26
Q

What are the main forms of JCT contract you know?

A
27
Q

What kinds of works would be included within the contractor’s design portion of a contract and why?

A
  • It is used when the contactor has agreed to design specific parts of the works. They will usually sub-contract the works
    whereby a specialist installer or manufacturer is required. Ensures buildability and other factors are taken into account. The contractor is responsible for the procurement and must adhere to the programme.
  • Specialist works can include; installation of services, roof replacement etc.
  • Takes the liability of the design off the client and design team.
28
Q

What are the responsibilities of a contract administrator

A
  • They are not a party to the contract and therefore must remain impartial at all times. Simply there to administer the contract.
  • Chair pre contract meeting.
  • Issue contract instructions.
  • Deal with payment provisions.
  • Manage change procedures – design changes etc.
  • Involve with dispute avoidance.
  • Issue certificates.
  • Deal with completion/possession issues.
29
Q

Explain the valuation process and the responsibilities of a contract administrator for a JC intermediate Contract / JCT Minor works contract?

A
  1. Contractor must issue application for payment no later than the valuation date.
  2. Valuation date occurs (stated in contract particulars – will change to closest business day).
  3. Due date (date at which the CA values the works) is 7 days after the valuation date.
  4. Contract administrator must issue a certificate for payment (interim cert) within 5 days after the due date – the cert = the
    amount they deem should be paid at the due date.
  5. Final date for payment in standard contract is 14 days from the due date.
  6. If the employer intends to withhold any amount from the sum certified, the they must provide written notice of their intention no later than 5 days before the final date for payment.

Note: The contract gives the contractor the right to submit its own payment application - they are not required to and the CA can undertake the valuation without it.

Note: If the CA doesn’t issue a payment certificate within 5 days after the due date, if the contractor issued an application for payment this becomes a payment notice and acts as the cert, otherwise a contractor can send a payment notice to the CA.

30
Q

How does the valuation process differ with regards to the JCT Design and Build Contract?

A

Essentially the same as the JCT intermediate contract BUT – Due dates can change.

If the contractor submits their application for payment before the valuation date, then the due date is still 7 days from valuation date, but if received after the valuation date then the due date is 7 days from the day of receipt of the AFP.

31
Q

How could an employer take part of a site back quickly?

A
  • By doing sectional completion.
  • Early possession – note: when early possession utilised the works or section of are deemed to be at practical completion
    regardless.

-Acceleration.

32
Q

What is practical completion? What happens contractually once PC is certified?

A

There is no definitive definition for the term Practical Completion. It is when the works are complete to the satisfaction of the Contract Administrator and the contractor has abided with their duties under the CDM regulations. The CA cannot certify PC where there are outstanding works or patent defects, but they also cannot withhold PC for minor outstanding defects.

HW Nevill (Sunblest) Ltd v William Press & Son Ltd [1981] (the flexible test) – PC will not be prevented where the works have been completed free from patent defects, other than ones to be ignored as diminimus or trifling (very minor in nature).

What is deemed diminmus or trifling will be different for each project / the intended end use – swimming pool analogy.

Once PC is certified:

Start of rectification period.

Liquidated damages cannot be claimed.

Release of half the retention.

Client then claims back possession of the site – insures it etc.

33
Q
A
34
Q
A
35
Q

What is partial possession?

A

Mechanism to allow employer to take early possession of a site.

Contract might have provision for sectional completion to allow partial possession.

Effect of partial possession:

 Any part of the works which partial possession is given is deemed to achieve practical completion.
 Half retention must therefore be released.
 Defects liability begin for that part of the works.
 Liquidated damages reduce?
 Client is responsible for that part of the works and will need to use its own insurances.

Contractor not obliged to give partial possession but can’t unreasonably withhold it.

Contactor may not wish to give partial possession due to occupants / other contractors on the site holding up works – may
lead to an extension of time application.

36
Q

What is the difference between a contract being executed as a deed or underhand?What is the difference between a contract being executed as a deed or underhand?

A

The Latent Damage Act 1986 stipulates the limitation period of building contract is (period for which a claimant can bring proceedings against a contractor):

6 years from completion for contracts signed underhand.

12 years for those executed as a deed.

The act prevents claimants bringing old cases against contractors and encourages them to do so without delay.

37
Q

What contractual processes need to occur with regards to an extension of time?

A

The contractor is required to notify the CA whenever it becomes reasonably apparent that the progress of the works or any section of the works is likely to be delayed by a relevant event.

The contractors notification should be in writing and should identify the relevant event that has caused the delay, request that an extension of time should be granted and then provide details and evidence of causation of the relevant event. They should also state whether the delay will impact the completion date and if so the amount of delay anticipated.

Contractually the contractor is also required to mitigate the delay even though it isn’t a result of their actions.

CA then analyses the contractors’ request for extension of time and to determine whether the identified relevant event has indeed caused the delay. If this is found to be the case they must then grant the extension of time and agree a new contractual completion date.

38
Q

What are the two broad groups of relevant events? Give some examples of relevant events

A

Relevant events caused by the employer / relevant events caused by neutral events.

Relevant events caused by the employer: variations and instructions, delays handing over possession of the site, suspension of the contract due to non-payment.

Relevant events caused by neutral events: Force majeure - act of god (war, natural catastrophes), adverse weather conditions, specified perils (fire, floods), civil commotion (acts of terrorism, strikes etc).

39
Q

What is single stage tendering?

A

Single stage tendering is a tendering procedure whereby a number of pre-selected contractors submit tenders on a competitive basis.

Each contractor provides a single cost for the whole of the construction works within a predetermined tender period.

Tenders are then analysed in terms of cost and quality before a single contractor is declared the preferred contractor and enters into a building contract with the client.

40
Q
A