Construction Documents & Services Flashcards

1
Q

Describes the positive and negative environmental effects of a proposed action, and usually lists one or more alternative actions that may be chosen instead of the described action.

A

Environmental Impact Statement

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

SMACNA

A

Sheet Metal and Air Conditioning National Association

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

A forecast of probable costs, as opposed to a firm bid

A

Estimate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Instructions in the bidding documents for preparing and submitting bids for a project. Also called ‘instructions to bidders’

A

Notice to bidders

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

A specification which calls for desired materials, products, systems and equipment by their trade names and model numbers

A

Proprietary Specification

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

A contractor’s written request for payment due on account of work completed and/or materials suitably stored on site. Also called ‘application for payment’

A

Payment Request

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

An ordinance which specifies the period of time within which legal action must be brought to obtain legal relief for damage or injury

A

Statute of Limitations

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

A document issued by the governing authority stating that a building complies with applicable laws and permitting occupancy for its designated use

A

Certificate of Occupancy

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Fire and property damage insurance for a project during construction, usually purchased by the owner. Also called ‘property insurance ‘

A

Builder’s Risk Insurance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

IPC

A

International Plumbing Code

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Abbreviation for not-in-contract, referring to items neither furnished nor installed by the contractor

A

NIC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Investigation involving remediation of a site with the aim to delineate the physical extent of contamination based on recommendations made in Phase II assessments

A

Phase III Environmental Assessment

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

A method to deliver a project in which the design and construction services are contracted by a single entity

A

Design Build

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

An agreement under which one party (the surety or bonding company) guarantees to make good to another party (the obligee or owner) the debt, default, or failure to preform of a third party (the principal or contractor). Also called a ‘bond’

A

Surety Bond

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

MERV

A

Minimum Efficiency Reporting Value

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

A proposal by a bidder for an amount to be subtracted from or added to the base bid if the corresponding change in the work is accepted. This may be either a deductive or additive alternate

A

Alternate Bid

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

An amount not included in the contract sum to cover the cost of certain items not specified in detail. Hardware and other finish items are often handled in the manner

A

Cash Allowance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

A bond obtained by the contractor or owner, which guarantees that the project will be completed free of liens

A

Completion Bond

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

The sum of money stated in the bid for which the bidder offers to do the work, not including any alternate bids

A

Base Bid

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

Direction of the work by the contractor’s personnel. Supervision is not the responsibility of the architect

A

Supervision

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

The invitation to bed, instructions to bidders, bid form, and the contract documents

A

Bidding Documents

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

Expense items directly incurred by or attributable to a specific project.

A

Direct Expense

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

An alternative to litigating a dispute, in which one or more arbitrators hears the evidence and renders a decision

A

Arbitration

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

A shop drawing, project data, or sample submitted by the contractor to the architect for review prior to incorporation in the work

A

Submittal

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

An invitation to a selected list of contractors soliciting bids for a project.

A

Invitation to Bid

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

ESA

A

Environmental Site Assessment

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
27
Q

A proprietary specification which requires a particular brand or trade name and does not permit any substitution

A

Closed Proprietary Specification

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
28
Q

A term used to describe poor air quality, which can lead to discomfort and possible disease

A

Sick Building Syndrome

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
29
Q

Building air quality

A

BAQ

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
30
Q

Indirect expense, that is, expenses indirectly incurred and not chargeable to a specific project. Also called ‘indirect expense’

A

Overhead Expense

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
31
Q

Coverage by contract (insurance policy), whereby one party (the insurance company) agrees to indemnify or reimburse another (the insured) against loss from a specified hazard

A

Insurance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
32
Q

Report prepared for a real estate holding that identifies potential or existing environmental contamination liabilities

A

Phase I Environmental Assessment

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
33
Q

Intrusive investigation which collects original samples of soil, groundwater, or building materials to analyze for quantitative values of various contaminants

A

Phase II Environmental Assessment

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
34
Q

Energy Standard for Building Except low-Rise residential Buildings is a standard that provides minimum requirements for energy-efficient designs for buildings except for low-rise residential buildings

A

Ashrea 90.1

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
35
Q

A measurement scale designed to rate the effectiveness of air-filters

A

MERV Rating

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
36
Q

Failure to meet the ordinary standard of care expected of an architect or other professional in a specific circumstance

A

Negligence

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
37
Q

Analysis typically addressing both the underlying land as well as physical improvements to a property

A

Environmental Site Assessment

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
38
Q

NFPA

A

National Fire Protection Agency

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
39
Q

NEC

A

National Electrical Code

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
40
Q

IMC

A

International Mechanical Code

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
41
Q

IFC

A

International Fire Code

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
42
Q

IECC

A

International Energy Conservation Code

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
43
Q

EPA

A

Environmental Protection Agency

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
44
Q

FEMA

A

Federal Emergency Management Agency

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
45
Q

NIOSH

A

National Institute for Occupational Safety and Health

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
46
Q

OSHA

A

Occupational Safety and Health Administration

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
47
Q

AHJ

A

Authority Having Jurisdiction

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
48
Q

ANSI

A

American National Standards Institute

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
49
Q

ASHRAE

A

American Society of Heating, Air Conditioning and Refrigerating Engineers

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
50
Q

ASTM

A

American Society of Testing Materials

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
51
Q

IBC

A

International Building Code

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
52
Q

ICC

A

International Code Council

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
53
Q

IEBC

A

International Existing Building Code

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
54
Q

The process of verifying that a building’s systems are performing as required by the owner and as specified in the contract documents.

Building commissioning supports training of maintenance personnel and documents that the goals for energy efficiency, HVAC efficiency, water conservation and occupant health are being meant

A

Building Commissioning

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
55
Q

A collaborative approach to designing, fabricating, and constructing buildings where the architect, technical consultants and contractors work as one team to reduce delivery times, reduce costs, reduce wastes, and eliminate litigation

A

Integrated Project Delivery (IPD)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
56
Q

BIM

A

Building Information Modeling (BIM) refers to the process of generating and managing building data during its life cycle.

BIM can incorporate nongraphical statistical data modeling as well as geometric modeling. Computer modeling facilitates linking nongraphic data to a 3-D graphic model

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
57
Q

A legal document addressing the sustainability issues within a project.

The sustainability plan details the sustainable objective; sustainable measures targeted and implementation strategies; roles and responsibilities of owner, architect and contractor for achieving sustainable measures; details of design reviews, testing, or validation of sustainable measures; and documentation required for certification

A

Sustainability Plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
58
Q

A legal term for a specific design feature or construction process that must be enacted, or a post-occupancy condition that must be met, in order to achieve a sustainable objective

A

Sustainable Measure

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
59
Q

A legal term for the owner’s intent to implement sustainable measures in a project for the purposes of achieving green building certification or other environmental benefits

A

Sustainable objective

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
60
Q

Refers to the evaluation of a building’s design construction methods, and post-occupancy performance in comparison to a set of predefined criteria related to sustainable building practices, consequently achieving specific performance thresholds.

Examples of green rating systems include ENERGY STAR, Green Globes, LEED, and BREAM

A

Green Building Certification

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
61
Q

Design and construction projects incorporating positive environmental considerations such as energy efficiency, water efficiency, occupant health, and the conservation of material resources, while reducing negative impacts such as pollution and waste generation,

Also called ‘green design’

A

sustainable design

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
62
Q

Instructions in the bidding documents for preparing and submitting bids for a project. Also called ‘notice to bidders’

A

Instructions to Bidders

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
63
Q

A memorandum which outlines the types and limits of the insurance coverages carried by the contractor for a project

A

Certificate of Insurance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
64
Q

A statement furnished to the architect by the contractor reflecting the amounts to be allotted for the principal divisions of the work. It serves as a guide for reviewing the contractor’s periodic applications for payment

A

Schedule of Values

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
65
Q

An amount established in an agreement between an owner and a contractor as the maximum cost of performing specified work. Also called the ‘upset price’

A

Guaranteed Maximum Cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
66
Q

An engineer or other specialist retained by the architect to provide specified professional services to the architect which the architect is required to provide to the owner under the owner-architect agreement

A

Consultant

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
67
Q

Insurance which financially protects the insured against liability on account of bodily injury or property damage sustained by another

A

Liability Insurance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
68
Q

An agreement under which the architect or contractor is paid a specific amount as the total fee for services performed. Also called a ‘stipulate sum contract’

A

Lump Sum Contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
69
Q

A letter signifying intention to enter into a formal agreement and setting forth the general terms thereof

A

Letter of Intent

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
70
Q

Additional services rendered to the owner by the architect following completion of the project

A

Post-Completion Services

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
71
Q

A material, systems, or product proposed by a contractor as being equivalent to that required by the contract documents

A

Substitution

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
72
Q

A specification which defines products or systems by describing end results

A

Performance Specification

73
Q

As defined in the AIA General Conditions, completion of a project to the point where the owner can occupy all or designated portions of the work for the purpose for which it is intended

A

substantial completion

74
Q

A claim on property by those who furnish material or labor for the construction of a building. Clear title to the property cannot be obtained until the claim is settled

A

Mechanic’s lien

75
Q

A material or method that is approved by the architect as being equivalent to what was originally specified

A

approved equal

76
Q

The requirements that a professional exercise reasonable ability and judgement in a specific circumstance, the absence of which constitutes negligence. Also called ‘standard of care’

A

due care

77
Q

A document by which one relinquishes the right of a mechanic’s lien against the property of another

A

waiver of lien

78
Q

One who has a contract with a prime contractor to perform a portion of the work

A

subcontractor

79
Q

Fire and property damage insurance for a project during construction, usually purchased by the owner. Also called ‘builder’s risk insurance’

A

property insurance

80
Q

An item of work involving additional cost

A

extra

81
Q

a written statement of the owner’s conditions and requirements for the project

A

program

82
Q

Professional services rendered by the architect, upon the owner’s request, in addition to the basic services identified in the owner-architect agreement. Also called ‘additional services’ (of the architect)

A

extra services

83
Q

A document signed by the owner and the architect, which authorizes a change in the work, the contract sum, or the contract time. it is used when there is not complete agreement on the terms of a change order

A

construction change directive

84
Q

A systematic listing of construction trades, materials, systems, and administrative requirements published by the Construction Specifications Institute (CSI) for the purpose of organizing construction specifications

A

CSI MasterFormat

85
Q

The elements which comprise an exit to the outside, including aisles, corridors, doors, and stairways

A

means of egress

86
Q

An owner-architect agreement under which the professional fee is based upon a percentage of the construction cost of the project

A

percentage agreement

87
Q

Insurance which financially protects an architect against claims for damages resulting from professional negligence. Also called ‘professional liability insurance’

A

errors and omissions insurance

88
Q

An amount established in an agreement between an owner and a contractor as the maximum cost of performing specified work. Also called the ‘guaranteed maximum cost’

A

upset price

89
Q

Overhead expense, that is, expenses indirectly incurred and not chargeable to a specific project. Also called ‘overhead expense’

A

indirect expense

90
Q

A specification which refers to quality standards established by recognized testing authorities or by the federal government

A

reference specification

91
Q

A term sometimes erroneously used to describe drawings revised to show changes made during construction. Sometimes erroneously called ‘as-built drawings’

A

record drawings

92
Q

A contract for building construction under which one prime contractor is responsible for the entire project, in contrast to having separate contracts

A

single prime contract

93
Q

The agreement between the owner and the contractor for the construction of a project

A

general contract

94
Q

An amount stated in dollars per unit, provided by the contractor with his or her bid for adding or deleting specific portions of the work

A

unit price

95
Q

A surety bond guaranteeing that the bidder will sign a contract, if offered, in accordance with his or her proposal

A

bid bond

96
Q

The maximum allowable cost of the construction work, as established in the owner-architect agreement

A

fixed limit of construction cost

97
Q

Part of the contract documents, prepared by the architect, which may modify provisions of the general conditions of the contract

A

supplementary conditions

98
Q

A deposit of money required for each bidder as security for the bidding documents, to ensure the return of the documents by unsuccessful bidders

A

deposit for bidding documents

99
Q

The substitution of one entity for another with regard to legal rights

A

subrogation

100
Q

A proprietary specification which names several acceptable materials, products, or systems, any of which may be used by the contractor

A

open propriety specification

101
Q

Professional services rendered by the architect, upon the owner’s request, in addition to the basic services identified in the owner architect agreement. Also called ‘extra services’

A

additional services (of the architect)

102
Q

A choice given to the contractor to provide specified alternates without prior approval of the architect

A

option

103
Q

A specification which describes all product components, arrangements, assembly methods, properties, and other details and requirements

A

descriptive specification

104
Q

On-site examination of the contractor’s work by the architect to determine in general if it is proceeding in accordance with the contract documents

A

observation

105
Q

PERT

A

Acronym for project evaluation review technique. A form of network analysis developed for military work and similar to the critical path method

106
Q

XCU

A

The exclusion from insurance coverage for liability arising out of (X) explosion or blasting, (C) collapse of or structural damage to a building, and (U) underground damage caused by mechanical equipment

107
Q

Salaries and wages attributable to a specific project, plus benefits such as employment taxes, insurance, sick leave, holidays, vacations, pensions, and similar contributions and benefits

A

direct personnel expense (DPE)

108
Q

Working drawings, specifications, addenda, general conditions of the contract, supplementary conditions, and the owner-contractor agreement

A

contract documents

109
Q

An approach to the delivery of goods or services in which quality is determined by customer satisfaction and conformance to requirements

A

total quality management (TQM)

110
Q

A document prepared by the architect stating that the work is substantially complete, thereby establishing the date of substantial completion. It generally fixes the time within which the contractor must complete the unfinished work listed

A

certificate of substantial completion

111
Q

The lowest bid which complies with all the stipulated requirements

A

lowest acceptable bona fide bid

112
Q

The sum established by the owner as available for the entire project, including the construction budget, land cost, equipment cost, financing cost, cost of professional services, and contingency allowances

A

project budget

113
Q

Federal civil rights legislation which establishes the right of persons with disabilities to equal access to sites and buildings and sets design guidelines for its implementation

A

Americans with Disabilities Act (ADA)

114
Q

A legal document signed by a supplier of material or labor for a project, which releases his or her mechanic’s lien against the property

A

release of lien

115
Q

Published public notice soliciting proposals for a construction project

A

advertisement for bids

116
Q

Describing a construction procedure in which construction on each phase of a project is begun when its design is completed, without waiting for overall project design completion

A

fast-track

117
Q

A material or assembly submitted for the architect’s approval prior to manufacture or delivery to the project

A

sample

118
Q

A legally enforceable assurance of the quality of materials and labor furnished for a project, or of the length of time that a project or a part thereof will perform satisfactorily. Also called a ‘guarantee’

A

warranty

119
Q

Part of the contract documents, other than the general and supplementary conditions, describing unique conditions of a project

A

special conditions

120
Q

The architectural services normally required for a building project, usually consisting of schematic design, design development, construction documents, bidding or negotiation, and construction contract administration

A

basic services

121
Q

An individual or company that guarantees to make good to another party the debt, default, or failure to perform of a third party

A

surety

122
Q

The contractor’s representative at the site

A

superintendent

123
Q

A legally enforceable assurance of the quality of materials and labor furnished for a project, or of the length of time that a project or a part thereof will perform satisfactorily. Also called a ‘warranty’

A

guarantee

124
Q

An amount included in a construction budget, normally 5 to 10 percent, to provide for unforeseen or unpredictable costs

A

contingency allowance

125
Q

Federal legislation that requires the Department of Labor to set prevailing wages for government-financed construction projects

A

Davis-Bacon Act

126
Q

The completion of all work in accordance with the terms and conditions of the contract documents

A

final completion

127
Q

The extra time available for a construction activity above its estimated time duration, without causing any delay of project completion

A

float

128
Q

A contractor’s written request for payment of the amount due on account of work completed and/or materials suitable stored on site. Also called ‘payment request’

A

application for payment

129
Q

A proposal by a bidder for an amount to be added to the base bid if the corresponding change in the work is accepted

A

additive alternate

130
Q

An agreement providing for payment for professional services based upon the direct personnel expense multiplied by an agreed factor

A

multiple of direct personnel expense agreement

131
Q

The date, certified by the architect, when the construction is sufficiently completed, in accordance with the contract documents, so that the owner can occupy the project for the intended use

A

date of substantial completion

132
Q

An agreement under which the architect or contractor is paid a specific amount as the total fee for services performed. Also known as a ‘lump sum contract’

A

stipulated sum contract

133
Q

The part of the contract documents, prepared by the architect, which graphically illustrates the construction required for the project

A

working drawings

134
Q

One who acts on behalf of another

A

agent

135
Q

the difference between the list price and the actual price paid

A

trade discount

136
Q

A proposal by a bidder for an amount to be subtracted from the base bid if the corresponding change in the work is accepted

A

deductive alternate

137
Q

A clause in a cost plus fee contract between the owner and contractor in which the savings between the guaranteed maximum cost and the actual project costs are proportionally shared

A

incentive clause

138
Q

A list of items to be corrected or completed, which is provided by the contractor and usually expanded by the architect based on a detailed inspection of the work prior to substantial completion

A

punch list

139
Q

Regulations which provide for accessibility to buildings and sites for persons with disabilities

A

barrier-free provisions

140
Q

A charge against the contractor for failing to complete the project by a specific date

A

penalty

141
Q

a term sometimes erroneously used to describe drawings revised to show changes made during construction. The correct term is ‘record drawings’

A

as-built drawings

142
Q

An agreement under which one party (the surety or bonding company) guarantees to make good to another party (the obligee or owner) the debt, default, or failure to perform of a third party (the principal or contractor). Also called a ‘surety bond’

A

bond

143
Q

An amount withheld from each payment to the contractor in accordance with the terms of the owner-contractor agreement

A

retainage

144
Q

One of several owner-contractor agreements for a project, each of which provides for constructing a major portion of the work (general construction, electrical, mechanical, etc) by a different contract

A

separate prime contract

145
Q

The requirement that a professional exercise reasonable ability and judgment in a specific circumstance, the absence of which constitutes negligence. Also called ‘due care’

A

standard of care

146
Q

An amount added to the contract sum either by an accepted additive alternate or by a change order

A

addition (to the contract sum)

147
Q

A contractual obligation whereby one party agrees to guarantee another party against loss or damage from specified liabilities. Also called the ‘hold harmless clause’

A

indemnification

148
Q

Drawings prepared by the contractor, subcontractor, manufacturer, or supplier, showing how specific portions of the work shall be fabricated and/or installed

A

shop drawings

149
Q

A small-scale plan of a building or complex of buildings

A

key plan

150
Q

Insurance which covers workers’ job-related injuries, usually required by law

A

workers’ compensation insurance

151
Q

The owner’s job site representative

A

clerk of the works

152
Q

A provision in the construction contract for payment of a bonus to the contractor for completing the project prior to a specific date, and for a charge (penalty) against the contractor for failing to complete the project by that date

A

bonus and penalty clause

153
Q

The total amount payable by the owner to the contractor, as stated in the owner-contractor agreement, for performing the work under the contract documents

A

contract sum

154
Q

Part of the contract documents, comprising written descriptions of materials, construction systems, and workmanship

A

specifications

155
Q

A statement by the architect informing the owner of the amount due the contractor on account of work completed and/or materials suitable stored

A

certificate for payment

156
Q

A legally enforceable promise made by the warrantor

A

express warranty

157
Q

All materials and/or labor required for a project

A

work

158
Q

The manual prepared by the architect for a project, including the technical specifications, bidding instructions and forms, general conditions, supplementary conditions, special conditions, and other legal and administrative documents

A

project manual

159
Q

An agreement under which the contractor, or the architect, is reimbursed for his or her costs, and, in addition, is paid a fee for his or her services

A

cost-plus-fee contract

160
Q

A contractual obligation whereby one party agrees to guarantee another party against loss or damage from specified liabilities. Also called ‘indemnification’

A

hold harmless clause

161
Q

The architect’s basic services expanded to include certain additional services, such as programming, land use studios, and so on

A

comprehensive services

162
Q

The General Requirements Division of the specifications which establishes the administrative and procedural duties of the contractor, architect, and owner during construction

A

Division One

163
Q

A bond which guarantees to the owner that the contractor will perform the work in accordance with the contract documents

A

performance bond

164
Q

a bond guaranteeing to the owner that the contractor will pay for all labor and materials used for the project

A

labor and material payment bond

165
Q

A system of planning and scheduling construction operations which analyzes sequences and durations of time using network diagrams

A

critical path method (CPM)

166
Q

The part of the contract documents which states the rights, responsibilities, and relationships of the parties involved, usually by means of standard documents published by the American Institute of Architects

A

general conditions

167
Q

A proposal by a contractor to do the work required by the contract documents for a stipulated sum of money

A

bid

168
Q

Any contractor on a project who has a contract directly with the owner

A

prime contractor

169
Q

the architect’s representative at the site, who assists in the general administration of the construction contract for a project

A

project representative

170
Q

Payments made to the contractor during progress of the work on account of work completed and/or materials suitable stored

A

progress payments

171
Q

The period of time within which the work must be completed, as established in the contract documents

A

contract time

172
Q

A sum chargeable against the contractor as reimbursement for damages suffered by the owner because of the contractor’s failure to complete the work within a specified time

A

liquidated damages

173
Q

Statements or drawings which modify the basic contract documents after the latter have been issued to the bidders, but prior to taking of bids

A

addenda

174
Q

A written order to the contractor, prepared by the architect and signed by the owner, contractor, and architect, which authorizes a change in the work, the contract sum, or the contract time

A

change order

175
Q

management services performed by the architect or others, over and above normal architectural services, that contribute to the control of time and cost in the construction project

A

construction management (CM)

176
Q

the sum established by the owner as available for construction of the project

A

construction budget

177
Q

insurance which financially protects an architect against claims for damages resulting from professional negligence. Also called ‘errors and omissions insurance’

A

professional liability insurance

178
Q

working drawings and specifications

A

construction documents