Chapter 7 - Cost Management Flashcards

1
Q

Life cycle costing

A

Looking at the cost of the whole life of the product, not just the cost of the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Value analysis

A

Finding ways to provide required features at the lowest overall cost without loss of performance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Plan Cost Management process

A

Identifying how you’re going to plan, manage, and monitor and controll project costs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Why are NPV, ROI, payback period, and IRR used in cost management?

A

Used to evaluate whether the project is still feasible within the charter and whether the measurable project objectives can be achieved

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Discounted cash flow

A
  • Used in project selection to estimate the attractiveness of an investment by predicting how much money will be received in the future, and then discounting it to its current value
  • Used to evaluate the potential revenue to be earned from specific project work
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is the output of the Plan Cost Management process?

A

Cost management plan, i.e., budget management plan or budget plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What costs should you estimate?

A
  1. Quality efforts
  2. Risk efforts
  3. PM’s time
  4. Project management activities
  5. Expenses for physical office spaces
  6. Overhead costs (management salaries, general office expenses, etc.)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What are the 4 types of costs?

A
  • Variable
  • Fixed
  • Direct
  • Indirect
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Variable costs

A

Costs that DO change with the amount of production or work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Fixed costs

A

Costs that DO NOT change as production changes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Direct costs

A

Costs that are directily attributable to the work on the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Indirect costs

A

Overhead items or costs incurred for the benefit of more than one project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Why is having a project schedule needed before you can come up with a budget?

A
  1. The timing of when you buy something may affect its cost
  2. You need to develop a time phased spending plan to monitor and control project expenditures so you know how much money will be spent during specific periods of time
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

When to use top down (analogous) estimating?

A
  • Strapped for time and money
  • When you have proper experience
  • Predictable projects
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

When to use bottom up estimating?

A
  • Not srapped for time and money
  • When you have detailed project activities
  • When you have proper info needed to manage and monitor and control costs
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Types of estimate ranges

A
  • Rough Order of Magnitude (ROM)
  • Budget
  • Definitive estimate
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Rough Order of Magniture (ROM) estimate

A
  1. Usually made during project initiating
  2. -25% to +75%
18
Q

Budget estimate

A
  • A more defined ROM estimate
  • -10% to +25%
19
Q

Definitive budget

A
  • More refined budget estimate
  • +/- 10%
  • or
  • -5% to 10%
20
Q

What are the ouputs of the Estimate Costs process?

A
  • Cost estimates
  • Basis of estimates (how you got the estimates)
21
Q

Steps to determine budget

A
  1. Activity estimates
  2. Work package estimates
  3. Control account estimates
  4. Project estimates
  5. Contingency reserves
  6. Cost baseline
  7. Management reserves
  8. Cost budget
  9. Compare figures to parametric estimates or to expert judgment
  10. Check cash flow
  11. Perform last reconciliation
22
Q

What does the Determine Budget process result in?

A

The scope baseline, including all funding requirements

23
Q

What can you do if a risk is no longer determined to be a threat?

A

Remove the associated contingency reserve from the cost baseline

24
Q

What does Earned Value Analysis utilize to measure project performance against?

A
  • Scope baseline
  • Schedule baseline
  • Cost basline
  • Better known as the performance measurement baseline
25
Q

Planned Value (PV)

A

As of today, what is the estimated value of the work planend to be done?

26
Q

Earned Value (EV)

A

As of today, what is the estimated value of the work actually accomplished?

27
Q

Actual cost (AC)

A

As of today, what is the actual cost incurred for the work accomplished?

28
Q

Budget at Completion (BAC)

A

How much did we budget for the total project effort?

29
Q

Estimate at Completion (EAC)

A

What do we currently expect the total project to cost?

30
Q

Estimate to Complete (ETC)

A
  • From this point on, how much more do we expect it to cost to finish the project?
  • ETC = EAC - AC
  • or
  • Reestimate
31
Q

Variance at Completion (VAC)

A
  • As of today, how much over or under budget do we expect to be at the end of the project?
  • VAC = BAC - EAC
32
Q

Cost Variance (CV)

A
  • CV = EV - AC
  • Negative = OVER budget
  • Positive = UNDER budget
33
Q

Schedule Variance (SV)

A
  1. SV = EV - PV
  2. Negative = BEHIND schedule
  3. Positive = AHEAD of schedule
34
Q

Cost Performance Index (CPI)

A
  • CPI = EV / AC
  • “We’re getting $___ worth of work out of every dollar we spend”
  • > 1 = GOOD
  • < 1 = BAD
35
Q

Schedule Performance Index (SPI)

A
  • SPI = EV / PV
  • “We’re progressing at ___% of the originally planned rate”
  • > 1 = GOOD
  • < 1 = BAD
36
Q

EAC to use when the original estimate was fundamentally flawed?

A

EAC = AC + Bottom up ETC

37
Q

EAC to use when no variances from the BAC have occurred, or if you will continue at the same rate of spending?

A

EAC = BAC / CPI

38
Q

EAC to use when current variances are thought to be atypical of the future?

A

EAC = AC + (BAC - EV)

39
Q

EAC to use when current variances are thought to be typical of the future and when project schedule constraints will influence the completion of the remaining effort?

A

EAC = AC + ( (BAC - EV) / (CPI x SPI) )

40
Q

To Complete Performance Index (TCPI)

A
  • To stay within the budget, what rate we do need to meet for the reamining work?
  • TCPI = (BAC - EV) / (BAC - AC)
  • > 1 = BAD
  • < 1 = GOOD
41
Q

Tips regarding CV, SV, CPI, and SPI

A
  • EV comes FIRST!
  • If the formula relates to cost, use AC
  • If the formula relates to schedule, use PV
  • Negative is bad and positive is good (also applies to VAC)
    • ^ Opposite is true for TCPI