Chapter 6 Vocab Flashcards
activity list
A listing of all of the project activities required to complete each project phase or the entire project.
activity on node
A network diagramming approach that places the activities on a node in the project network diagram.
activity sequencing
The process of mapping the project activities in the order in which the work should be completed.
analogous estimating
A duration-estimating technique that bases the current project duration estimate on historical information from similar projects.
crashing
A duration-compression technique that adds project resources to the project in an effort to reduce the amount of time allotted for effort-driven activities.
critical chain method
A network diagramming approach that considers the avail- ability of project resources and the project’s promised end date to determine the critical path(s) in the project.
critical path method
A network diagramming approach that identifies the project activities that cannot be delayed or the project completion date will be late.
discretionary dependencies
The order of the project activities do not have to be completed in a particular order. These tasks can be completed in the order of the project manager or at the project team’s discretion.
fast-tracking
A duration-compression technique that allows entire phases of a project to overlap other phases.
finish-to-finish
A relationship between project activities where the predecessor activities must finish before successor activities may finish.
finish-to-start
A relationship between project activities where the predecessor activities must finish before the successor activities may start; this is the most common network diagramming relationship type.
float
A generic term to describe the amount of time an activity may be delayed with- out delaying any successor activities’ start dates.
FNET
A project constraint that requires an activity to finish no earlier than a spe- cific date.
fragnet
A portion of the project that is usually contracted to a vendor to complete, yet the project work is still represented in the project network diagram.
hard logic
The project activities must be completed in a particular order; this is also known as mandatory dependencies.