Case Study Flashcards
What contract was used on your project
Single Stage JCT design and build with selective tendering
Why is did you use Selective tendering
Due to the Client request to use their framework, we asked to procure outside of this but were told to proceed within the framework
Why did you use Design and build
Design and build provided the benefit of cost certainty and time efficiency which the client wanted to focus on
Why Single stage over two stages, what were the advantages
Two-stage did not provide cost certainty as early as the single-stage and two-stage had a slightly longer total duration and therefore I saw it fit to use Single-stage for these two points
What did you use to make your decision about the procurement decision
I used the Clients goals and objectives and weighed up the different options and chose a route which provided them the best match
What would you have done if your client did not want to use your suggestion?
Was your client happy
the Client agreed with my recommendation and proceeded through to tendering
what happened next? (procurement selection)
I reviewed the returned tenders and provided my client a report using their scoring matrix to choose a preferred contractor
How does D&B provide good quality?
I created a robust set of employer requirements, which fulfilled the design aspirations of the Client and the design team, which matched the Post covid hybrid working model of office space
How does D&B provide cost certainty
The contractor prices the contract a fixed price lump sum contract.
How does D&B provide time benefit
Due to the overlapping of design and construction, the overall programme is reduced compared to traditional procurement
Why Single stage if the project was complex
Due to Design and build the ability for the contractor to provide benefits of both build ability and methodology is provided, which can be provided within D&B single stage
Would a PCSA process not aided this project
Yes, a PCSA could have provided benefits for the project however, due to the reduced cost certainty and extended programe I suggested a single stage to meet my client’s goals
What is JCT
Joints Contract tribunal
What was your CAT A budget? what was included?
It was £41/ft² therefore £2,576,398