Commercial management Flashcards

1
Q

How do you proactively control costs during construction?

A

Operate a robust change control procedure.
Regular dialogue with the design team and contractor to monitor progress and issues.
Operate a rigorous payment process (interim valuations and payment certificates).
Cash flow forecasting.
Regular cost reporting.
Manage the expenditure of provisional sums (JOT contracts).
Proactive risk and contingency management.
Minor and agree variations/compensation events as they arise.
Identify and reduce the impact of claims.
Monitor and mitigate early warnings (NEC contracts).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is a purchase order (PO)?

A

A purchase order (PO) is a commercial document issued by the buyer to the seller.

Sending a PO to a supplier constitutes a legal offer to buy the product and/or service. Acceptance of a purchase order by a seller usually forms a contract between the parties.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is the purpose of change control on a construction project?

A

Change control has three key purposes:

All relevant parties are consulted.

The change is properly assessed in terms of time, cost, quality or any other impact prior to implementation.

Once the change is agreed, a record is formed to capture the change.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is cost I value reconciliation (CVR).

A

In simple terms, CVR is the profit and loss statement for the project, whereby the organisation calculates the amount of work done to date, and the cost incurred to date.

The two are then compared, with the difference being the amount of profit or loss made at that point in time.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is earned value analysis (EVA)?

A

Earned value analysis (EVA) is a method of measuring a project’s progress at any given point in time, forecasting its completion date and final cost, and analysing variances in the schedule and budget as the project proceeds.

It compares the planned amount of work with what has actually been completed, to determine if the cost and work accomplished are progressing in accordance with the programme.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

How can you protect your client from contractor insolvency?

A

Consider the structure of the company, a parent company guarantee could be obtained.
Request a performance bond.
Conduct a credit check (e.g. Dun & Bradstreet I Experian report).
Obtain references and observe if there are any industry rumours about impending insolvency.
Oblige the contractor to obtain collateral warranties from subcontractors and consultants.
Hold retention on contractor payments.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Assuming the contractor has fallen insolvent, what are the next steps you would take?

A

Inform all parties involved and secure the site.
Inform the bondsman (bank I insurance company).
Take ownership of materials off-site (if paid for in valuations).
Schedule all plant and materials.
Consider stopping pending payments to the contractor and seek legal advice.
Value completed works and value any defects.
Monitor loss & expense incurred by the employer.
Review consultant and subcontractor agreements for any payment obligations.
Retender the project, retaining existing subcontractors where possible.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is value engineering (VE)?

A

Value engineering is a method used to eliminate any unnecessary costs and/or increase the ‘value’ of a speciation or product. The ‘value’ is not necessarily related to cost, value could be increased efficiency, functionality, appearance etc.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is capital expenditure?

A

Known as CAPEX.
Funds used by a company to acquire or upgrade physical assets such as property or equipment.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is operational expenditure?

A

Known as OPEX.
Expenditure a business incurs performing its normal business operations.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Businesses typically split expenditure into capital and revenue - why?

A

Operating expenses and capital expenses are treated quite differently for accounting and tax purposes.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What are capital allowances?

A

Capital allowances are a way of reducing the after-tax cost of buying plant, equipment, fixtures and fittings, and acquiring, building, fitting-out or refurbishing property.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is the key reason for capital allowances?

A

Capital allowances are used by government as an investment incentive to encourage businesses to spend money on assets.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Is there any legislation relating to capital allowances?

A

The Capital Allowances Act 2001 (CAA 2001 ).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Can you explain what a public-private partnership (PPP)

A

A public-private partnership (PPP) is often defined as a long-term contract between a private party and a government agency for providing a public asset or service, in which the private party bears significant risk and management responsibility.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Can you briefly explain the build-operate-transfer (BOT) model please?

A

Build and operate for a certain period.

During this period, the private party has responsibility to raise the finance for the project and is usually entitled to retain all revenues generated by the project. The facility is then transferred to the public administration at the end of the concession agreement.

17
Q

Can you briefly explain the build-own-operate-transfer (BOOT) model please?

A

The private entity owns the works.

The government entity grants to a private sector party the right to finance, design, construct, own and operate a project for a specified number of years. This structure is very similar to the build-operate- transfer (BOT) structure, except that the private sector party owns the asset during the term of the agreement.

18
Q

Can you briefly explain the build-own-operate (BOO) model please?

A

The private sector party owns the project and does not have to transfer it to the government entity at the end of the term.

19
Q

Can you briefly explain the build-lease-transfer (BLT) model please?

A

The private entity builds a complete project and leases it to the government. After the expiry of the leasing period, the ownership of the asset and the operational responsibility are transferred to the government at a previously agreed price.