Case Study Flashcards

1
Q

What contract was used on your project

A

Single Stage JCT design and build with selective tendering

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Why is did you use Selective tendering

A

Due to the Client request to use their framework, we asked to procure outside of this but were told to proceed within the framework

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Why did you use Design and build

A

Design and build provided the benefit of cost certainty and time efficiency which the client wanted to focus on

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Why Single stage over two stages, what were the advantages

A

Two-stage did not provide cost certainty as early as the single-stage and two-stage had a slightly longer total duration and therefore I saw it fit to use Single-stage for these two points

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What did you use to make your decision about the procurement decision

A

I used the Clients goals and objectives and weighed up the different options and chose a route which provided them the best match

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What would you have done if your client did not want to use your suggestion?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Was your client happy

A

the Client agreed with my recommendation and proceeded through to tendering

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

what happened next? (procurement selection)

A

I reviewed the returned tenders and provided my client a report using their scoring matrix to choose a preferred contractor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

How does D&B provide good quality?

A

I created a robust set of employer requirements, which fulfilled the design aspirations of the Client and the design team, which matched the Post covid hybrid working model of office space

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

How does D&B provide cost certainty

A

The contractor prices the contract a fixed price lump sum contract.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

How does D&B provide time benefit

A

Due to the overlapping of design and construction, the overall programme is reduced compared to traditional procurement

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Why Single stage if the project was complex

A

Due to Design and build the ability for the contractor to provide benefits of both build ability and methodology is provided, which can be provided within D&B single stage

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Would a PCSA process not aided this project

A

Yes, a PCSA could have provided benefits for the project however, due to the reduced cost certainty and extended programe I suggested a single stage to meet my client’s goals

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is JCT

A

Joints Contract tribunal

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What was your CAT A budget? what was included?

A

It was £41/ft² therefore £2,576,398

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What was your shell and Core Budget before and After

A

Before it was £195/ft² and after £220/ft² so £19,591,000

17
Q

What is the build-up to your floor realignment cost?

A

the additional £2,360,000 includes costs for removing the floors designated and also attaching the new floors to the envelope of the building and the core and with the increase to the NIA the CAT A allowance increased by C.£110,000

18
Q

How do you achieve BCO accreditation ? Why does this provide better sales and rental values?

A

The design team were working together to make sure that the specifications which they were creating included items which ensured that aspects of the project met the criteria of

19
Q

Why was the contingency based on a percentage?

A

Due to the early stage in which we created this budget, we took from different sources to provide a contingency budget, including bench marking from other projects of a similar nature with complex facade retention and floor jacking.

20
Q

what is value engineering?

A

an essential construction concept that helps reduce costs and ensure a project is completed within budget

21
Q

What is RIBA stage 2?

A

Concept design: design team develops architectural concepts that align with project brief and scope

22
Q

What did the contract include for errors or ommisions given this was a public project? Alternative 1 or 2?

A

this was not a public project, the Client was a public entity however it was a privately funded project and therefore they use Alt 2

23
Q

What was the contract sum? Case study

A

Apprx 25m

24
Q

-Did you not consider Construction management?

A

No because my Client did not want the risk nor the direct responsbility

25
Q

-Can you give me some of the risks of the project? Case study

A

facade retention, floor alignment and jacking, updating existing structure

26
Q

What is assessed in the first stage of a two-stage tender??

A

Prelims, OHP and on oncosts

27
Q

-What would you suggest if the packages came over budget your process?

A

-Check prov sums and lump items
-Ensure contractor has understood the scope of works.
-See if some work was required
-Try and fix higher costs early.

28
Q

What is the risk of lack of competition?

A

if the tenders knew that the people tendering the job either didnt want the job or werent suited to the project they would inflate their bids therefore their would not be proper competition for the bids

29
Q

-Can you give me the contents of your tender analysis report?

A

The background to the contract.
The scope of the contract.
Pre-qualification criteria.
The tender evaluation criteria.
Reasons for rejection of unsuccessful tenders.
Reasons for the recommendation.
A summary of any post-tender negotiations.
Comparison with the pre-tender estimate.
Any implications for the project.

30
Q

What is value management

A

a creative, problem-solving. process that uses a methodical approach to include the. necessary parties and, working together, achieve the. best solutions for value from construction