CHP 12 Flashcards

1
Q
  1. Overview of capital project appraisal
A

A capital project means any project where there is initial expenditure and then a stream of revenues less running costs.
A capital project does not have to involve the construction of a physical asset.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q
  1. Overview of capital project appraisal steps
A

identify project opportunity
INITIAL APPRAISAL
Detailed appraisal
Investment submission

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q
  1. Initial appraisal
A

Main purpose: ascertain if a proposed capital project is likely to satisfy the criteria of the sponsoring organization.
The criteria will typically be expressed in financial results expected and the risks of this not being achieved.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

In practice there may be additional criteria for initial appraisal

A
  • Achieving synergy or compatibility with other projects
  • Satisfying political constraints
  • Having sufficient upside
  • Using scarce investment funds or management resources in the best way.

These can often not be factored into a financial model, a subjective assessment will be needed.
During the appraisal process it will be necessary to investigate the risks of the project and mitigation of these (taking into account the cost of the mitigation).
The remaining risks will need to be listed for the benefit of the sponsor, lender and investors.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q
  1. Detailed appraisal
A

1st step: define the project and its scope and assess its likely length of operating life.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q
  1. Detailed appraisal

3. 2. Evaluation of cashflows

A

Evaluate the most likely cashflows for capital expenditure, running costs, revenues and termination costs.
Cashflows should allow for any consequential effects on the sponsor’s other activities or costs.
Accurate definition and evaluation of most likely cashflows is critical to success as this constitute the base line. Document all assumptions carefully.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Appraisal techniques

A

After the initial cashflow projection, estimate the financial result of undertaking the project. A discounted cashflow approach is normally used, e.g.
• Net Present Value (NPV)
• Internal Rate of Return (IRR)
• Payback period – time it takes for capital to be recouped from the net revenues without discounting
• Discounted payback period

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

• Internal Rate of Return (IRR)

A

IRR could have multiple solutions – especially if there are negative cashflows. If there is not large start up capital needed, the IRR can be very big but the project could still make a small absolute profit. Thus IRR less popular than NPV.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

• Net Present Value (NPV)

A

NPV result will be satisfactory if it is positive and IRR is above the hurdle rate, the payback period will be good if shorter than the predetermined period.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Appraisal techniques results

A

These calculations will result in an initial appraisal of the project. Broad sensitivities can be done, if unsatisfactory it could indicate the project is not worthwhile or needs redesign. If satisfactory, detailed analysis should start.
Sensitivity analysis – tests sensitivity to a single factor
Scenario testing – varies all assumptions in a mutually consistent manner.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Sensitivity analysis

A

tests sensitivity to a single factor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Scenario testing

A

varies all assumptions in a mutually consistent manner.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q
  1. Choice of risk discount rate
A

Normal practice is to factor inflation into the cashflows and use a nominal risk discount rate.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

4.2. Systemic (or systematic) risk and specific risk

A

This risk cannot be eliminated by investing in similar project many times over. (non-diversifyable risk) These risks can vary from one type of project to the next.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

4.3. Choosing the discount rate for projects with a normal degree of systemic risk

A

Assume the sponsor is a commercial company.
The starting point is the cost of raising incremental capital for the company to carry out projects. This is the rate that needs to be earned on a project to put shareholders in the same position as before.
This could be the company’s normal cost of raising capital, taking this as a weighted average where the weights are based on the optimum capital structure for the company as between equity and debt. If the structure is not currently optimum, it can be made optimum by a separate decision.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

The cost of debt should be taken as the cost in real terms of new borrowing.

A

This is calculated by taking an appropriate margin over the current expected total real return on index-linked bonds, taking into account the company’s credit rating and multiplying by (1-t).

17
Q

Cost of equity

A

Cost of equity is the current expected total real return on index-linked bonds plus a margin for the company’s risk.
This gives a real discount rate to be applied to cashflows expressed in present day monetary values, or adjusted by the assumed future inflation rate and used with cashflows in nominal terms.

18
Q

4.4. Choosing the discount rate for projects with a higher than normal degree of systemic risk

A

Higher risk requires higher discount rate. How to know how much to increase the discount rate:
Look at other companies
Life insurance companies

19
Q

4.4. Choosing the discount rate for projects with a higher than normal degree of systemic risk
Look at other companies

A

What discount rate is used by companies that regularly engage in such projects. In practice, this data may not be available thus an arbitrary number may need to be added.

20
Q

4.4. Choosing the discount rate for projects with a higher than normal degree of systemic risk
Life insurance companies

A

Often projects are financed from the long term insurance fund. (sometimes for with-profits companies, or companies with large free reserves and always for mutual funds)
Here the question is, can the capital be used better elsewhere after allowing for risk? The starting point for the risk discount rate (in nominal terms) might therefore be the expected long-term return on equity-type investments.

21
Q

RDR 4.5. Other factors to consider

A

Companies sometimes use very high hurdle rates when appraising projects.
Using a discount rate that is too high distorts the longer and shorter term cashflows and could lead to wrong decisions as it does not generate a uniform contingency margin.
Too much precision in the risk discount rate is onerous as NPV is not very sensitive to small changes. It is usually appropriate to carry out NPV calc at two rates and if both are satisfactory then there is no need to worry about the appropriate risk discount rate.

22
Q
  1. Risk identification

Steps for effective identification of risks facing a project:

A

• Make a preliminary high-level risk analysis – to make sure that the project could be viable.
• Brainstorm with experts and senior internal people who thinks strategically about the long term.
The aim will be to:
o Identify project risks – both likely and unlikely, upside and downside
o Discuss these risks and their interdependency
o Attempt to put initial evaluation on each risk – frequency of occurrence and probable consequences
o Generate initial mitigation options
• Carry out a desktop analysis to supplement the brainstorming results by identifying further risks and mitigating actions, research similar projects undertaken by the sponsor or others, obtain expert opinions
• Set out risks in a risk register, with cross reference to other risks where there is interdependency.

23
Q
  1. Analysis of risks
A
  • Frequency of occurrence
  • Consequences if risk event occurs
  • Correlations between risks
  • Controllability of the risks
24
Q

6.1. Distribution of NPVs

A

Scenario analysis – construct future scenarios and test effects.
Stochastic modeling - model risks stochastically and get NPV’s for each.

25
Q

7.1. Ways of mitigating risk

A

For each risk, consideration would be given to identifying the main mitigation by:
• Avoid the risk
• Reduce the risk – reduce probability of the risk or the consequences of both.
• Reduce uncertainty
• Transfer risk – e.g. engage with a contractor for a fixed price
• Insure risk
• Sharing the risk with another party.

26
Q

Each mitigation option will be evaluated by assessing:

A
  • Likely effect on frequency, consequence and expected value
  • Feasibility and cost of implementing the option
  • Secondary risks resulting from the option
  • Further mitigating action to respond to secondary risk
  • Overall impact of each option on the distribution of NPVs
27
Q

7.2. The financial consequences of risk mitigation

A

Adopting a particular option will usually reduce downward volatility of the NPV’s and also either increase or decrease the expected NPV. If it increases NPV, the mitigation option is beneficial and should be built into the project.
For the second option, use judgment to decide on whether to include or not.

28
Q
  1. The investment submission
A

The investment submission is the basis on which the decision whether the project should proceed is taken. The assumption is that the best combination of mitigating options will be implemented.

29
Q
  1. The investment submission should include:
A
  • The NPV – allowing for upside and downside risk and contingency margin to cover probabilistic risks that have not been fully analysed.
  • Probability distribution of the NPV’s
30
Q

The residual risks should be fully identified and analysed.

A

Pay particular attention to the submission of remaining risks that could have a catastrophic or serious effect on the outcome of the project (even if it has a low probability).
Specify the method proposed to finance the project and include analysis of the effect of this on investors (tax, price inflation, borrowing etc.).

31
Q

Aim of the investment submission is to discuss the how the project relates to the sponsor’s criteria for judging whether or not to proceed with the project
Consider intangible considerations outside the scope of formal analysis:

A

• Allowance for likely bias or approximations in the estimates
• Hunch
• Knowledge not in the possession of those who prepared the submission
• Last-minute developments
• Doubts about feasibility or quality of implementation
• Overall project credibility
Consider if the upside potential have been estimated realistically.
Judgment after taking all the aspects into account – should the project proceed.