Chapter 7 - Investment decisions Flashcards

1
Q

Name a fallacy/drawback/difficulty/weakness of the NPV method for choosing investments

A

The major point is that the cost of capital can be difficult to get 100% correct.

Luckily, we might not have to get it 100% correct. More on that later

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

how do we mitigate the weakness of the NPV method?

A

First of all, the NPV method weakness is that the cost of capital can be uncertain.

If we create a so-called NPV profile, which is a graph that shows the relationship between interest rate (cost of capital) and NPV (NPV on Y-axis, rate on X-axis), then we can easily see where the IRR lies in terms of an interest rate/cost of capital. We can use this value as a limit. As long as our cost of capital is better (lower) than the IRR, then the NPV is good, and we should choose the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

When considering stand-alone projects, what can happen if we do not use the appropriate investment decision method?

A

if we use the NPV, we are good.

If we use some other method, they may give a result different from NPV. If so, it would mean that we are either accepting a negative NPV project OR rejecting a positive NPV project. Either case is bad for the current value of the firm.

As long as we are considering only stand-alone projects, NPV method is generally the correct one.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is the difference between the cost of capital and IRR?

A

The difference between cost of capital and IRR represent the maximum error in the estimate of cost of capital that is allowed without altering the final decision.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

when will the IRR decision reule work+

A

The IRR decision rule is guaranteed to work if all of the negative cash flows precede the positive cash flows.

if this is not the case, the IRR decision rule may give correct or wrong results.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is actually the IRR decision rule?

A

Stand alone project.

Take any project where the IRR is higher than the opportunity cost of capital. Turn down all others.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

name a pitfall of the IRR decision rule that is different from “negative cashflows must precede positive cash flows”

A

There can be multiple IRRs. Then which should one take? No easy solution here.

We can also have cases with no IRRs. These are the ones where the NPV is positive for all rates.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

elaborate on the payback rule

A

The payback rule states that you should first find the payback period, which is the time it takes to pay back the original investment. then we check this time against some pre-specified requirement to decide on whether we should accept or reject.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Why does the payback rule suck?

A

1) It ignores cost of capital and the time value of money

2) Ignores cash flows after the payback period

3) Relies on ad-hoc decision criterion.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Can we use IRR method to compare projects that are mutex?

A

NO.

Always use NPV.

The reason is that the IRR is completely arbitrary in terms of scale of cash flows, timing etc.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Elaborate on incremental IRR

A

Incremental IRR refers to the IRR of the incremental cash flow that would result from replacing one project with another project.

We take one project cashflow, and subtracts the other. This is the same as saying “we had the project we subtract, and change to the project we subtract from”.

The IRR of the resulting cash flow is the incremental IRR.

This IRR represent the crossover point where one project becomes better than the other. But it does not necessarily tell us whether the best option is NPV positive.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Can we compare IRRs?

A

No, since projects have different scales.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

key takeaway of this chapter?

A

Use the NPV rule for decisions, IRR for boundaries.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is the profitability index?

A

bang for your buck measure whenever the projects take some resource constraint.

PI = NPV (amounts of resources required)

The profitability index requires 2 conditions in order to be completely accurate:

1) The set of projects taken under the guidance of the method must completely exhaust the resource

2) There is only a single relevant resource

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q
A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly