Construction Administration Flashcards

1
Q

The purpose of the architects observation is:

A

To become generally familiar with the progress and quality of the work and to keep the owner informed
To endeavor to guard the owner against defects and deficiencies in the work
To determine if the work is progressing in such a way that it will be in accordance with the contract documents when completed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

A field report should include:

A

Report name and the architects project number (and a project number assigned by the owner or contractor if applicable)
Filed report number
Dare and time of the observation, and the weather conditions at the site
Work currently in progress
Number of workers present at the site or an estimate of the number, if the project is large
Observation made, including any problems, which may include photographs documenting the conditions at the site
As assessment of the conformance with the construction schedule and the estimated percentage of completion
List of items to verify, and action or information needed from owner, contractor or consultants
List of any attachments, and the names of the person making the report

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Regress documentation the architect should maintain:

A

The standard forms used to administer the contract, such as change orders, certificates of payment, etc
Correspondence
Memoranda
Meeting notes
Emails
Telephone logs
Similar written or electronic material that records the daily who, what, why, when, and how of the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What could constitute the official start of the construction work?

A

Notice to proceed as issued by the owner

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What actions should an architect take to address the issue of lead based paint being present?

A

Recommend remediation
Recommend a testing agency
Develop a hazardous materials plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

5 steps of responding to an rfi

A

Catalog the rfi
Assess the validity
Distribute to reviewer
Review information
Submit final response

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

3 types of valid rfi

A

Clarifying graphic details or content of specifications
Requesting coordination or missing information
Confirming code or contract information

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Invalid rfi

A

Incomplete or contains errors
Does not ask a question
Requests approval of means and methods, submittals, substitutions, adjustments to contract sum or time, interpretation of architects action on submittals

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Verify that the owner has received the required performance bonds and labor and material payment bonds

A

Architect

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Verify that the contractor issues acceptable certificates off insurance to the client

A

Architect

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Establishing a site visit schedule based on contract and project requirements

A

Architect

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Receiving the construction schedule from the contractor

A

Architect

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Receiving field reports from design consultants and forwarding copies to the client

A

Architect

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Reviewing and approving design consultants billings

A

Architect

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Monitoring the contractors progress against the construction schedule and notifying the client of any problems

A

Architect

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Monitoring the architects fees expended and conformance to the architects schedule

A

Architect

17
Q

Monitoring allowances and contingencies

A

Architect

18
Q

Maintaining all documentation of construction administration activities, including issuance of architects supplemental instructions, responses to rfi’s, construction change directives, and change orders

A

Architect

19
Q

Verify issuance of certificate of occupancy by the building official

A

Architect

20
Q

Monitoring conformance to sustainability requirements and process reports, certificates, and other forms as required by the type of sustainability certification being used

A

Architect