Chp 5 Flashcards
Scope refers to all the work involved in creating the products of the project and the processes used to create them.
True
Deliverables are only product-related, such as a piece of hardware or software.
False;
can also be process-related
Project scope management includes the processes involved in defining and controlling what is or is not included in a project.
True
The scope management plan can be informal and broad or formal and detailed, based on the needs of the project.
True
The project’s size, complexity, importance, and other factors do not affect how much effort is spent on collecting requirements for scope planning.
False;
they do Affect
Information from the project charter provides a basis for further defining the project scope.
True
Project scope statements must include the project boundaries, constraints, and assumptions.
False;
not a must, just Helpful
The scope of a project is clear and specific from the start.
False;
it becomes more clear and specific with time
Many information technology projects also require detailed functional and design specifications for developing software, which also should be referenced in the detailed scope statement.
True
The project scope statement should reference supporting documents, such as product specifications that will affect what products are produced or purchased, or corporate policies, which might affect how products or services are produced.
True
The project scope statement, stakeholder requirements documentation, and organizational process assets are the primary inputs for creating a WBS.
True
The scope baseline in a WBS consists of the requirements documentation and enterprise environmental factors.
False;
includes approved project scope
The WBS is organized solely around project phases
False;
around project products, project phases, or the project management process groups
A work package represents one component of the product that the project aims to deliver.
False;
a task at the lowest level of the WBS; represents the level of work that the project manager monitors and controls
A work package must always represent less than 80 hours of work.
False;
represent work completed in one month or more
The tasks in a WBS must be developed as a sequential list of steps.
False;
he tasks do not have to be developed as a sequential list of steps
The executing tasks of the WBS remain constant from project to project.
False;
vary the most from project to project
Many organizations provide different guidelines and templates for developing WBSs.
True