Chapter 6 Vocab Flashcards

1
Q

activity list

A

A listing of all of the project activities required to complete each project phase or the entire project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

activity on node

A

A network diagramming approach that places the activities on a node in the project network diagram.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

activity sequencing

A

The process of mapping the project activities in the order in which the work should be completed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

analogous estimating

A

A duration-estimating technique that bases the current project duration estimate on historical information from similar projects.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

crashing

A

A duration-compression technique that adds project resources to the project in an effort to reduce the amount of time allotted for effort-driven activities.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

critical chain method

A

A network diagramming approach that considers the avail- ability of project resources and the project’s promised end date to determine the critical path(s) in the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

critical path method

A

A network diagramming approach that identifies the project activities that cannot be delayed or the project completion date will be late.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

discretionary dependencies

A

The order of the project activities do not have to be completed in a particular order. These tasks can be completed in the order of the project manager or at the project team’s discretion.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

fast-tracking

A

A duration-compression technique that allows entire phases of a project to overlap other phases.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

finish-to-finish

A

A relationship between project activities where the predecessor activities must finish before successor activities may finish.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

finish-to-start

A

A relationship between project activities where the predecessor activities must finish before the successor activities may start; this is the most common network diagramming relationship type.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

float

A

A generic term to describe the amount of time an activity may be delayed with- out delaying any successor activities’ start dates.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

FNET

A

A project constraint that requires an activity to finish no earlier than a spe- cific date.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

fragnet

A

A portion of the project that is usually contracted to a vendor to complete, yet the project work is still represented in the project network diagram.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

hard logic

A

The project activities must be completed in a particular order; this is also known as mandatory dependencies.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

lag

A

Time added to a project activity to delay its start time; lag time is considered posi- tive time, and it is sometimes called waiting time.

17
Q

lead

A

ime added to an activity to allow its start time to begin earlier than scheduled; lead time is negative time, as it moves the activities closer to the project’s start date.

18
Q

mandatory dependencies

A

Project activities must happen in a particular order due to the nature of the work; also known as hard logic.

19
Q

Monte Carlo analysis

A

A what-if scenario tool to determine how scenarios may work out, given any number of variables. The process doesn’t actually create a specific answer, but a range of possible answers. When Monte Carlo is applied to a schedule, it can present, for example, the optimistic completion date, the pessimistic completion date, and the most likely completion date for each activity in the project.

20
Q

network template

A

A network diagram based on previous similar projects that is adapted for the current project work.

21
Q

parametric estimating

A

Ideal for projects with repetitive work where a parameter, such as five hours per unit, is used to estimate the project duration.

22
Q

Parkinson’s Law

A

Work expands to fill the amount of time allotted to it.

23
Q

precedence diagramming method

A

The most common method of arranging the project work visually. The PDM puts the activities in boxes, called nodes, and connects the boxes with arrows. The arrows represent the relationship and the dependencies of the work packages.

24
Q

project calendar

A

A calendar that defines the working times for the project. For example, a project may require the project team to work nights and weekends so as not to disturb the ongoing operations of the organization during working hours. In addition, the project calendar accounts for holidays, working hours, and work shifts the project will cover.

25
Q

resource calendar

A

The resource calendar shows when resources, such as project team members, consultants, and SMEs, are available to work on the project. It takes into account vacations, other commitments within the organization, restrictions on contracted work, overtime issues, and so on.

26
Q

resource-leveling heuristics

A

method to flatten the schedule when resources are overallocated or allocated unevenly. Resource leveling can be applied in different methods to accomplish different goals. One of the most common methods is to ensure that workers are not overextended on activities.

27
Q

schedule control

A

Part of integrated change management, schedule control is con- cerned with three processes: the project manager confirms that any schedule changes are agreed upon; the project manager examines the work results and conditions to know if the schedule has changed; and the project manager manages the actual change in the schedule.

28
Q

schedule management plan

A

A subsidiary plan of the overall project plan. It is used to control changes to the schedule. A formal schedule management plan has procedures that control how changes to the project plan can be proposed, accounted for, and then implemented.

29
Q

schedule variance

A

The difference between the planned work and the completed work.

30
Q

SNET

A

A project constraint that demands that a project activity start no earlier than a specific date.

31
Q

soft logic

A

The preferred order of activities. Project managers should use these rela- tionships at their “discretion” and document the logic behind making soft logic deci- sions. Discretionary dependencies allow activities to happen in a preferred order because of best practices, conditions unique to the project work, or external events; also known as discretionary dependencies.

32
Q

start-to-finish

A

A relationship that requires an activity to start so that a successor activity may finish; it is unusual and is rarely used.

33
Q

start-to-start

A

A relationship structure that requires a task to start before a successor task activity may start. This relationship allows both activities to happen in tandem.

34
Q

three-point estimate

A

An estimate that uses optimistic, most likely, and pessimis- tic values to determine the cost or duration of a project component.