Chpt 11 - Project Planning And Scheduling Flashcards

1
Q

Backward pass

A

A scheduling technique used to calculate an activity’s late start and late finish.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Critical path

A

The longest path through a network diagram schedule, which includes those activities that have zero days of float. The critical path determines the overall project duration.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Total float

A

The amount of leeway available to start or complete an individual schedule activity before it affects the planned project completion.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Forward pass

A

A scheduling technique used to calculate an activity, early start and early finish. The Ford pass must be completed before the project duration can be determined.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Gantt chart

A

Considered revolutionary when Henry Gantt first published his planning tool around 1910, a type of bar chart that illustrates a project schedule. It displays the start and finish dates of various activities of a project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Gantt chart

A

Considered revolutionary when Henry Gantt first published his planning tool around 1910, a type of bar chart that illustrates a project schedule. It displays the start and finish dates of various activities of a project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Network diagram

A

A common type of construction scheduled also called a critical path method CPM that depicts a continuous chain of activities showing them both active activity durations and the relationship of the activities. There are two types of network diagrams activity on arrow. AOA or an activity on node aon?

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Network logic

A

The order in which activities are sequenced into the network diagram relative to their interdependent relationships

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Network logic

A

The order in which activities are sequenced into the network diagram relative to their interdependent relationships

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Precedence diagramming

A

A graphic presentation of a schedule depicting project activities on a node with an arrow that depicts the dependencies that exist between activities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Short interval schedules

A

Also called a look-ahead schedule. They focus on short periods of time and a limited scope of work. They usually plan work for the 2 to 4 week time period.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What are the two most common types of schedules used in construction?

A

The two most common types of schedules used in construction are the Gantt chart or bar chart and the network diagram

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What are the two most common types of schedules used in construction?

A

The two most common types of schedules used in construction are the Gantt chart or bar chart and the network diagram

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Name the two techniques used to create a network diagram

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly