Chapter 9: Frustration Flashcards
What is the case that laid down the definition of Frustration?
Definition (taken from Davis Contractors Ltd v Fareham UDC)
- Where an unforeseen event occurs
- Occurred after the contract had been formed
- It was not the fault of any party
- Which makes the performance of contract illegal, impossible or renders the performance as fundamentally/radically/significantly different from what was initially intended at the time the contract was entered into
What is the term of the outcome of succesful frustration?
Contract would be discharged/comes to an end automatically
- Regardless of the parties’ wishes (Hirji Mulji v Cheong Yue SS. Co. (1926))
Note
- Use the words ‘comes to an end by operation of law’
- Do NOT use ‘void’
What are the 3 attitudes of the courts when dealing with frustration cases?
What are the cases that laid down the approach for each ?
timeline of events
Strict approach (before)
- Paradine v Jane (1647)
- Absolute obligation theory
Relaxed approach (after Paradine)
- Taylor v Caldwell (1863)
- Implied term theory
Today
- Davis Contractors Ltd v Fareham UDC (1956)
- Unforeseen event was fundamentally radical to the contract that was entered
Paradine v Jane (1647)
Strict approach (before)
Theory
- Absolute obligation theory
Held
- Decision was based strictly on ‘freedom to contract’ (laissez faire)
- On grounds that they should have foreseen/included such possible events in the contract to begin with
- Only then it would become illegal or impossible to perform
Problem
- However, the whole point about frustration is that it’s a freak accident/event (how would they know?)
Taylor v Caldwell (1863)
Relaxed approach (after Paradine)
Theory
- Implied term theory
Facts
- Destruction of a music hall brought the contract to an end and discharged both parties
Held
- There was an ‘implied condition’ that the SM has to exist for the contract to be performed
- On grounds that, they can’t hold parties to account for something they do not have control over
Davis Contractors Ltd v Fareham UDC (1956)
Can a contract be frsutrated if the obligations were more difficult/expensive - case?
IMPORTANT
appraoch today
Theory
- Unforeseen event was fundamentally radical to the contract that was entered
Facts
- Contractor agreed to build 78 houses within 8 months for £94,000
- Turns out they did not have enough workers and materials to complete it within the time given
- The houses ended up being complete after 22 months, and costed £115,000
- Contractors argued that there was frustration, to avoid needing to pay compensation
Held - Lord Reid & Viscount Radcliffe
- Could not plead frustration
- On grounds that they should include such possibilities in the terms of the contract
- In situations where the contract has been entered, and unforeseen changes in circumstances (not due to fault of parties).
The contract is to be said as impossible, illegal or radically different from what the parties have originally intended. Justice requires that courts should treat the contract as coming to an end - The contract would only be frustrated where there is a complete change between what was undertaken in the contract circumstances which were called upon to be performed (National Carriers Ltd v Panalpina (Northern) Ltd (1981))
Note
- It is not good enough if the obligations are just more difficult/onerous/expensive (Tsakiroglou & Co v Noblee and Thorl (1962))
- Must be freak accident (something radically different) which can’t be controlled by either party
What is the ‘Test of multi-factorial approach’? What case was this laid down in?
What are the preconditions to this test. And what are the 5 conditions/factors to consider?
Used in Edwinton v Tsavliris (The Sea Angel) (2007)
Precondition
- Must be a break in identity between what was contemplated and the new performance
- Courts will not easily conclude that such break has occurred
5 conditions/factors courts take into account
- Terms of the contract itself
- Matrix/context
- Parties’ knowledge, expectation, assumptions and contemplations, in particular as to risk, as to time of the contract, at any rate so far as these can be ascribed mutually and objectively
- Nature of the surprising event
- Parties’ reasonable and objectively ascertainable calculations as to the possibilities of future performance in the new circumstances
What is there to note about the ‘Test of multi-factorial approach’
This test gave a degree of flexibility to the law for the courts to take into account to decide if a contract has been frustrated
- Although frustration is still very strict/limited
Test may be arbitrary but pragmatic (practical) - MSC Mediterranean Shipping Company SA v Cottonex Anstalt (2016)
What are the 2 reasons the doctrine of frustration is so narrow/strict?
Introduction
- On the basis that courts do not like to entertain/protect parties that entered into a bad bargain
2 reasons courts don’t like to protect parties
1. Bad bargains
2. Express provisions in the contract (clauses)
What is the case for parties entering into a bad bargain
Davis Contractors Ltd v Fareham UDC (1956)
Davis Contractors Ltd v Fareham UDC (1956)
Bad bargain
Context
- A clear example of a bad bargain
Held
- Claimant could not rely on frustration
Takeaway
- Courts did not want to protect the claimant
- A clear rule that the courts will not lend their assistance to a party that is looking for a way out of a bad bargain
Why are courts less inclined to allow frustration to parites where there are express provisions in the contract (clauses)
What are the 3 kinds of expressed clauses in a contract?
