Building Pathology (2) Flashcards

1
Q

(1) North Caldeen Road - What is cut edge corrosion and why does it occur?

A
  • Corrosion that affects profiled metal roofs typically at the sheet laps and ends.
  • Profiled metal sheets (typically galvanised steel) are coated with a factory finish. Once coated, the galvanised steel sheets are rolled into coils before being sent to be cut and profiled.
  • Where they are cut, this leaves an untreated metal edge.
  • Over time, the treatment begins to peel back from the edge.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

(2) North Caldeen Road - How to treat / prevent cut edge corrosion?

A
  • If not too damaged, the surface level corrosion can be removed with an angle grinder. The edge can then be treated with a silicone based paint (such as Seamsil). These products can often come with a guarantee, where Seamsil offers a 15-year guarantee.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

(2) North Caldeen Road - What are the different types of profiled steel finishes and how do you identify them?

A

The three main types of profiled metal steel finishes are;
- Plastisol (PVC). This can be identified with a slightly leathery, raised finish.
- PVF2 / PVDF - Paint based, this has a smooth finish.
- Powder Coated - Polyester based (synthetic resin) very smooth yet almost slightly plastic feeling. Typically used on windows and doors.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is corrosion?

A

Deterioration of materials (usually metals) by chemical / electrochemical reaction with their environment (oxygen / water).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are the stages of failure to a paint finish of profiled steel?

A

Loss in colour, delamination, rust.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

(2) North Caldeen Road - What other defects did you identify and the causes?

A

Leaking gutters - failed gutter linings
Drainage issues due to build up of gutter sediment
Rotten window frames
Impact damage / damage to cappings.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

(2) Trystings Close - What would be the typical construction of a 1960s bungalow?

A

Timber trussed roof
Cavity wall (early) with brick outer leaf and blockwork inner leaf
Strip foundations
Casement windows of steel / aluminium / timber
Concrete slab floor with sometimes a DPM of polythene / bitumen.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

(2) Trystings Close - How did you conduct your inspection?

A

I first did a desktop study, where I found borehole data of the local area (Claygate). I then did some research (OSMAPS) to determine the age of the premises.
I arrived on site and discussed with the owner to establish the timeline of the cracking.
I asked whether any as built drawings were made available but there were none; however I was informed that the extension was carried out in the 1990s.
I had a walk around the site to familiar myself. I recorded the construction of each element, and noted the location of the services.
I observed the topography of the site.
I carried out a sketch noting; crack locations, widths, types of cracks. I used a level, and discovered that the walls were not deflecting.
Internally, I recorded the location of the internal cracks. I checked for any floor sags / gaps in the skirting or doors jamming.
After the survey I wrote up my notes and determined that the cracks were affecting the serviceability of the premises, however at present it was not deemed to be structurally unstable / dangerous.
As per BRE digest 251, I determined the damage as ‘Category 3’ - the cracks could be repaired by a skilled trade but my main concern was future progressive movement. This is because the ground conditions were likely clay based, and I observed a large Oak tree to the rear of the garden within a proximity of 5-6 metres of the extension.
This would warrant further monitoring (Tell-Tales) and further investigation by a structural engineer. However, the buildings insurance provider should be notified as they would likely monitor and investigate the problem if subsidence is covered within the policy.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What are tell-tales and how would you use them?

A

It is a crack monitoring gauge that monitors horizontal and vertical movement across a crack on a flat surface. It consists of two plates which overlap for a part of their length.
The bottom plate is marked in MM and the top plate is transparent and marked with a hairline cursor.
This is fixed into the wall using screws and adhesive
You fix the tell tale across the crack. As the crack opens or closes the cursor moves relative to the calibration scale
You then record the opening and closing of the crack to be able to tell if the movement is structurally progressive.
10 mm horizontal - 20mm vertical

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

LVL 1 - What is differential settlement, subsidence and heave?

A

Differential Settlement - Unequal foundation pressures arising from such factors such as extensions added to existing buildings or concentrations of load.

Subsidence - A movement down in the ground level. In clay soil, the growth of large trees which remove water from the ground can cause this. This can lead to vertical cracking in the centre of the building or diagonal cracking towards the corner of the building, which is stepped and gets wider at the top due to rotational movement. Generally leading from ground level.

