CHAPTER 7: MANAGING PROJECT COSTS Flashcards

1
Q

ACTUAL COST (AC)

A

Actual amount of money spent to date

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Analogous Estimating

A

Based on historical information cost of project is predicted. Least reliable, top down estimating.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

BUTTOM UP ESTIMATING

A
  • Starts from Zero
  • accounts for each component of the WBS and sums them up
  • most time consuming and reliable
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

BUDGET ESTIMATE

A
  • broad, often top down
  • -10 to +25 percent range
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

COMMERCIAL DATABASE

A
  • uses a data base to estimate cost
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

CONTINGENCY RESERVE

A
  • allowance to account for overruns in costs
  • used at pms discretion and with management’s approval to counteract overruns
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

COST AGGREGATION

A
  • Cost parallel to WBS WP
  • Each WBS WP is aggregated to their control acc
  • each controll acc is aggregated to the sum of project costs
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Cost Baseline

A
  • time lapse of when money is to be spend in relation to cumulative value of the work completed in the project
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

COST BUDGETING

A
  • applies cost estimates over time
  • cost aggregation assigning dollar amounts for each scheduled activity or each WP in the WBS
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

COST CHANGE CONTROL SYSTEM

A
  • system examines any changes associated with scope change, cost of materials or other resources
  • impact on overall project costs
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

COST MANAGEMENT PLAN

A
  • plan that dictates how cost variances will be managed
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

COST OF POOR QUALITY

A
  • Cost of non conformance to quality
  • e.g. rework, defect repair, loss of life
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

COST OF QUALITY

A
  • money spend to attain expected level of quality
  • e.g. training, testing, safety precautions
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

COST PERFORMANCE INDEX (CPI)

A
  • Measures financial performance
  • CPI = EV/AC
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

COST VARIANCE (CV)

A

CV = EV - AC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

DEFINITIVE ESTIMATE

A
  • accurate, late in planning phase
  • buttom up
  • based on WBS
  • Variance -5 +10 percent
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Direct costs

A
  • costs attributed directly to project work
  • not shared with other projects
  • e.g. hotels, phone calls etc
18
Q

EARNED VALUE

A
  • physical work done and authorized budget for it
  • percent if BAC that represents actual work completed
19
Q

ESTIMATE AT COMPLETION (EAC)

A
  • forecasting formulas to predict the costs of the project at the time of completion
20
Q

ESTIMATE TO COMPLETE

A
  • predicts how much funding the project will require to be completed
  • 3 variations of formula based on project conditions
21
Q

FIXED COSTS

A
  • remain constant throughout the life of the project
  • e.g rental fee, consultant fee etc
22
Q

FUNDING LIMIT RECONCILIATION

A
  • approach of managing cash flow against project deliverables based on schedule, milestone accomplishment or data constrains
23
Q

INDIRECT COSTS

A
  • costs representative for more than one project
  • PM software license, utilities for company etc
24
Q

KNOWN UNKOWNS

A
  • Event that will likely happen
  • but when and to what degree is unknown
25
Q

LEARNING CURVE

A
  • assumption that the cost per unit decreases the more units are produced
26
Q

OLIGOPOLY

A
  • tight market
  • action of one vendor affects action of others
27
Q

OPPORTUNITY COST

A
  • cost of opportunity that is refused to realize an opposing opportunity
28
Q

PARAMETRIC ESTIMATING

A
  • using parametric model to extrapolate costs needed for a project
  • e.g. cost per hour, cost per unit
29
Q

PLANNED VALUE (PV)

A
  • work scheduled and budget authorized to accomplish that work
  • percentage of BAC reflecting where project should be at a given point of time
30
Q

PROJECT VARIANCE

A
  • discovered at project completion
  • VAR = BAC - AC
31
Q

REGRESSION ANALYSIS

A
  • statistical approach predicting future values
  • based on historical values
32
Q

RESERVE ANALYSIS

A
  • included in budget but not as cost baseline
  • revmserve for unknown unkowns
33
Q

ROUGH ORDER MAGNITUDE

A
  • rough estimate used during initiating processes and top down estimates
  • -25 to +75 percent of range
34
Q

SCHEDULE PERFORMANCE INDEX (SPI)

A
  • SPI = EV/PV
35
Q

SCHEDULE VARIANCE

A

Difference between earned and planned value
- SV = EV - PV

36
Q

SINGLE SOURCE

A
  • many vendors existing
  • prefer to work with selected vendor
37
Q

Sole source

A
  • only one vendor existing for what I need
  • e.g. ASML
38
Q

Sunk costs

A
  • money already invested into project
39
Q

TO COMPLETE PERFORMANCE INDEX (TCPI)

A
  • formula to forecast likely hood of project achieving its goals based on what is happening
  • meet BAC? TCPI = (BAC - EV)/(BAC-AC)
  • Meet newly created estimate? TCPI = (BAC-EV)/(EAC-AC)
40
Q

VARIABLE COSTS

A
  • costs that change based on conditions applied in the project
41
Q

VARIANCE

A
  • difference between what was expected and what was experienced
42
Q

VARIANCE AT COMPLETION (VAC)

A
  • predict variance project will likely have based on current condition
  • VAC = BAC - EAC