Introduction
- Parties are expected to foresee such possibilities when entering into contract and guard against them with the contracts
- E.g. parties can make provisions in the contract for what’s to happen when performance becomes impossible/radically different due to freak events
Very important in commercial contracts - where provisions clause are stated in the contract -
- ‘Force majeure’
- Hardship clauses
- Intervener clauses
What is a ‘Force majeure’ clause?
What is the case for this?
Express provisions in the contract
Introduction
- Clause that covers the actions of when such situations could possibly occur
- Then the courts will give it effect
Case
- Channel Island Ferries Ltd v Sealink UK Ltd [1988]
Channel Island Ferries Ltd v Sealink UK Ltd [1988]
‘Force majeure’
Held
* A party won’t be liable in the event of non-fulfilment of any obligation arising under this contract by reason of Act of God or any nature beyond the control of the relevant party
What are hardship clauses?
Express provisions in the contract
Introduction
- Clauses which generally define what constitutes ‘hardship’ (usually economic). And will state the procedure adopted by the parties in such hardship occurring
- Clause will propose obligations for procedure of renegotiation to alleviate the hardships arisen
Example
- Predictable events (e.g. possible labour deficit, not enough funds, etc.) which when occurred to renegotiate terms
What are intervener clauses?
Express provisions in the contract
Introduction
- Similar to hardship clause, but gives authority to a third party to adjust/dispute the terms
- Clause saying, in the event the situation happens, they will appoint an independent arbitrator (intervener)
Intervener
- Employed as a sanction to negotiate their way out of a hardship event
Example
- An independent expert to negotiate terms that the parties may not been knowledgeable to
What are the 4 advantages of such Express provisions in the contract
- Helps prepare for future events
- Provides a greater degree of certainty
- It is much wider than frustration as the parties can stipulate wider range categories of events
- Parties can stipulate what happens after the event
What are the 5 situations/scenarios for frustration?
- Impossibility of the performance of the contract
- Frustration of purpose
- Illegality (effects of war)
- Government action
- Other frustrating events
What are the 3 scenarios for Impossibility of the performance of the contract?
What are the cases for each?
1) Destruction of subject matter
- Taylor v Caldwell (1863)
- Asfar v Blundell (1896)
2) Personal incapacity
- Contract to be carried by a certain individual - Condor v Barron Knights (1966)
3) Performance only temporarily impaired - contract still can be frustrated
- Jackson v Union Marine Insurance Co
Taylor v Caldwell (1863)
Destruction of subject matter
Facts
- License to use the “Surrey Gardens and Music Hall” for a series of concerts
- Music hall burnt down, and was impossible to stage the concert
- C argued that Ds were in breach of contract in failing to supply the hall
- Sued for wasted advertising expenditure
Held
- Frustrated - discharged
- Destruction of the hall rendered the performance of the contract impossible
What is there to note about Asfar v Blundell (1896) ?
Destruction of subject matter
Full destruction may not be necessary
Jackson v Union Marine Insurance Co
Performance only temporarily impaired - contract still can be frustrated
Facts
- Ship was supposed to sail from Liverpool to Newport, to offload cargo in San Francisco
- Ship had suffered some structural damages at the coast of Newport
- It was not fully repaired for several months
- Charterer then used another ship to carry cargo, on the basis that the contract had been frustrated
- Ship owner sued for breach of contract. That the charter contained a clause stating ‘damages and accidents of navigation excepted’.
Held
- Contract had been frustrated
- As it was not available for the voyage for which it was chartered
- On the basis that performance was radically different from that originally contemplated/agreed to
- The clause could not have been able to intend to apply in reaction to the delay of length occurred (it was an unforeseen possibility)
Takeaway
- Though there was a clause stating about damages and accidents, they could not have possibly foreseen that such delay was possible
What is Frustration of purpose (non-occurrence of an event)?
What are the 3 cases?
IMPORTANT
situations of frustation
Introduction
- Where common purposes which the contract was entered into can no longer be carried out, due to an unforeseen event
Case
- Krell v Henry (1903)
- Chandler v Webster (1904)
- Herne Bay Steam Boat Co. Hutton (1904)
Krell v Henry (1903)
Frustration of purpose
Facts
- Room hired for 2 days in Pall Mall to view the coronation (become king) procession of King Edward VII
- This purpose was not expressed in the contract
- After contract concluded, coronation process was postponed - due to king’s illness
Held
- Frustrated