Contract administration Flashcards
(1) What is the role of the Contract Administrator?
The Contract Administrator manages the contract between the employer and building contractor. The role commences when the contract is in place.
pre-contract services are often included in instructions which rely on advise on the method of procurement, calculation of liquidated damages and deciding on the appropriate type of building contract.
(1) Can you give some typical activities for the Contract Administrator?
- Chairing meetings
- Ascertaining that the works are in accordance with the contract documents
- Giving instructions, including variations or change orders
- Determining any applications for extensions of time for the contractor
- Authorising interim payments to the contractor
- certifying the date of completion
- Setting the adjusted contract sum
(2) What are the responsibilities of the Contract Administrator
Information
- Ensure provision of information
- Supply documents
Financial matters
- Certify interim payments
- Consider: Interim valuations
- Send computations of the adjusted contract sum
Supervision
Approve quality of materials
instruct the contractor, may or may not require a variation
Make a fair and reasonable extension of time
Misc
Undertake the role of CDM Coordinator by default
Give notice identifying default by the Contractor
Direct the contractor for the integration of the design portions
(1) Can you explain interim valuations
Interim valuations are required for most contracts due to the Housing, Grants, Construction and Regeneration act of 1996. These must be carried out with the contractual provisions.
JCT Intermediate contract (unamended)
Due date 7 days after the interim valuation date
5 days after due date (fixed by HGCR) = CA issues payment certificate
Final date for payment = 14 days after due date
Total payment cycle = 21 days (prescribed period)
QS to be named in the contract - only obliged to carry out interim valuations whenever the Contract Administrator considers him or her necessary to amount to be stated in an interim certificate (or prepare a valuation where a application for payment has not been submitted).
JCT minor works contract / JCT D&B Contract (unamended)
Due date - Contractor’s interim application for payment
5 days after due date (fixed by HGCR) = CA issues payment certificate.
Final date for payment = 14 days after payment.
Total payment cycle = 14 days (prescribed period)
Amendments recommended as there is no stipulation for an interim valuation date (BY QS).
If the CA does not issue the payment certificate within 5 days after the due date, the Contractor’s payment application will become their payment notice.
(1) What happens if the Employer fails to pay?
Simple interest is applied for the period between final date for payment and once the payment is made. Interest Rate is set within the contract definitions.
(1) What is a payment certificate
A certificate which certifies the gross value of work executed, less any retention, less previous amounts previously certified, to give a net amount for payment within the period.
(2) Explain the process of issuing a payment certificate
- Receive the Contractor’s interim application for payment. Review this before the site meeting
- Meet the contractor’s QS on site.
- Inspect the works on site to ascertain works are in accordance with the contract, and the basis of the valuation (quantities, % complete etc). Ascertain any additional substantiation that may be required
- Produce photographic record and take notes.
- Record adjustments made to the contractor’s interim application for payment, give reasons. Agree with QS
The Payment Certificate
Gross valuation
Adjustments (retention)
= Net valuation
Less previously paid
= Net balance due.
(1) What are the main elements of a valuation / what do you expect to
be included in a valuation?
Preliminaries
Measured work
Variations
Materials on site
Materials off site
Loss and expense
Retention
(2) Explain the process of issuing the completion certificate
(1) What is a provisional sum
A sum of money included within the contract to cover the cost of something that cannot be entirely foreseen / costed / detailed accurately at the time of tender invitation.
‘Defined’ or ‘Undefined’
Defined -
(1) what is the difference between a provisional sum and a PC sum?
(2) How would a variation be administered under a JCT contract?
(2) How did you administer the provisional sum / variation under the JCT contract
(2) Can you explain the change control procedure
(1) What is an extension of time