Contract Administration Flashcards
Explain the valuation process and the responsibilities of a contract administrator for a JCT intermediate Contract / JCT Minor works contract?
- The contractor issues application for payment no later than the valuation date.
- Valuation date occurs. The date is defined in the contractor particulars.
- The CA values the work on the due Date. The due Date is 7 days after the valuation date.
- Under 21 day payment terms, Final date for payment in standard contract is 14 days from the due date.
- The CA must issue a certificate for payment (interim cert) within 5 days after the due date.
- If the employer intends to withhold any amount from the sum certified, a pay less notice of their intentions must be provided no later than 5 days before the final date for payment.
Note: The contract gives the contractor the right to submit its own payment application - they are not required to and the CA can undertake the valuation without it.
Note: If the CA doesn’t issue a payment certificate within 5 days after the due date, if the contractor issued an application for payment this becomes a payment notice and acts as the cert, otherwise a contractor can send a payment notice to the CA.
What are the main forms of JCT contract you know?
JCT Intermediate Building Contract, 2016 (+with contractor’s design portion).
JCT Minor Works Building Contract 2016 (+with contractor’s design portion).
JCT Design and Build.
Management Building Contract 2016.
Measured Term Contract 2016.
What kinds of works would be included within the contractor’s design portion of a contract and why?
Sections of work that the contractor has agreed to design and take on design liability.
Usually items which the designer or client is not willing or unable to design themselves.
Contractor is responsible for the procurement and programme provisions.
Usually performed by specialist subcontractors.
What are the responsibilities of a contract administrator
They are not a party to the contract and therefore must remain impartial at all times.
Simply there to administer the contract.
Chair pre contract meeting.
Issue contract instructions.
Deal with payment provisions.
Manage change procedures – design changes etc.
Involve with dispute avoidance.
Issue certificates.
Deal with completion / possession issues.
How does the valuation process differ with regards to the JCT Design and Build Contract?
Essentially the same as the JCT intermediate contract BUT – Due dates can change.
If the contractor submits their application for payment before the valuation date, then the due date is still 7 days from valuation
date, but if received after the valuation date then the due date is 7 days from the day of receipt of the AFP.
How could an employer take part of a site back quickly?
By doing sectional completion.
Early possession – note: when early possession utilised the works or
section of are deemed to be at practical completion regardless.
Acceleration.
What is practical completion? What happens contractually once PC is certified?
Practical completion is when the works is deemed to be practically complete by the CA. This is at the digression of the CA.
For PC to be issued the contractor must have abided with their duties under CDM regs.
PC can be withheld for outstanding work or defects.
PC cannot be withheld for minor defects or snagging items.
Once PC is certified:
Start of rectification period.
Liquidated damages cannot be claimed.
Release of half the retention.
Client then claims back possession of the site – insures it etc.
What is partial possession?
Mechanism to allow employer to take early possession of a site.
Contract might have provision for sectional completion to allow partial possession.
Work on this section must be Practically complete.
Same occurrences as PC: defects liability begins, client to insure, retention partly released etc.
Contractor not obliged to give partial possession but can’t unreasonably withhold it.
Contactor may not wish to give partial possession due to occupants / other contractors on the site holding up works – may
lead to an extension of time application.
What is the difference between a contract being executed as a deed or underhand?
The Latent Damage Act 1986 stipulates the limitation period of building contract is (period for which a claimant can bring proceedings against a contractor):
6 years from completion for contracts signed underhand.
12 years for those executed as a deed.
The act prevents claimants bringing old cases against contractors and encourages them to do so without delay.
What contractual processes need to occur with regards to an extension of time?
- The contractor notifies the CA in writing to specify the relevant events that has caused the delay and request an extension of time.
- Details and evidence of causation of the relevant event.
- They should also state if this relevant event will impact the completion date and if so, the amount of delay anticipated.
- CA to assess the EoT and determines whether the identified relevant event has caused a delay. If so, the EoT must be granted and agree a new contractual completion date.
What are the two broad groups of relevant events? Give some examples of relevant events
Relevant events caused by the employer / relevant events caused by neutral events.
Relevant events caused by the employer:
1. variations and instructions
2. delays handing over possession of the site
3. suspension of the contract due to non-payment.
Relevant events caused by neutral events:
1. Force majeure,
2. adverse weather conditions,
3. specified perils (fire, floods),
4. civil commotion (acts of terrorism, strikes etc).
What is single stage tendering?
In a competitive basis, the contractors submit one single cost for the works.
What are the advantages of single stage tendering?
- Design is already defined by formulated at tender stage.
- The contractor assumes responsibility and financial risk to construct the works within a pre-contractually confirmed contract sum and period.
When would traditional procurement appropriate?
1.When the design is defined at contractor selection.
- The client wishes to retain control over the design and specification.
- When cost certainty is required.
What forms of contract might you use with traditional procurement?
JCT Minor Works, 2016.
JCT Intermediate
What are the advantages of traditional procurement?
- Competitive fairness and transparent process
- Design Led
- Price Certainty
What are the disadvantages of Traditional Procurement?
- It can increase overall project duration
- Reduced buildability within the design as contractor has had no input.
- Client responsible for design and construction
What is included within a tender report?
- Details of the tenders received; figures and the contractors selected.
- Any cost qualifications
- Any adjustments in line with The JCT Tendering Practice Note 2017.
- Comparison of tender sums and a recommendation of instruction.
What are the key contractual procedures have to occur to enable an employer to claim liquidated damages?
- Part or full non completion of the contractual work.
- CA to issue a certificate of non completion notifying the contractor in writing that the employer in tends to claim liquidated damages.
- This can either be payment from the contractor or deducting them from the sim of money owed to the contractor.
Note: If the employer wants the deduct the liquidated damages from sums owed to the contractor then a pay less notice is required to
ensure compliance with the Housing Grants, Construction and Regeneration Act 1996.
What is procurement?
The overall act of obtaining goods and services from external sources (for example a building contractor) and includes decision making with regards to how the goods are to be acquired by reviewing a client’s requirements (i.e time, quality and cost). and their attitude to risk.
What is tendering?
Forms part of procurement.
Contractor bidding process for work
What is two-stage tendering?
First Stage tender enquiry to preselected contractors at RIBA stage 2 / 3 (concept design and spatial coordination) .
Contractors submit costs for their prelims, proposed sub letting of work to subcontractors and their OH&P
The preferred contractor is selected and joins the design team on a pre-construction services agreement.
The design is worked up with the contractor and a bid is presented for the works.
What is negotiated tender?
- One contractor prices the work as a whole.
- The contractor undertakes the work for an agreed cost subject to variations.
What are the advantages and disadvantages of single-stage tendering? When would you utilise single stage tendering?
Advantages:
- Only approved contractors are approached.
- Lump sum for the works
Disadvantages:
- Full design has to be defined prior to tender
- May result in a longer design period prior to tender.