CHOP 6.7 - TAKE-OVER PROCEDURES, COMMISSIONING, AND POST-OCCUPANCY EVALUATION Flashcards
Certificate
A document attesting to the truth of a fact; in construction. A certificate is prepared by a professional, either an architect or an engineer.
Certificate of Substantial Performance
A certificate issued under the appropriate lien legislation attesting that the contract between the owner and the contractor is substantially complete.
Guaranty
A three-party agreement in which the third party (such as a surety) guarantees the performance of an obligation to the second party (such as an owner) in the event of default of the first party (such as a contractor)( CCDC).
Holdback
A percentage of the monetary amount payable under a (construction) contract, which is held as security for a certain period. The percentage and period are based on the provincial lien legislation.
Lien
A legal claim on real property to satisfy a debt owed to the lien claimant by the property owner. This claim can carry the right to sell the property upon default.
Maintenance
The act of keeping a building system, process or property in proper and efficient working condition.
Post-occupancy Evaluation
An assessment of the performance of a building after the building has been occupied. The evaluation may address one or more different aspects of building performance.
Ready-for-Takeover
A term adopted by the Canadian Construction Document Committee (CCDC), used to describe a set of contractual and regulatory requirements that must be satisfied prior to achieving a financial milestone for the release of the project close-out payment(s).
Warranty
A two-party agreement which provides an assurance by a builder or a seller of goods (such as a contractor) to a purchaser (such as an owner) that the warrantor will assume stipulated responsibilities for correction of defects in the goods within a stated period of time (CCDC).
Introduction to “Take-over Procedures, Commissioning, and Post-occupancy Evaluation”
In a project, even though the architect may have provided great design and contract administration services, poor takeover and commissioning services may be all a client remembers about the project, leaving the architect with an overall poor review.
Takeover procedures are a normal part of the architect’s basic services that close the contract administration phase. The takeover deliverables should be clearly specified in the general requirements section of specifications listing the owner’s requirements for record documents, demonstration and training, and operations and maintenance documentation.
After takeover, the architect is responsible for reviewing defects and deficiencies during the warranty period and for notifying the contractor of items to be corrected.
Commissioning may commence at the beginning of a project and may continue until occupancy by the owner. Takeover, by contrast, starts when a project nears construction completion.
With the increasing integration of green building rating systems into projects, post-occupancy evaluation may be a requirement of certifications systems.
Take Over Procedures
Ready for Takeover and Substantial Performance:
Ready-for-takeover may vary from contract to contract; however, CCDC has established a list of factors that constitute the ready-for-takeover state. From CCDC 2 2020,
12.1.1 The prerequisites to attaining Ready-for-Takeover of the Work are limited to the following:
1) The Consultant has certified or verified the Substantial Performance of the Work.
2)Evidence of compliance with the requirements for occupancy or occupancy permit as prescribed by the authorities having jurisdiction.
3) Final cleaning and waste removal at the time of applying for Ready-for-Takeover, as required by the Contract Documents.
4) The delivery to the Owner of such operations and maintenance documents reasonably necessary for immediate operation and maintenance, as required by the Contract Documents.
5) Make available a copy of the as-built drawings completed to date on site.
6) Startup, testing required for immediate occupancy, as required by the Contract Documents.
7) Ability to secure access to the Work has been provided to the Owner, if required by the Contract Documents.
8) Demonstration and training, as required by the Contract Documents, is scheduled by the Contractor acting reasonably.
Generally, for projects that involve new buildings or renovation of unoccupied space, a project is deemed substantially complete when both the following criteria are met:
1) The building is ready for its intended use and, if applicable, an occupancy permit is issued.
2) The balance of payment to the contractor is at a level below the threshold indicating that the work has been substantially performed as stated in provincial and territorial construction lien legislation.
For the purposes of release of a statutory holdback, it is possible to waive the requirements associated with the certificate of substantial performance and to proceed directly to a statement of deemed total completion (as defined in the lien legislation). In this case, the warranty period commences on the date of total completion. This is often used on small projects when the time between substantial performance and total completion is short.
Final Certificate for Payment
Once the architect is satisfied that all deficiencies have been corrected and that all work under the contract has been completed, the contractor can apply for payment for the outstanding amount. The final completion or correction of deficiencies can be frustrating for the architect for the following reasons:
1) progress towards final completion of outstanding deficiencies seems to be very slow.
2) the architect’s authority to certify payments and thus influence the contractor to work expeditiously decreases once the major part of the payment has been released.
3) many contractors tend to lose interest in the project when there is no longer a significant financial incentive.
If the contractor is efficient in correcting all the deficiencies, the date of this certificate may precede the date for release of final holdback.
Certification for Release of Holdback
The architect prepares a certificate authorizing payment of the amount of holdback which has accrued to the date of substantial performance. The certificate should be dated for payment one day after the termination of the lien claim period. When issuing the release of the holdback certificate, the architect should advise the owner to obtain legal counsel to ensure that no liens have been registered or notices of liens have been received.
The holdback monies are a trust fund. This fund cannot be used to enforce the performance of the contractor nor to ensure that deficiencies are corrected. Certification of payment for known deficiencies should never be made until the performance of the work is acceptable.
Letters of Assurance
In some jurisdictions, authorities having jurisdiction require a letter of assurance, letter of undertaking or commitment certificate from the architect or registered professional that a building has been constructed in general compliance with the building code, applicable regulations, and the construction documents accepted for building permit purposes.
Final Submissions
Prior to occupancy of the building by the owner, the contractor must satisfy the conditions of ready-for-takeover and forward required documentation to the architect for review. This may include:
1) operations instructions and maintenance manuals.
2) a complete set of keys
3) record documents, which may include shop drawings in the appropriate format as specified in the contract documents.
4) maintenance materials and spare parts.
5) copies of warranties and bonds for each system along with dates for warranty periods.
6) certification of the operation of various systems.
It is important for the architect and the engineers to scrutinize these items carefully because they may be inaccurate or incomplete on first submission and require re-submission before they are acceptable.
The final submission may be in two stages:
1) Those items required for the proper operation of the premises for occupancy and, therefore, for certification of substantial performance.
2) Those items necessary to complete the contract.
Ultimately, all actions and submission of ready-for-takeover must be satisfied by the contractor.
It is also at this point of a project when the architect benefits from assembling a file for their own future reference