CHOP 4.2 - CONSTRUCTION PROJECT COST PLANNING AND CONTROL Flashcards
Construction Budget
The maximum amount of money, including contingency allowances, which the client is prepared to spend on the construction cost.
Construction Cost
The total cost of the work to the client to construct all elements of the project designed or specified by, or on behalf of, or as a result of coordination by, the architect, consisting of the construction contract price, cost of changes to the work during construction, construction management fees or other fees for the coordination and procurement of construction services, and all applicable taxes, except value-added taxes, which shall be excluded. Construction cost excludes the compensation of the architect and consultants, land cost, land development charges and other professional fees.
Construction Cost Estimate
The anticipated total construction cost at the anticipated time of construction, including contingency allowances, as determined or agreed to by the architect from time to time, the accuracy of which corresponds to the available level of detail of design development and the construction documents, and the extent of construction completed.
Construction Contingency
A reserve included in the construction cost estimate established to provide funds for the implementation of risk management strategies should risk events occur, including such events as the evolution of the design prior to construction, price escalation between the time of cost estimate preparation and construction, unknown conditions, and/or function and design changes made during construction.
Element
Term used in cost estimating to describe a component of a building, such as a sub-structure (footings, foundations) or envelope (walls and roof).
Indexing
Applying an index or factor to adjust costs from one geographic region to another (a typical index might be expressed as a percentage, such as 102.7%
Program
Group of related projects and operations that are managed in a coordinated way to obtain the benefit that could not be achieved if managed separately.
Project
An endeavour undertaken within a defined period of time that produces a unique outcome.
Project Budget
The client’s estimated total expenditure for the entire project. It includes, but is not limited to, the construction budget, professional fees, costs of land, rights of way and all other costs to the client for the project.
Project Risk
The sum of uncertainties associated with a project undertaking.
Quantity Survey
A bill of quantities or a detailed listing and quantities of all items of material and equipment necessary to construct a project.
Providing Advice on Costs
In most client-architect agreements, one responsibility of the architect is to prepare an estimate of the probable construction cost. This estimate is neither a quotation nor a guarantee. Due to the variable market conditions, the architect should never guarantee or warrant a construction cost estimate. Such a warranty may void portions of an architect’s professional liability insurance policy.
Cost Planning and Control by Project Stage
COST PLANNING:
1) Cost Limit established ( Requirements and Pre-Design)
2) First Cost Plan (Schematics)
COST CONTROL:
3) “Many” Cost checks (Design Development)
4) Finale Estimate and Cost Check (Contract Documents - Drawings and Specifications)
5) Cost Analysis (Bid / Contract Award) (Construction) (Take-Over) (Post Construction)
Liability of the Architect
The typical client-architect agreement will include a general condition that stipulates the terms under which an architect will be responsible for redesign at no cost to the client should the lowest tendered bid exceed the construction cost estimate by a predefined amount, often 10% to 15%.
Format of Cost Estimates
There are two widely accepted formats in which construction cost information is presented: Uniformat II and MasterFormat 2016, both developed by Construction Specifications Canada and the Construction Specifications Institute. These two formats relate through cross-referencing tables.
Methods of Cost Estimation
There are several methods for estimating construction costs:
1) analogous (or top-down);
2) parametric;
3) bottom-up.
Analogous Cost Estimating
An analogous cost estimate is performed when little, if any, information is available about the project at hand. It is very inexpensive and quick but its accuracy is highly questionable.
Parametric Cost Estimating
Parametric estimating applies a measurement of a building, system, or component against a known cost per unit. For example:
- size of the building in metres X $/sq. m.;
- area of flooring X $/sq. m.;
- length of steel lintels X $/m.;
- number of light fixtures X $/supply and install of fixture.
Bottom-up Cost Estimating
The bottom-up estimate is the result of analyzing the work in detail, including estimates of the effort hours, labour rates, materials, logistics and overhead. The bottom-up estimate is the most accurate but requires extensive effort from all parties in the construction endeavour.