Chapter 9 - Contract Administration Flashcards

1
Q

Claim

A

An issue that occurs during construction and remains unresolved after the job is complete

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Mock-up

A

Physical models or small samples constructed to allow the arch and owner to review the appearance and function of materials, colors, textures, and other aesthetic features before incorporating them into the actual project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Partnering

A

a team-building technique, calling upon the parties to the construction contract to establish a common set of project foals and objectives and develop mutually acceptable protocol for communication and conflict resolution through a formal agreement

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Request for Information (RFI)

A

A written request for clarification regarding the plans or specifications. the request are usually made by the subcontractors through the general contractor to the architect.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Retainage

A

A certain % of money owed to the contractor for work progress that is held back by the owner to encourage completion of the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Schedule of Values

A

a budget template established early on in the project against which progress payment are measured. The schedule summarizes the total project cost by the various divisions of work.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Shop Drawings

A

A supplemental drawing to the plans and specs, prepared by subs, vendors, or fabs, that details methods, materials, and models of a product or installation associated with the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Submittals

A

Data, samples, details, colors, and product lit required by the terms of the contract to be presented to the arch by the contractor for approval prior to ordering and installation.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is partnering?

A

Partnering is a team building technique to establish a set of common goals and objectives for the project and develop a mutually acceptable protocol for communication and conflict resolution through a formal agreement.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

How does the contractor receive clarification form the architect regarding details of the design?

A

The contractor receives clarification from the architect regarding details of the design by processing a formal request for information in writing

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is the purpose of the submittal?

A

Submittals provide a means by which the arch and owner can confirm the intent of the design

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is a shop drawing?

A

A shop drawing is a special king of submittal, usually required when a building material must be fabricated from scratch. The drawing must include details, dimensions, and the configuration of the item being fabricated.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is the name of the document that establishes the template for measuring work progress as it relates to requests for payments?

A

The name of the document that establishes the template for measuring work progress as it relates to request for payment is a schedule of values.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is the name of the document that formally and officially authorizes a payment to the contractor?

A

The document that authorizes payment to the contractor is called an application and certificate for payment

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What are liquidated damages?

A

Liquidated damages are an amount of money that is assessed to the contractor for a failure to meet a specified completion date.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is retainage?

A

Retainage is a certain % of money owed to the contractor that is held back by the owner to encourage completion of the project.

17
Q

Identify two instances when a change order might need to be initiated

A

A change order would be required to correct a detail of the design that contained an error or omitted information or would be required when an owner wants to add scope to the project.

18
Q

Name three alternatives to traditional litigation for resolving construction contract disputes.

A

Three alternatives to traditional litigation for resolving construction disputes are mediation, the minitrial, and arbitration.