Heave - Opposite to subsidence, an upward movement. In clay soil the removal of a tree will lead to an increase of moisture content which will cause the soil to swell. This causes wider cracking at the bottom and thinner at the top.

I believed the action upon the building was differential settlement, mostly because the cracking was along the joint line. This would likely occur naturally, but due to the shrinkable soil conditions, heatwave and the presence of the mature Oak Tree, this caused a great deal of settlement in this instance. In any case further input should be taken from a structural engineer, the cracks should be monitored and remedial work carried out if required.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

(2) Trystings Close - Why would clay soils be an issue?

A

Clay soils - mouldable, smooth and greasy

Due to the open nature of the molecules, they readily absorb and let go of water. This means that clay soils shrink and swell depending on moisture content.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

(2) Trystings Close - Why would the tree have an affect here?

A

Due to the heat wave, desiccation of the soil would occur, resulting in downward movement of the soil in the summer. The tree would be extracting moisture from soil in an already dry environment.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

(2) Trystings Close - If the foundations were found out to be insufficient, what would be the options?

A

Three options:

  • Tree removal (however there would be a risk of heave). Also the tree might be a protected under a Tree Preservation Order.
  • Underpinning.
  • The exact cause must be investigated further, and separated from the design process.
  • BS 8004 ‘ Before underpinning is resorted to, the fullest possible investigation should be carried out by an experienced and competent person to determine whether an underpinning procedure will achieve the object intended’.
  • The shape, size, depth and condition of the existing foundations of a damaged building are examined.
  • Geotechnical investigation - trial pits to define the soil type, clay, silt, sand, gravel, silty clay, sandy gravel etc.
    Consistency and strength
    Structure and texture
    Moisture conditions
    Root areas

During the investigation it is imperative that the level of any water table is determined. These have a major influence on the choice of type of underpinning (standpipe used to monitor ground water levels) although for domestic it is not often used.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

(2) Trystings Close - Can you explain the types of underpinning?

A
  • Mass Concrete (most popular)
    ‘traditional method - extending an existing strip or pad foundation downwards to reach an adequate bearing stratum. Constructed in sequence of ‘bays’, where each section is excavated, concreted and pinned. Generally restricted up to 2m depth due to labour costs. Propping may be required
  • Beam and pier (second)
    Reinforced concrete beam formed at or above the footing level spanning between mass concrete piers
    Small areas of brickwork below DPC are broken out and props ‘stools’ are fixed into the wall (Steel) with precast concrete top and bottom plates
    The remaining brickwork or existing footing is removed, reinforcement and formwork fixed and the beam cast into the wall; the stools are incorporated into the beam. The beam is pinned up to the existing brickwork. Isolated piers are then excavated to appropriate depth, concreted and pinned up to the underside of the beam
    Used in most situations
    Less risky
    High labour costs in hand excavation tend to restrict their use to depths less than about 4m
  • Beam and pile (less etc.)

Where a suitable bearing stratum is not available within a depth economical for hand excavation (>4-5m) or through shallower depths through soft, loose or water bearing strata.

Similar to beam and pier, but beams are extended at corners and intersections to form caps attached to pile heads.
Piles usually augered or bored and cast in-situ.
Can be used satisfactorily in all circumstances but economical to depths of 4-6 m.
Less risky
Trickier detailing forming pipe caps after completion of the beams.

Piles / Mini pile

Loads transferred directly from the stricture to the piles either by needles or cantilevered pile caps, or by placing the piles directly through the existing footing.
Depends on inherent strength of existing structure

  • Expanding resin injection
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

(3) Forge Cottages - What is timber decay?

A

The deterioration of wood cells via fungi - resulting in the loss of weight and strength of the timber

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

(3) Forge Cottages - Why is a mortar fillet detailing unfavourable? What would be the solution?

A

They are prone to cracking and moisture penetration

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

3) Forge Cottages - What is an impermeable sarking membrane?

A

A membrane that is fixed after the battens to provide a line of defence for moisture. Older felts are often bitumen based products which are non-permeable. Breathable membranes are synthetically made which allow for moisture to escape from one side. Often foil backed to reflect heat

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

3) Forge Cottages - What does 22% wood moisture mean?

A

> 22% wood moisture is the percentage of wood moisture that will allow fungi to develop in timber.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

3) Forge Cottages - Talk me through how you used the electronic moisture meter

A

I used the electronic moisture meter to measure moisture contents throughout the whole roof area, not simply around the area of where the moisture is apparent.

I took note of the moisture contents of the timbers from the rafters, purlins, battens and joists where possible throughout all accessible areas.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

3) Forge Cottages - How did you know condensation was also an issue

A

I noted that the moisture levels were excessive (70%^) around the rafters that were affected by the roof leak.

However, a consistent reading of around 20% was noted in all other areas.

This lead me to the conclusion that condensation was affecting the loft space, as originally it was a cold roof construction. Sarking membrane installed (probably around the 1960s-1970s), and loft insulated. Naturally, the ventilation would be provided by the gaps in the tiles and through the soffit.

Since insulation was provided throughout at the eaves lead me to this conclusion.

As a backup check, I measured the humidity levels using a humidity meter, which were measured around 70% Relative Humidity.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

3) Forge Cottages - Why did you recommend vent tiles?

A

These are an inexpensive fix for a homeowner. Can be afforded by ‘mushroom’ vent tiles or ridge tiles. In some instances soffits can be provided with vents in cold roofs - however there was no overhang on this roof.

22
Q

3) Forge Cottages - What is condensation? What is relative humidity?

A

Condensation is the conversion of vapour or gas into a liquid.

Condensation occurs in a building when water vapour condenses on a cold surface.

Humidity = the amount of water vapour present in the air.

Relative humidity (RH) (expressed as a percent) alsomeasures water vapor, but RELATIVE to the temperature of the air. In other words, it is a measure of the actual amount of water vapor in the air compared to the total amount of vapor that can exist in the air at its current temperature.

Air can hold different amounts of moisture depending on temperature. Higher temperature = higher levels of moisture.

Lower temperatures = lower levels of moisture.

A higher humidity level with a low temperature = higher dew point, meaning that water droplets will form at a warmer temperature.

Dew point = temperature at which water droplets begin to condensate.

23
Q

3) Forge Cottages - What is penetrating damp?

A

Moisture moving from the exterior of the building internally

24
Q

3) Forge Cottages - What is dampness?

A

Presence of moisture within a material

25
Q

3) Forge Cottages - Why would ventilation tiles help, and how are these installed?

A

Ventilation tiles would help by increasing the air flow. This will lower the humidity levels within the loft space. These can either be installed using vent tiles which can be either used at the ridge or pitch.

26
Q

3) Forge Cottages - Did you use a humidity meter? How do these work?

A

Humidity meters measure the relative humidity. They display this as a percentage and provide a dew point temperature. Relative humidity should be around 40-50% for comfort.

27
Q

3) Forge Cottages - How would you know that this is successful?

A

Although I was only appointed for a building survey, the way in which they could determine whether this was acceptable is by taking further readings. <20% would mean that the remedial method had worked.

28
Q

3) Forge Cottages - How is a lead flashing installed?

A
29
Q

3) Forge Cottages - How do you calibrate a humidity meter?

A
30
Q

3) Forge Cottages - How do you calibrate a moisture meter?

A
31
Q

3) Forge Cottages - Can you describe a little more about the localised decay to the rafters. How did you identify that the timber was decaying?

A

The end of the rafter which was affected by penetrating damp had white staining white rot in the area of the defective chimney detailing.

32
Q

3) Forge Cottages - Can you describe a little more about the localised decay to the rafters. How did you identify that this was wet rot and not dry rot?

A

I noted it was wet rot because it was exhibiting white staining around the darkened timbers; this is attributable to wet rot (Coniphora Puteana).

It was not considered dry rot as dry rot generally will not colonise timber that is saturated (20-40%) . Dry rot would be discernible from wet rot due to deep, cuboidial cracking (although it can occur in wet rot), crumbles under fingers.
A good indicator is cotton wool type mycelium. Hyphae have tinges of lilac and patches of yellow.
The strands are grey/white when branching out.
When dried (over night) they become very brittle and grey.
Fruit bodies shaped like pancakes / brackets, tough and fleshy when fresh, but brittle when dry.
Margin remains white but centre rusty red.
Rust coloured spore dust spreading on other surfaces.

33
Q

3) Forge Cottages - Can you describe a little more about the localised decay to the rafters. How would you recommend that this is treated?

A

Considering I did not observe any evidence that dry rot was affecting the timbers, and that it was not affecting a main structural element (such as a purlin), the first priority would be to eliminate the source of damp (condensation and penetrating damp) and promote drying.

The area of wood that is rotten could be removed, and a localised preservative treatment could be applied (liquid preservative, borate rods, pastes or tables). The presence of boron disrupts the cellular production of enzymes that allow the fungi to extract nutrients from the wood

If severely damaged - the affected area could then be cut out and repaired via splice / resin repair to the rafter end. The new bits of timber could be treated with a wood preservative.

Always consult a structural engineer if affected load bearing elements, building regulation approval may be required.

34
Q

How would you treat dry rot?

A

Therefore identifying and removing the cause of moisture is key to eradicating the rot.
- Inspection of timbers in all areas, probe the timbers. Remove skirtings, floor boards to reveal joists
- Woodwork in adjacent rooms need to be inspected
- Removal of plaster where timber is embedded into walls
- Removal of rotted wood 300-450mm beyond the last indication of rot, and replaced with treated timber. Any remaining timbers at risk of being affected by the dry rot should be treated with an effective fungicide.
- Where the dry rot has passed through the masonry, it should be isolated using physical containment and/or masonry sterilisation.

Always consult a structural engineer if affected load bearing elements, Always consult a structural engineer if affected load bearing elements, building regulation approval may be required.

35
Q

3) Forge Cottages - How did you investigate the moisture ingress?

A
36
Q

3) Forge Cottages - Did you advise the Client how long the drying would take?

A

A matter of months (3-4) and monitoring would be required.

37
Q

3) Forge Cottages - How would you know that the remedial work was successful?

A

As this was a level 3 building survey, I heard no further feedback from the Client. In practice, I would know that the remedial work was successful by taking further moisture meter readings as I did in the original inspection.

38
Q

3) Treadway - Why did you advise the roof was coming towards the end of its usable life?

A

A large number of cracked tiles

39
Q

3) Treadway - Who did you advise should carry out the works?

A

The works were to be carried out by the Landlord, as there was a schedule of condition on file.

40
Q

3) Treadway - Why did you advise the Client that it was a health and safety hazard?

A
  1. Access - Repairing the tiles could lead to further tiles being damaged.
  2. The tiles contained asbestos which is hazardous to human health.
41
Q

3) Treadway - How would the replacement cladding be achieved by the Client during tenancy?

A

Realistically, this would be carried out at the tenant’s exit. In this case it was only a number of years.

A careful short term repair should be carried out and replacement carried out at lease end.

Alternatively, roof over cladding could be carried out.

42
Q

3) Treadway - Why didn’t you recommend overcladding?

A

This was an option

43
Q

(1) What is an electronic moisture meter and how does it work?

A

Typically comes in pinless or with pins

Used on the surface of timber, and measures the electrical resistance.
Pin: electrical current flows from one pin to the other. Wood does not conduct electricity. Takes a measurement from the surface of the wood.
Drier wood = more resistance.
Pinless: electromagnetic sensor pad, can go down as deep as .25” =- 1.5” depending on calibration.
Pin moisture meters require a greater amount of readings to be taken.

Electrical resistance method is not accurate for masonry and plaster and often misdiagnose moisture trapped within walls.

44
Q

(1) What other forms of damp testing are there?

A

Drilling for masonry - Masonry is drilled to take sample of the dust. This dust is taken to the lab and weighed. Assuming it is wet, this will be the (Wet weight).
This is then placed in an industrial oven to dry, the sample is then weighed again (dry weight).

Moisture content will be wet weight-dry weight x100 / dry weight

Removable core samples can also be taken.

Calcium carbide technique - Variation of the drilling technique, but provides a relatively accurate on-site determination of moisture content.

Individual samples are inserted with calcium carbide into a pressurised vessel to provide a reading of moisture content. The moisture in the drilled sample reacts with the calcium carbide to produce acetylene gas. The subsequent gas pressure produces an indication of moisture content.

45
Q

(1) What are the common deleterious materials that you might encounter as a surveyor?

A
46
Q

(1) Give me an example of modern and historical construction methods.

A
47
Q

(1) Can you describe what asbestos is and the different types of asbestos

A
48
Q

(1) What are deleterious materials?

A
49
Q
A
50
Q

(2) Trystimgs Close - BRE Digest 251 - How did you use this material to assess the cracking damage?

A