Chapter 7 Vocab Flashcards

1
Q

actual costs

A

The amount of funds the project has spent to date. The difference between actual costs and the earned value will reveal the cost variance.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

analogous estimating

A

This relies on historical information to predict estimates for current projects. Analogous estimating is also known as top-down estimating and is a form of expert judgment.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

bottom-up estimating

A

A technique where an estimate for each component in the WBS is developed and then totaled for an overall project budget. This is the longest method to complete, but it provides the most accurate estimate.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

budget at completion

A

The predicted budget for the project; what the project should cost when it is completed. Budget at completion represents 100 percent of the planned value for the project’s completion.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

chart of accounts

A

A coding system used by the performing organization’s account- ing system to account for the project work.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

cost baseline

A

This shows what the project is expected to spend. It’s usually shown in an S-curve and allows the project manager and management to predict when the project will be spending monies and over what duration. The purpose of the cost base- line is to measure and predict project performance.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

cost budgeting

A

A process of assigning a cost to an individual work package. This process shows costs over time. The cost budget results in an S-curve that becomes the cost baseline for the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

cost change control

A

This is part of the integrated change control system and documents the procedures to request, approve, and incorporate changes to project costs.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

cost control

A

An active process to control causes of cost change, to document cost changes, and to monitor cost fluctuations within the project. When changes occur, the cost baseline must be updated.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

cost estimating

A

The process of calculating the costs, by category, of the identified resources to complete the project work.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

cost management plan

A

A subsidiary plan of the overall project management plan that defines how costs will be estimated, budgeted, and controlled.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

cost performance index

A

The process of calculating the costs, by category, of the identified resources to complete the project work.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

cost variance

A

The difference between the earned value and the actual costs.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

direct costs

A

These costs are attributed directly to the project and cannot be shared
with operations or other projects.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

earned value

A

The value of the work that has been completed and the budget for that work: EV = % Complete × BAC.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

earned value management

A

Earned value management integrates scope, sched- ule, and cost to give an objective, scalable, point-in-time assessment of the project. EVM calculates the performance of the project and compares current performance against plan. EVM can also be a harbinger of things to come. Results early in the project can predict the likelihood of the project’s success or failure.

17
Q

estimate at completion

A

A hypothesis of what the total cost of the project will be. Before the project begins, the project manager completes an estimate for the project deliverables based on the WBS. As the project progresses, there will likely be some variances between what the cost estimate was and what the actual cost is. The EAC is calculated to predict what the new estimate at completion will be.

18
Q

estimate to complete

A

Represents how much more money is needed to complete the project work: ETC = EAC – AC.

19
Q

estimating publications

A

Typically, a commercial reference to help the project estimator confirm and predict the accuracy of estimates. If a project manager elects to use one of these commercial databases, the estimate should include a pointer to this document for future reference and verification.

20
Q

fixed costs

A

Costs that remain the same throughout the project.

21
Q

indirect costs

A

These costs can be shared across multiple projects that use the same
resources—such as for a training room or piece of equipment.

22
Q

parametric modeling

A

A mathematical model based on known parameters to predict the cost of a project. The parameters in the model can vary based on the type of work being done. A parameter can be cost per cubic yard, cost per unit, and so on.

23
Q

planned value

A

The worth of the work that should be completed by a specific time in the project schedule.

24
Q

risk

A

An uncertain event that can have a positive or negative influence on the project’s success. It can affect the project costs, project schedule, and often both. All risks and their status should be recorded in the risk register.

25
Q

schedule performance index

A

This reveals the efficiency of work. The closer the quotient is to 1, the better: SPI = EV / PV

26
Q

schedule variance

A

The difference between the planned work and the earned work.

27
Q

to-complete performance index

A

An earned value management formula that can forecast the likelihood of a project to achieve its goals based on what’s currently happening in the project.

28
Q

top-down estimating

A

A technique that bases the current project’s estimate on the total of a similar project. A percentage of the similar project’s total cost may be added to or subtracted from the total, depending on the size of the current project.

29
Q

variable costs

A

Costs that vary, depending on the conditions within the project.

30
Q

variance

A

The time or cost difference between what was planned and what was actually experienced.